/
EAR2 Beam Line EAR2 Beam Line

EAR2 Beam Line - PowerPoint Presentation

kittie-lecroy
kittie-lecroy . @kittie-lecroy
Follow
398 views
Uploaded On 2016-05-01

EAR2 Beam Line - PPT Presentation

Report on the Status C Weiss 28112013 EAR2 Beam Line Report on the Status 1 28112013 EAR2 Beam Line Report on the Status 2 Beam Dump EAR2 Exp Hall 2 nd Collimator Magnet Pit Shielding ID: 300799

ear2 beam 2013 line beam ear2 line 2013 status report collimator shielding vacuum service chamber gallery target concrete filter section capture dump

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "EAR2 Beam Line" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

EAR2 Beam LineReport on the Status

C. Weiss

28.11.2013

EAR2 Beam Line - Report on the Status

1Slide2

28.11.2013EAR2 Beam Line - Report on the Status

2

Beam Dump

EAR-2 Exp. Hall

2

nd

Collimator

Magnet

Pit Shielding

Target

New Area

Existing Area

1

st

Collimator

Filter Box

S

hielding

Service Gallery

ISR Tunnel

h

[m]

0

9.8

18.1

24.4

EAR1Slide3

Beam Line - Design Considerations

Exchangeable components in order to allow new target installation (2018).

Minimum background to the experiment.

Maximum neutron fluence to the

experiment.Acceptable dose rate in working area close to beam

line (0.5 mSv/h in ISR

).

Maximum

flexibility for experiment

installation (capture &

fission setup

).Automatic alignment with neutron beam.

Feasibility :-)!28.11.2013EAR2 Beam Line - Report on the Status

3Slide4

Vacuum chambers

28.11.2013

EAR2 Beam Line - Report on the Status

4Slide5

28.11.2013EAR2 Beam Line - Report on the Status

5

Special vacuum chamber at the beam dump with inserted shielding material (avoid backscattered neutrons).

Target

Special vacuum chamber at the 2

nd

collimator, to allow the insertion of the collimator and

to optimize shielding.

Special vacuum

chamber to get as close as possible to the

target and allow material irradiations close to target.

SiMon

: carbon

f

ibre

v

acuum

chamber(LNS / INFN).Slide6

n_TOF Target from the Top

28.11.2013

EAR2 Beam Line - Report on the Status

6

Opening on top of the spallation target structure

 EAR2 TOF tube goes through there Slide7

Vacuum Chamber 18.9 m total

length:‘Triangular’ shape for the first 1.1 mCylindrical shape (d = 317.9 mm) from top of target onwards

Window: 1.5 mm Al, concave shape 12 mm gap of air btw. target and window

28.11.2013

EAR2 Beam Line - Report on the Status

7Slide8

Production on-going

28.11.2013

EAR2 Beam Line - Report on the Status

8

Vacuum chamber 1Slide9

28.11.2013

EAR2 Beam Line - Report on the Status

9

New

guidings

for irradiation on target

Basket Ø160

Vacuum chamber 1Slide10

Collimators

28.11.2013

EAR2 Beam Line - Report on the Status

10Slide11

Collimators

Decisions on beam parameters:

n_TOF

coll. meeting May – capture beam

n_TOF tech. meeting in Sept. – fission beam

2nd collimator: 2 m Fe + 1 m PE (with B or Li)1

st

collimator: 1 m Fe

28.11.2013

EAR2 Beam Line - Report on the Status

11

Measurement

Collimator & Shape

Inner Diameter [mm]Capture2nd: conicald2 = 20

d1 = 691st: cylindricald0

= 200Fission2nd: conicald2 = 85.6d1

= 124.6Slide12

1st Collimator

28.11.2013

EAR2 Beam Line - Report on the Status

12

Shutter replaced with vacuum chamber

Collimator

1:

1 m Fe

d

inner

= 200 mm

(will be inserted in vacuum chamber 1)

