Reduction Reduction

Reduction - PowerPoint Presentation

karlyn-bohler
karlyn-bohler . @karlyn-bohler
Follow
470 views
Uploaded On 2016-05-06

Reduction - PPT Presentation

in Downtime via Interlocking Date 3 rd March 2012 A tripping occurred since the Areva panels had a tripping command system if the DC supply failed This was removed by removing that function from the panel and a alarm using a contractor with a reset operation was ID: 308419

downtime hooter time future hooter downtime future time saving power ups fed savings failure avoided fault reset tripping

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "Reduction" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

Reduction in Downtime via Interlocking

Date: 3rd March 2012

A tripping occurred since the Areva panels had a tripping command system if the DC supply failed.This was removed by removing that function from the panel and a alarm using a contractor with a reset operation was madeFor future purposes a downtime of 60 minutes was avoided.

1Slide2

How did the failure happen?

2Slide3

K1 (N.C.)

Push Button

(

N.O)

K2 (N.O

.)

a1

b1

g

h

K2

K1

MCB

Output

Fed by

UPS Power

Hooter

SLD of the Hooter Circuit

K1 (N.C.)

K2 (N.C.)

e

f

e1

f1

Fed by

UPS Power

3Slide4

Load loss per hour

70,000

INRBreakdown on transmission line will create breakdown for hours:60

minutes 

 

Total savings

70,000.00

INR

Savings Calculations

Now if the DC fails the Hooter will show the fault.

There is also a ‘Reset Button’ to accept the fault and bring it back to normal condition.

This is not a one time saving it is applicable for the future also.

Now Downtime of Unit 1, 2, 5 and

Gyaanpeeth

from DC failure can be avoided.

Hooter would run and action can be taken in time.

*

This is not a one time saving. For future there will be no downtime due to this reason.

4