/
Christopher Payne, PE, CCM Christopher Payne, PE, CCM

Christopher Payne, PE, CCM - PowerPoint Presentation

kittie-lecroy
kittie-lecroy . @kittie-lecroy
Follow
358 views
Uploaded On 2018-11-09

Christopher Payne, PE, CCM - PPT Presentation

Mairav Mintz PE CCM Omoniyi Ladipo CCM CCP EVP  2018 Project Management Symposium So your schedule says your project will finish on time is that all it is really telling you Learn how common distortions and practices make CPM schedules less useful than they should be ID: 723468

review schedule cost project schedule review project cost schedules projects progress research combined time cpm performance critical finish late

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "Christopher Payne, PE, CCM" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

Christopher Payne, PE, CCMMairav Mintz, PE, CCMOmoniyi Ladipo, CCM, CCP, EVP 2018 Project Management Symposium

So your schedule says your

project will finish on time . . .

is that all it is really telling you?Slide2

Learn how common distortions and practices make CPM schedules less useful than they should be.Understand earned value metrics in cost-loaded schedules.Examine insights gained from research of thousands of cost-loaded schedules.

Understand distinction between “schedule delay” (days) and “progress delay” (earnings).

See practical applications of these concepts.

Learning ObjectivesSlide3

Projects are often behind and finish late.Owners/construction managers consistently misinterpret schedules.Combined schedule and EVM review can help.Our research findings support this.

Our project experience supports this.

What We KnowSlide4

Is the critical path reasonable?Does the schedule show negative float?Is the project predicted to finish on time?Is progress recorded accurately?Are schedule revisions explained and justifiable?

The Obvious Signs in CPM Schedule ReviewSlide5

We conducted schedule review and EVM in tandem on a number of our projects.Our observations confirm that the best determination of project health is through the use of concurrent measurement of progress in time and earnings.

CPM Schedule Review & EV AnalysisSlide6

Origin of Combined cpm Review & EVm AnalysisSlide7

A result of a contract requirement.Project team understood the benefits resulting from looking beyond the critical path projection of completion and known distortions

How Has Combined Review Emerged?Slide8

Cpm schedule reviewSlide9

Owners examine contractors schedules to:Determine whether project is on, behind, ahead of plan through current critical and near critical path review.Forecast when the

project will be

completed through current critical path

review.

CPM Schedule ReviewSlide10

Some owners examine contractor schedules to:Review resource and cost loading plan, earnings and projections

Construction industry has been slow to adopt

Requires detailed updates to reflect

accurate progress.

Requires detailed

review of baseline

plan versus previous

and current updates.

CPM Schedule ReviewSlide11

COMBINED Cpm schedule review and EV analysisSlide12

Owners develop and analyze the PMBPMB: A time-phased budget plan for accomplishing work, used to measure contract performance. Developed using the data in the Baseline Schedule.

Performance Measurement BaselineSlide13

Owners use parameters such as:Planned Value (PV) or Budgeted CostEarned Value (EV)

Actual Cost (AC)

Derive EV schedulemetrics and

cost metrics 

EVM ParametersSlide14

EV Schedule Metrics:Schedule Variance (SV)Schedule Performance Index (SPI)EV Cost Metrics:

Cost Variance (CV)

Cost Performance Index (CPI)

Estimate at

Completion (EAC)

EV AnalyticsSlide15

Project examples and our observations Slide16

Earned Schedule and Actual TimeSlide17

Budgeted costs vs. EV (S curves) were very effective illustrations of

progress.

EV curve for overall project showed overall

performance.

EV curves for subsets of

project revealed more

details about performance.

ObservationsSlide18

As time progressed, and work fell behind the plan, the S curves became steeper.Progress delay (AT-ES) also increased. Progress delay based on the critical path was sometimes more optimistic than the progress delay (AT-ES).

Schedule review and EV analysis used

concurrently to predict performance.

ObservationsSlide19

Tracked earned vs. planned values based on early, late, and average dates.Used average dates to determine performance

Late dates are too

late to course correctEarly dates don’t

consider float

ObservationsSlide20

Focused on monitoring work on the critical/near critical paths.Tracked earned vs. planned values

separately for:

Trades.Installation.

Procurement/

Level of Effort.

Change orders.

ObservationsSlide21

Tracked remaining work effort for trades against remaining time to planned completionEffective in projecting estimate to complete (ETC).Helped contractor

re-plan as needed.

ObservationsSlide22

Project schedule contained too much float.  Contractor’s early completion schedule was unrealistic – confirmed by S curves.The continuing erosion

of float month after

month resulted in

S curves that were

progressively less

achievable.

ObservationsSlide23

Benefits of combined reviewSlide24

Alerts project team to project risks

Facilitates informed decision making

Enhances project team collaboration

Improves forecasting capabilities.

Benefits of Combined ReviewSlide25

Provides historical data for future projects.Provides lessons learned for future projects.

Scalable and

valuable for many

sizes and types

of projects.

Benefits of Combined ReviewSlide26

Independent research project by MBP.Are there common factors we can identify in looking at many projects and their schedules?

Are there common indications of trouble that can be observed by looking beyond the obvious signs?

Given Benefits of Combined Review, We Launched a Broader StudySlide27

Our research and findingsSlide28

Reviewed 128 projects of various types.Reviewed more than 2,500 schedules.Strictly used cost-loaded schedules.Converted all schedules to a common base of percentage time and percentage cost.

Our ResearchSlide29

The “crystal ball” of a CPM schedule is often broken.There is no “point of no return” in terms of schedule slippage. But…There is no “out of the woods” point, either!

In other words, projects can fail at any point.

Is there a project tipping point?Slide30

Earned Schedule and Actual TimeSlide31

We accept a poor baseline schedule…Late earnings too late.Late performance too steep. How realistic?

Research shows many

schedules exhibit unrealistic aspects.

Large float values

The

First

Crack in the Crystal BallSlide32

We look at the updates in the wrong way…We ignore EVM metrics in schedule updates.We zero in on projected end date/minimum float value.

We should look for the trend of earnings.

Our research shows: a “persistent delusion” on projects that finish late.

The

Second

Crack in the Crystal BallSlide33

Look for:

Underperformance compared to plan.

ES/AT vs. Projected

Finish/Planned Finish.

These should be

similar.

AT - ES is “progress

delay”.

Projected finish vs.

Planned finish is

“schedule delay”.

The

Second

Crack in the Crystal BallSlide34

We fail to consider, "Can it be done?"In baselines or updates, be very skeptical of steep sloping curves.J-curve or S-curve

Max slope? Recommend no more than 4

The Crystal Ball is Broken in halfSlide35

Research – Huge Slope Variations BadSlide36

Weak work breakdown structure, poor scheduleand cost loading pose

difficulties.

Lack of scheduling and EVM capabilities.Inaccurate specifications.

Cost of EVM – scalable.

Subjective interpretation of EVM metrics.

Challenges of Combined ReviewSlide37

The research findings have been borne out on several of our projects.The findings cannot be ignored.Adapt our practice of schedule management to address what we have learned.

Transform the way we think about progress.

Changing the Way we Think Slide38

Contact Niyi Ladipo at

nladipo@mbpce.com or 703-641-9088

Thank You!