MagnetSlide13

PE

(+B or Li)

c

ore

260 kg

1.5 m

2 m

1 m

Steel core

2 t

Steel vacuum vessel

5 t

28.11.2013

EAR2 Beam Line - Report on the Status

13

2

nd

Collimator Slide14

28.11.2013

EAR2 Beam Line - Report on the Status

14

2

nd

Collimator

Multiple-step design

as conical is not

machinable

!Slide15

Beam line shielding

28.11.2013

EAR2 Beam Line - Report on the Status

15Slide16

Additional shielding

layer

on the floor of EAR2

for background reduction.

Steel balls above service gallery.

1.5 m concrete right above service gallery.

Fe

collar at the level of 1

st

collimator.

Concrete

around beam pipe up to service gallery.

h

[m]

0

9.8

18.1

Target

Service GallerySlide17

Service Gallery

Section 1

Section 2

Section 3

Section 4

Shielded Pit

Section 1

Section 2

Centering

pins

Section 3

Section

4

28.11.2013

EAR2 Beam Line - Report on the Status

17

TargetSlide18

New Concrete

S

hieldings

28.11.2013

EAR2 Beam Line - Report on the Status

18Slide19

Steel forms for concrete taps

 Green light for production

28.11.2013

EAR2 Beam Line - Report on the Status

19

Concrete Tap

B

locksSlide20

1.5 m

2 m

1 m

St steel balls 3 t (0.6m³)

Concrete 1.1 t

28.11.2013

EAR2 Beam Line - Report on the Status

20

Shielding

above

Service GallerySlide21

Service Gallery - Magnet and filter box

28.11.2013

EAR2 Beam Line - Report on the Status

21Slide22

Magnet and Filter Box

28.11.2013

EAR2 Beam Line - Report on the Status

22

Filter Box

Permanent Magnet: 0.2 Tm

r

eady by end 2013

1

st

collimator in ‘storage position’

Ducts for steel ball removalSlide23

Filter Box

*

Proposed by

E.

Berthoumieux

, F. Gunsing

and C.

Lederer

28.11.2013

EAR2 Beam Line - Report on the Status

23

Filter

EAR1

AvailableEAR2Proposedd [mm]Cd*

✗0.5Ag

✔0.5W

*✔0.8

Mo*

1Co*

0.25Na*

✗10Al*

✔ / ✔

30 / 80S*✗

80

C

60Slide24

Filter Box

EAR2: 276 mm available length, each filter:

350 x 350 mm

2

28.11.2013

EAR2 Beam Line - Report on the Status

24

Filter

EAR1

Available

EAR2

Proposed

d [mm]

Cd*✗?0.5

Ag

✔✔0.5

W*✔

0.8Mo

*

✔1Co*

✔✔

0.25Na*

✗✔10

Al*

/

✔ / ✗

30 / 80S*

80C

?

60Slide25

Filters: Transmission Probabilities

28.11.2013

EAR2 Beam Line - Report on the Status

25Slide26

Beam dump

28.11.2013

EAR2 Beam Line - Report on the Status

26Slide27

Beam Dump28.11.2013

EAR2 Beam Line - Report on the Status

27

Design constraints:

Background situation in EAR2 (

n_TOF

)

Dose rate outside (Radioprotection)

Maximum weight (Civil

E

ngineering)

Outer dimensions

(to be confirmed by RP):Concrete: 3.2 x 3.2 x 2.4 m3Iron: 1.6 x 1.6 x 1.6 m3Slide28

Beam Dump Entrance28.11.2013

EAR2 Beam Line - Report on the Status

28

Vacuum chamber Ø200

Borated polyethylene

Borated polyethylene

Concrete block

Gap 60mm

Alignment accuracy to be defined!

Al window (300

m

m)Slide29

Experimental area

28.11.2013

EAR2 Beam Line - Report on the Status

29Slide30

Additional Shielding in EAR2

28.11.2013EAR2 Beam Line - Report on the Status

30

Additional shielding below beam dump.

