/
Project Delivery Method Selection Guidance Project Delivery Method Selection Guidance

Project Delivery Method Selection Guidance - PowerPoint Presentation

liane-varnes
liane-varnes . @liane-varnes
Follow
422 views
Uploaded On 2017-06-13

Project Delivery Method Selection Guidance - PPT Presentation

ACECWSDOT Annual Meeting June 11 2015 Jeff Carpenter Director WSDOT Construction Division AcronymsDefinitions PDMSG Project Delivery Method Selection Guidance PDM Project Delivery Method ID: 559116

pdm project pdmsg selection project pdm selection pdmsg delivery final method process projects wsdot checklist probable design determine part

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "Project Delivery Method Selection Guidan..." is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

Project Delivery Method Selection Guidance

ACEC/WSDOT Annual Meeting

June 11, 2015

Jeff Carpenter

Director, WSDOT Construction DivisionSlide2

Acronyms/Definitions

PDMSG – Project Delivery Method Selection Guidance

PDM – Project Delivery Method

Alternative Project Delivery Method – a delivery method other than Design-Bid-Build

Probable Project Delivery Method

- a

temporary determination

at project scoping that

is used for project planning until it can be

validated/updated

by the

Engineering Project Office assigned

to the project.

Final Project Delivery Method

- is

the PDM determination submitted for approval to use as the contracting method for the project early in the project design process. Slide3

PDMSG Team Purpose

Develop

formal guidance to aid WSDOT staff

in the

selection of project delivery methods based on a project’s attributes, opportunities and risks that will result in the most cost effective and best value

project delivery

in alignment with Reform VII.Slide4

PDMSG Task Goals

Establish a systematic

approach that can be consistently applied throughout WSDOT,

Establish

how and when a project should

be assessed,

Develop the

PDMS P

rocess to be scalable for all projects,

Design the PDMSG

Process

to provide

the documentation

for delivery

method

approval,

Clearly identify all levels of approval or endorsement in the process. Slide5

PDMSG Background

Current Selection Process

Design-Bid-Build is automatic unless an Alternative Delivery Method is pursued

Design-Build approval is required from WSDOT Chief Engineer

General Contractor/Construction Manager approval is required through CPARBSlide6

PDMSG Background

New Selection Process

All projects will be evaluated for the optimal Project Delivery Method (PDM),

The PDMSG evaluates three methods,

Design-Bid-Build,

Design-Build,

General Contractor/Construction Manager,

The selected PDM will be endorsed and/or approved through the Regions and HQ.Slide7

PDMSG Outline

Project Delivery Selection Matrix from University of Colorado, Boulder and CDOT was used as a foundation - data and some forms retained

WSDOT PDMSG was tailored to WSDOT Policy and Values

All projects are evaluated in two steps

The Probable PDM is determined during Scoping of the project

The Final PDM is determined by the Design PEO by validating, updating or revising the Probable PDMSlide8

PDMSG Outline

A Selection Checklist is used to quickly screen out projects that are obvious Design-Bid-Build or have a easily determined PDM,

A Selection Matrix (if needed as a second step) is used to determine the Probable PDM and validate/revise it to determine the Final PDM,

The work to determine the Probable PDM and the Final PDM are scalable to the size and complexity of the projects,

The timing and requirements for different levels of work are integrated with the existing project development process.Slide9

Determining Probable PDM

Project Size

Required Process

Project less than $10 Million

Complete Part

1 of Selection Checklist

Projects less than $25 Million or if Part 1 of Checklist does not determine a Probable PDM

Complete Part

1 and 2 of Selection Checklist

Projects greater than or equal to $25 Million or if Part 2 of the Checklist does not determine a Probable PDM

Complete Selection

MatrixSlide10

Determining Final PDM

Project Size

Required Process

Project less than $10 Million

Validate/Revise

Part 1 of Selection Checklist

Projects less than $25 Million or if

Validation/Revision

of Part 1 of Checklist does not determine a Final PDM

Validate/Revise or Complete Part

1 and 2 of Selection Checklist

Projects greater than or equal to $25 Million or if

Validation/Revision

of Part 2 of the Checklist does not determine a Final PDM

Validate/Revise or Complete Selection

Matrix

Projects greater than or equal to $100 Million or if

Validation/Revision

of the Selection Matrix does not determine a Final PDM

Complete Selection

Matrix WorkshopSlide11

PDMSG TimingSlide12

Probable PDM ProcessSlide13

Probable PDM EndorsementSlide14

Final PDM Determination -Validation/Revision ProcessSlide15

Final PDM Determination – Selection Workshop ProcessSlide16

Final PDM ApprovalSlide17

PDMSG Status

“White

Paper” on other

DOT/Agency project

delivery selection

guidance Completed

PDMSG Team Formed

HQ Construction, HQ Design, Program Management , OR and NWR

Draft PDMSG Documents Developed

Selection Checklist

Selection Matrix

Processes including flowcharts

Endorsement/Approval Processes

Preliminary User Guidance and ToolsSlide18

PDMSG Next Steps

Expand guidance document

Review PDMSG with WSDOT/AGC/ACEC DB Committee

Test “Beta” guidance, tools and processes with an independent WSDOT group

Refine document from test group input

Review PDMSG through Executive

Create user friendly platform for delivery to users

Develop Training and Implementation Plan

ImplementSlide19

Questions?

Jeff Carpenter

Director, Construction Division

CARPENJ@wsdot.wa.gov

360.705.7821 (x7821)