AT RISK IN GREENSBORO NORTH CAROLINA INTRODUCTION Team City of Greensboro HDR Constructors Garney Capital Improvement Needs Townsend WTP TZO WRF CMAR vs Alternate Delivery Methods ID: 786153
Download The PPT/PDF document "UTILIZING CONSTRUCTION MANAGER" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.
Slide1
UTILIZINGCONSTRUCTION MANAGER AT RISK IN GREENSBORO, NORTH CAROLINA
Slide2INTRODUCTION
Team
City of Greensboro
HDR Constructors
Garney
Capital Improvement Needs
Townsend WTP
TZO WRF
CMAR
vs.
Alternate Delivery Methods
Slide3PROJECT BACKGROUND
Construction Manager at Risk
(CMAR)
in Greensboro
Owner Objectives / Goals
RFQ Process
CM Selection
Design and Partnering
Designer and CM
Pre-Construction Timeline
Slide4DESIGN-BID-BUILD Traditional Baseline for Project DeliveryProven Procurement SolutionDIFFERING DELIVERY METHODS
PROCESS
Design-Bid-Build ADVANTAGESCompetitively BidSeparate ContractsSelf-Performance CapabilitiesTime-Tested Process / Used in All StatesMaximizes Owner InputDIFFERING DELIVERY METHODS
Slide6Design-Bid-Build DISADVANTAGESLimited Collaboration / TeamworkEliminates Qualifications-Based SelectionNo Contractual RelationshipAdversarial ApproachLow BidValue EngineeringDesign DIFFERING DELIVERY METHODS
Slide7DESIGN-BUILDDesign and Construction Fixed PriceBased on Concept Design and/or Description from Procurement DocumentsDIFFERING DELIVERY METHODS
CONSTRUCTION
PROCESS
Slide8Design-Build ADVANTAGESTeam Qualifications-Based SelectionAccelerated Schedule Public Acceptance for Lump-Sum ContractSelf-Performing Contractor Controls ScheduleKnown Performance CriteriaFinal GMPDIFFERING DELIVERY METHODS
Slide9Design-Build DISADVANTAGESLonger Procurement ProcessEliminates or Reduces Participation in Procurement ProcessInefficient Use of Municipal Funds and Staff Time Bidding ProcessDIFFERING DELIVERY METHODS
Slide10CMARQualifications-Based SelectionContractor Engaged Early in Design PhaseTwo-Contract Relationship DIFFERING DELIVERY METHODS
CONSTRUCTABILITY REVIEW
CONSTRUCTION
PROCESS
CMAR ADVANTAGESOwner Control of Project Goals Provides for Value Engineering (VE) and Constructability ReviewsContractor-Led EstimatesReduces Overall RiskSchedule AccelerationCompetitive Selection DIFFERING DELIVERY METHODS
Slide12CMAR DISADVANTAGESEngineer’s Estimate for Initial Project CostsPotential Cost Increase with VE and Constructability Review Preconstruction Services CostDouble-BondingSeparate ContractsIncreased Design Duration DIFFERING DELIVERY METHODS
Slide13TZO WATER RECLAMATION FACILITYRetrofitting Existing Anthracite Media Filters with new Aqua-Aerobic Systems Diamond Cloth Filter EquipmentNew Chlorine Contact TankChemical System UpgradesSite-Wide Stormwater ImprovementsElectrical Improvements
Slide14PRECONSTRUCTION AT TZOEstimates at 90% Document PhaseDevelopment of CPM Schedule Executed Mentor / Protégé Program with Local MBE, SRSM/WBE Work Packages
Slide15TZO CHALLENGES AND BENEFITSChallenges & BenefitsDividing Competitive Work PackagesFlexibility with NCDEQ Filter Construction Sequencing - Eliminating Option to Bypass FiltersIncreasing Minority ParticipationConstructability / Cost Review at 90%
Slide16TZO SCHEDULEWork PackagesConstraints of Existing Plant OperationsMinimal Shutdowns / Uninterrupted Access
Effluent Filter Modifications
One Bank of Filters Off-Line Per Time
Slide17TOWNSEND WATER TREATMENT PLANTLime / PAC FacilityFlocculation & Sedimentation BasinsFilter UpgradesBackwash Process UpgradesMAY 16
–
DEC 17
JAN 15
–
DEC 15
PRECONSTRUCTION
CONSTRUCTION
Slide18TOWNSEND PRECON METHODOLOGYCost Models60% DocumentsVEEarly Project Schedule DevelopmentInput from O&M Staff, Engineer and SubcontractorsDetermines General Conditions DurationSubcontracting PackagesFacilitate Area MarketClear Scope Delineation
Slide19TOWNSEND CHALLENGES/BENEFITS - GMPOpen Book EnvironmentCollaborative Preconstruction WorkshopsProactive Project Execution Planning - Plant Production RestrictionsConstructability and Value Analysis
Procurement (Buy-Out) Plan
Start-Up and Commissioning Plan
Slide20TOWNSEND CHALLENGES/BENEFITS – M/WBEAspirational GoalsCommitment to M/WBE ProgramOutreach and Communication with Interested IndividualsProvide Guidance during Bidding, Contracting and Construction Phases
Ensure Parties Follow City’s Guidelines for Implementation
Slide21CMAR AT TOWNSEND WTPQualifications-Based SelectionBetter Control of Construction Implementation of M/WBE ProgramCollaborative and Team-Oriented Project DeliveryLess Adversarial Construction Environment
Slide22TOWNSEND – ENGAGING THE CMAR EARLY60% Design DocumentsUnderstand Project BudgetAbility to Value Engineer ProjectEarly Development of CPM
Slide23TOWNSEND – CHALLENGES/BENEFITS - MOPOMaintenance of Plant Operations (MOPO)Ability to RedesignIdentify Schedule ConstraintsMinimize Timeframe for OutagesAbility to Understand Construction Sequencing
Slide24TOWNSEND PROJECT SCHEDULEEarly Development of CPM ScheduleIdentified SequencingIncorporated Peak TimesSequenced MOPOs
Slide25OWNER CHALLENGES - LEGALContract Vehicle State Standard Contract vs. CMAA vs. AIAPrequalification ProcessState Statute RequirementsCriteria to Prequalify Target Audience for the Process
Slide26OWNER CHALLENGES – M/WBEDisparity StudyHispanic Participation - Goal AchievementSetting of GoalsGMP Estimate or Trade PackagesBid ResponsivenessPrequalification vs. BidsHUB Understanding of Formal Bid Process
Slide27OWNER CHALLENGES – M/WBE (CONT.)Mentor – ProtégéCity ProcedureGoal AchievementNew Process for Evaluating Good FaithCM Level and Sub-Tier LevelMandatory PrequalificationParticipation ResponsivenessEducation
Slide28OWNER CHALLENGES - DESIGNDesign Completion Level60% Townsend vs. 90% TZOSelf-PerformanceState StatuteTeam CohesivenessExperience Receptiveness to FeedbackDesign Review ProcessConstructability and VE
Slide29GMP Finalization / Sub-Contract ExecutionBudgeting Value Engineering Construction PhaseNTP and DurationNEXT STEPS
Slide30M/WBE UnderstandingBudgeting / Value EngineeringPrequalification ProcessStaff Understanding of CMAR ProcessEducate Key Departments / StaffDevelop Procedures to Support Delivery Method KEY TAKEAWAYS
Slide31QUESTIONS?