/
MICROSOFT PROJECT MICROSOFT PROJECT

MICROSOFT PROJECT - PowerPoint Presentation

karlyn-bohler
karlyn-bohler . @karlyn-bohler
Follow
418 views
Uploaded On 2017-05-25

MICROSOFT PROJECT - PPT Presentation

MODULE 6 RESOURCE LEVELING CLASS DETAILS Jeremy Callinan Wednesday 6315 Friday 6515 Wednesday 61015 All sessions 1230 pm until 430 pm Overview of classes MODULE 1 INTRO ID: 552056

resources leveling overallocated module leveling resources module overallocated project level resource priority task work tasks view click

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "MICROSOFT PROJECT" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

MICROSOFT PROJECT

MODULE

6 – RESOURCE LEVELINGSlide2

CLASS DETAILS

Jeremy Callinan

Wednesday, 6/3/15

Friday, 6/5/15

Wednesday, 6/10/15

All sessions: 12:30 pm until 4:30 pmSlide3

Overview of classes

MODULE 1 – INTRO

MODULE 2 – EXAMPLE PROJECT : BUILD A HOUSE – MAKING TASKS

MODULE 3 – SETTING UP YOUR PROJECT FILES – WORKING TIME & OTHER OPTIONS

MODULE 4 -

TASKS &

PREDECESSORS

MODULE 5 – SETTING UP RESOURCES

MODULE 6 – RESOURCE LEVELING

MODULE 7 – CRITICAL PATH

MODULE 8 – REPORTING

MODULE 9 – OTHER EXAMPLE PROJECTS

MODULE 10 – PROJECT SERVER

MODULE 11 – PROJECT MANAGEMENT TECHNIQUES

MODULE 12 – OTHER EXAMPLE

PROJECTS

Module 13 – TRACKING PROGRESS

Note: module 9 also has a glossarySlide4

Leveling

Resource leveling is a way to fix resource 

overallocation

. Generally, resources are leveled in two ways:

By delaying a task until the assigned resource has time to work on it.

By splitting a task so that part of a task is done when planned and the rest of it is done later when the assigned resource has time.Slide5

Leveling

Overallocated

Resources

The basic how-to:

On the

Tools

menu, click

Level Resources

, and then choose the leveling options you want.

Click Level Now.2013 – Resources – Level AllSlide6

Leveling Overallocated Resources

Under

View

>

Resource Sheet

,

resources

in

red would be over allocated

Under the Tools menu > Level Resources, there’s this dialog box (next slide…):In 2013 - Slide7

Leveling

Overallocated

Resources

If you’re leveling over and over

Level within a date range when your project is underwaySlide8

Leveling

Overallocated

Resources

If you don’t see any

overallocated

resources, make sure “Day by Day” is selected here:

So, if it’s a more finite value, Project won’t bother highlighting the person in red, if, let’s say, they’re

overallocated

by an hour….Slide9

Leveling

Overallocated

Resources

Determines priority.

ID Only: numerically higher ID numbers get delayed first (i.e. items you entered later in the project.

Standard delays tasks according to their predecessor relationships, start dates, task constraints, slack, priority, and IDs.

Priority, Standard… (next slide)Slide10

Leveling Overallocated

Resources

“Priority, Standard” uses Task Priority – a numeric ranking between 0 and 100 that indicates the task’s appropriateness for leveling. Tasks with the

lowest

priority are leveled or split first.Slide11

Leveling

Overallocated

Resources

Level only within available slack

A good thing, if you don’t want Project to extend the project finish date.

If it’s okay to extend the project finish date, clear this check box.Slide12

Leveling Overallocated Resources

You might still see some people in red, even though their overallocation icons have disappeared.

They’re overallocated hour by hour or minute by minute, but not day by day.Slide13

Leveling

Overallocated

Resources

Leveling can adjust individual assignments on a task

It’ll delay work for the resource, or split work, that is, if you’ve got the next checkbox also checked, “Leveling can create splits in remaining work.”Slide14

Leveling Overallocated Resources

Once you’ve got all of your settings selected in the Resource Leveling dialog box, click

Level Now

. It’ll ask you if you want to level selected resources or the entire pool. Choose one, and click

OK

.Slide15

Leveling

Overallocated

Resources

In the Leveling Gantt View, you can view the before and after of your leveling.

View

menu >

More Views

>

Leveling Gantt

> Apply.