Additional shielding above 2

nd

collimator

= false floor (20 cm).

C6D6 detectors in FLUKA.Slide31

Capture Setup

28.11.2013

EAR2 Beam Line - Report on the Status

31

SiMon

and sample exchanger (INFN) included in model.

Support for sample exchanger to be modified (less material, detector closer to sample).

Beam-line reductions before and after sample not included yet.

Small

Kapton

windows planned before and after sample (like in EAR1).

Valve below

SiMon (vacuum + safety).Additional shielding not included yet (false floor + below beam dump).Slide32

Capture Setup

28.11.2013

EAR2 Beam Line - Report on the Status

32

Vacuum Valve

1 m from beam centre to pillarsSlide33

Capture + Fission Setup

28.11.2013

EAR2 Beam Line - Report on the Status

33

Top part of the beam line will have to be dismantled before the crane can be used.

Vacuum chamber with inserted shielding different for capture and fission => also needs to be removed when changing the collimators.Slide34

From Capture to Fission(and reverse!)

28.11.2013EAR2 Beam Line - Report on the Status

34

Vac. chamber + shielding in roof

To be dismantled and remounted:

Beam Line + Detectors

2

nd

Collimator

False Floor = Shielding

1

st

Collimator in Service Gallery!

4-5 days!Slide35

6Li or 10B

28.11.2013

EAR2 Beam Line - Report on the Status

35Slide36

InvestigationsUse

6Li(n,a)

3H instead of 10

B(n,a)

7Li for 2nd collimator and all shielding material in

EAR2.Cross-section of 6Li(

n,

a

)

3

H

is 4 times smaller than 10B(n,a)7

Li – higher neutron background expected.See presentation of Silvia for details about the simulations.Available material: 7.5

% natLithium-Polyethylene.Material properties: machinable like normal PE, no safety issues reported.Budget: Approximately 10 000 Euros for 1 m3

.28.11.2013EAR2 Beam Line - Report on the Status

36Slide37

Conclusions

28.11.2013

EAR2 Beam Line - Report on the Status

37Slide38

ConclusionsProduction

started for various elements:Vacuum chamber 1All needed bellows

Magnet (almost ready)To be decided:

Filters (proposed: Ag, W, Mo, Co, Na, Al, S)

10B or 6Li

Monitoring system (capture)Error margins for beam dump alignmentSafety margins for vacuum chambers inside EAR2

To Do:

Supports (detectors, sample exchanger, etc.)

Equipment in EAR2 (tools, sources, etc.)

28.11.2013

EAR2 Beam Line - Report on the Status

38Slide39

Master Mind Sylvain Girod

28.11.2013

EAR2 Beam Line - Report on the Status

39Slide40

What have we forgotten?Thank you for your attention!

28.11.2013

EAR2 Beam Line - Report on the Status

40Slide41

Backup

28.11.2013

EAR2 Beam Line - Report on the Status

41Slide42

1.5 m

2 m

1 m

28.11.2013

EAR2 Beam Line - Report on the Status

42

Collimator 2

Material

Thickness 20 mm

Gap 60 mm

Minimum aperture Ø320 mm

Pit Ø800 mm

175 mm available for chicanes on radius

.

(Here 3x58mm)

Maximum gap: 2mmSlide43

Additional shielding

layer at the floor of EAR2

for background reduction

Steel balls above service

gallery

1 m Concrete right above service galleryFe + Concrete wall in ISR

tunnel

Fe

collar at the level of 1

st

collimator

Concrete

around beam pipe up to service gallerySlide44

1

st

Collimator:

Removal

The green shielding is brought above the collimator with

a trolley on the rails

The collimator is lifted inside the green shielding with

a hoist

The rails guide the trolley to the storage position

The collimator is lowered in the storage pit

28.11.2013

EAR2 Beam Line - Report on the Status

44

Hoist 0.5t