/
Amendments to the Public Works Contracts Amendments to the Public Works Contracts

Amendments to the Public Works Contracts - PowerPoint Presentation

karlyn-bohler
karlyn-bohler . @karlyn-bohler
Follow
395 views
Uploaded On 2017-06-24

Amendments to the Public Works Contracts - PPT Presentation

7 March 2017 Amendments to the PWCs Primacy of Bill of Quantities Specialist Work Packages New Dispute Management Procedures Bill of Quantities A return to Primacy Guidance Note 153 ID: 563091

contract works contractor specialist works contract specialist contractor main specialists sum pricing boq item employer requirements reserved tender document

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "Amendments to the Public Works Contracts" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

Amendments to the Public Works Contracts

7 March 2017Slide2

Amendments to the PWC’s

Primacy of Bill

of Quantities Specialist Work Packages New Dispute

Management ProceduresSlide3

Bill of Quantities – A return to Primacy

(Guidance Note 1.5.3)Slide4

The Need for Change

Schedule Part 1K17 – No

Errors between Works Requirements and

BoQ at Contractor’s riskMeasures and descriptions were inadequateAccuracy of drawings were not tested at tender stageContracts being tendered not fully designed with an under-measured/under-descriptive BoQPrice certainty?!Slide5

Making Contracts “With Quantities”

Fully measured

BoQ is mandatory for Employer Designed ProjectsEmployer retains the risk of errors in the BoQ

The BoQ is the primary reference for pricing purposes – no other document is to be included in the Pricing DocumentSlide6

Inconsistencies - Cl1.3.4

Inconsistencies

between the Works Requirements and the Pricing

Documentresolved by an instruction from the ER.Works Requirements takes precedence and a Compensation Event may arise in accordance with the Schedule, Part 1K(17).Slide7

Resolution of Inconsistencies Works

Item

Works Item

described in the Works Requirements but not in BoQThe Contractor will be required to complete the Works Item, if so directed

by the

ER, and

shall be

entitled

to an

adjustment to the Contract

Sum

The ER may direct the Contractor

not to

complete the Works Item, and there shall be

no adjustment

to the Contract SumSlide8

Resolution of Inconsistencies Works Item

Works

Item described in

BoQ but not in the Works RequirementsThe ER may direct the Contractor to complete the Works Item but the Contractor shall have no entitlement to an adjustment to the Contract SumThe ER may direct the Contractor not to complete the Works Item, and the ER or Employer

shall be

entitled to adjust the Contract SumSlide9

Resolution of Inconsistencies Quantities

B

oth the Works Requirements and BoQ include the Works Item but an inconsistency in the quantities exists.

If the ER directs the quantity shown in the Works Requirements to be completed, the Contract Sum may be adjustedIf the ER directs the quantity shown in the BoQ

is to be completed, the Contract Sum

shall not

be adjustedSlide10

Other Risk Allocation

Overall risk allocation in Schedule 1K must be considered e.g.

‘unforeseeable ground conditions’ is contractor risk

Unforeseen ground encountered resulting in quantities of work increasing or decreasingK(19) overrules K(17) and a Compensation Event shall not arise The BoQ Preliminaries Section shall detail the allocation of risks, as per Schedule 1KSlide11

Related Issues

Clause 4.4 – ER Communications

Clause 4.5 – InstructionsClause 4.11 – Contractor to request instructionClause 10.3 – condition precedent remainsSchedule 1K (1), (9), (17) – €500 Slide12

Specialist Works ProcurementSlide13

Specialists and Employer

Appointment subject to varying levels of involvement

Little or no engagement – e.g. tax compliance, i.e. sub contractors

not specialistsSets pre-qualification standardsDirect tendering of specialist worksSuccessful specialist tenderer → novated to contractor

Naming successful specialist

appointed by contractor as sub-contractor (nomination?)Slide14

When should named Specialists be considered?

Early engagement is necessary,

Detailed design required for Works RequirementsSpecialist required to undertake portion of their works in advance of main contractor agreement

Value of single specialist works exceeds 15% of overall pre-tender estimate for the worksNot possible to accurately define the specialist works enable it to be tendered as part of main contractSlide15

Types of Specialist

Employer designed works:

Reserved SpecialistNovated Specialist

Contractor designed works:D&B SpecialistsSlide16

The Appointment Process for Reserved SpecialistsSlide17

Shortlist main

contract

and

specialist candidates

Main Contract tender deadline

Identify successful Main Contract tenderer

Reserved Specialist tender deadline

Identify successful Reserved Specialist tenderer

Award contract to successful tenderer for main contract

Main Contract tender

1

Evaluate tender

3

Specialist tender

2

Standstill

Evaluate tender

4

Standstill

5

Contract

admin

6Slide18

Reserved Specialists

Restricted procedure used to pre-qualify both

main contractors; andspecialistsSpecialist contract in N

N CIFSlide19

Novation – Specialists

Employer tenders the specialist work

Informs tendering specialists that its intention is to novateMust provide novation agreement and collateral warranty

Specialist and contractor enter contractForm of contract dependent on CWMF guidanceSlide20

Novation – Main Contractor

Employer tenders for Main Contractor

Informs Main Contractor of novationNovation agreementIdentity of specialist

Programme for novated specialist worksSlide21

D&B

Specialists

Extent of contracting authority’s involvement:Sets appropriate pre-qualification criteria/standards that proposed specialists must meetEstablishing pre qualification panel of specialists

Novation – where specialist is required in advance of contractor appointmentSlide22

Main Contract PricingSlide23

Main Contract Pricing

Schedule Part 1F(iii) sets out the named Specialist Works Packages:

Reserved Sums and Contract S

ums (for Novated Specialists) are to be provided in the Pricing DocumentPricing Documents (unpriced) for each of the named Specialist works packages should be provided in the main contract Pricing DocumentSlide24

Main Contract Pricing

Pricing Document must include items to allow for the pricing of the following:

General attendances – lump sum itemsSpecial attendances defined as required – lump sum items

Contractor’s management, risk acceptance and indirect overhead costs – lump sum itemContractor’s profit – percentage of Specialists Reserved/Contract SumLump sum items priced less than zero will be deemed to be zero and negative percentages will be treated as zero per centSlide25

New

Dispute Management ProceduresSlide26

The Dispute Management

Procedure

The Project Board:Members stated in Schedule Part 1A1-3 members nominated from each side

Function of Project Board:review disputes referred to Clause 13.110.5.4 and 10.5.5 determinations onlyNo authority to review any other such dispute or may ariseMust have capacity and authority to negotiate binding agreementsSlide27

The Dispute Management

Procedure

Project Board must meet at least every 60 days to review disputes referred to itAll binding agreements reached must be signed by the Employer and the Contractor

If no agreement is reached, the Board shall on the next working day, notify the parties of the failure to resolve disputeSlide28

Standing Conciliator

When

Contract Value is in excess of €10mAppointed by the Parties

When Contract Value is below €10mEmployer has option of requiring a Standing Conciliator to be appointed by the PartiesCan chair the Project Board and advise/draft binding agreementsReserved sum shall be included in the Pricing Document – 50% of feeSlide29

Questions?

Pauric

Marray

Pauric.Marray@QuiggGolden.com

London

+44 (0)20 7022 2192

London@QuiggGolden.com

Dublin

+353 (0)1 676 6744

Dublin@QuiggGolden.com

Belfast

+44 (0)28 9032 1022

Belfast@QuiggGolden.com

Jeddah

+966 (0)2 651 82 22

Jeddah@QuiggGolden.com