Critical Path Method Kegiatan Predecesor Waktu A 8 B 4 C A 10 D A 2 E B 5 F DE 3 Critical Path Method 1 0 0 2 8 8 3 4 10 4 10 15 5 18 18 A8 C10 D2 B4 ID: 658045

method path cost critical path method critical cost 100 total waktu normal aktivitas ongkos kemiringan 150 dan 400 diatas

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "Critical Path Method Eko Hartanto" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

Critical Path Method

Eko HartantoSlide2

Critical Path Method

Kegiatan

Predecesor

Waktu

A

-

8

B

-

4

C

A

10

D

A

2

E

B

5

F

D,E

3Slide3

Critical Path Method

1

0

0

2

8

8

3

4

10

4

10

15

5

18

18

A/8

C/10

D/2

B/4

E/5

F/3

Total Cost : 100+150+50+100+100+80 = 580Slide4

Critical Path Method

Aktivitas

Normal

Dipercepat

Waktu

Ongkos

Waktu

Ongkos

A

8

100

6

200

B

4

150

2

350

C

10

100

5

400

D

2

50

1

90

E

5

100

1

200

F

3

80

1

100

Data waktu dan ongkos masing-masing kegiatan pada gambar diatas adalah sebagai berikut :Slide5

Critical Path Method

Analisis dari persoalan diatas akan tergantung pada kemiringan garis ongkos dan waktu untuk berbagai aktivitas. Kemiringan garis dapat dihitung :

Cc - Cn

Kemiringan =

Dc – Dn

Dimana

:

- Cc = Cost crash

- Cn = Cost normal

- Dn = Duration normal- Dc = Duration crash

Aktivitas

Kemiringan

A

50

B

100

C

60

D

40

E

25

F

10Slide6

Critical Path Method

1

0

0

2

7

7

3

4

9

4

9

14

5

17

17

A/7

C/10

D/2

B/4

E/5

F/3

Total Cost : 580+50 = 630Slide7

Critical Path Method

1

0

0

2

6

6

3

4

8

4

9

13

5

16

16

A/6

C/10

D/2

B/4

E/5

F/3

Total Cost : 630+50 = 680Slide8

Critical Path Method

1

0

0

2

6

6

3

4

7

4

9

12

5

15

15

A/6

C/9

D/2

B/4

E/5

F/3

Total Cost : 680+60 = 740Slide9

Critical Path Method

1

0

0

2

6

6

3

4

6

4

9

11

5

14

14

A/6

C/8

D/2

B/4

E/5

F/3

Total Cost : 740+60 = 800Slide10

Critical Path Method

1

0

0

2

6

6

3

4

5

4

9

10

5

13

13

A/6

C/7

D/2

B/4

E/5

F/3

Total Cost : 800+60 = 860Slide11

Critical Path Method

1

0

0

2

6

6

3

4

4

4

9

9

5

12

12

A/6

C/6

D/2

B/4

E/5

F/3

Total Cost : 860+60 = 920Slide12

Critical Path Method

1

0

0

2

6

6

3

4

4

4

9

9

5

11

11

A/6

C/5

D/2

B/4

E/5

F/2

Total Cost : 920+(60+10) = 990Slide13

Critical Path Method

Aktivitas

Predesesor

Normal

Percepatan

Time

Cost

Time

Cost

A

-

4

210

3

280

B

-

8

400

6

560

C

A

6

500

4

600

D

A

9

540

7

600

E

D

5

500

2

1100

F

B,C,E

5

150

4

240

G

F

3

150

2

400

H

D

9

600

6

750

Dari tabel aktivitas diatas, hitung :

1). Waktu penyelesaian normal dan ongkosnya !

2). Waktu penyelesaian tercepat dan ongkosnya !