/
I-66 Outside the Beltway I-66 Outside the Beltway

I-66 Outside the Beltway - PowerPoint Presentation

lois-ondreau
lois-ondreau . @lois-ondreau
Follow
362 views
Uploaded On 2018-03-20

I-66 Outside the Beltway - PPT Presentation

Design Public Hearing Meetings November 13 14 amp 16 2017 Susan Shaw PE Megaprojects Director Virginia Department of Transportation Tolling begins December 2017 Multimodal projects benefitting I66 users funded by toll revenue ID: 658015

design noise wall 2017 noise design 2017 wall construction trail project 2018 environmental trails comments final express traffic public november lanes 2016

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "I-66 Outside the Beltway" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

I-66 Outside the Beltway

Design Public Hearing Meetings

November 13, 14 & 16 2017

Susan Shaw, P.E., Megaprojects Director

Virginia Department of TransportationSlide2

Tolling begins December 2017

Multimodal projects benefitting I-66 users funded by toll revenue

Widening I-66 eastbound between Dulles Connector Road and Fairfax Drive-Exit 71 (approximately 4 miles) – construction begins in 2018 and open in 2020

2Slide3

Project Segments

Hearing Agenda

Open House Starts:

6:00 p.m.

Presentation Begins:

7:00 p.m.

Comments:

7:30 – 8:30 p.m.

Segment

1

Segment

3

Segment

2

3Slide4

2022:

Transforming I-66

Over $3B in transportation improvements designed to:

Relieve congestion in all lanesProvide faster transit through Express LanesMove 2,000 to 4,000 more people per hourFund new buses and transit routesAdd 4,000 new park-and-ride spacesImprove safety

4Slide5

Project

Overview

Multimodal improvements to 22.5 miles of I-66

2 express lanes in each direction from I-495 to Gainesville3 general purpose lanes in each directionHOV and transit access to Express Lanes Median space reserved for future transitImproved park-and-ride options with access to Express Lanes

Bike-pedestrian trail integrated with existing and planned trails

5Slide6

Project

Video

Video Overview:

I-66 Project Design

6Slide7

Where We Are

7

July 2016

VDOT Design Concepts

and RFP

October 2016

Technical Proposals

Submitted from

Two Teams

Including Alternative

Technical Concepts

(ATC’s)

November 2016

Partner Selected(I-66 Express Mobility Partners)June 2017Public Information MeetingsSummer 2017 Concept Adjustments November 2017Design Public Hearings

Late 2017

Construction Start-up Activities

Fall 2017 - Winter 2018

Environmental andTraffic Analyses

May/June 2015EnvironmentalPublic HearingsOctober 2015Public InformationMeetingsTODAYSlide8

Right of Way

Activity

To Date

Next Steps

Outreach and letters to impacted landowners –

through June 2018

Appraisals and interviews with property owners

Estimated 75-90 days between appraisals and offers for properties

Acquisition negotiations

200 property owners (commercial and residential) notified of access needs and surveys –

March 2017

Initiated 1-on-1 contact with residential relocation owners –

S

pring 2017Survey work – April through September 2017Design Public Hearings – November 20178

292 Acquisitions - 10 Residential RelocationsSlide9

Noise Analysis Process

Identify noise receptors

Perform noise measurements at representative receptors along corridor

Perform noise modeling to identify impacts

Design and assess noise walls

Noise walls were shown in preliminary concept plans in 2015

Show preliminary noise wall locations on updated 2017 design plans

Perform final noise analyses based upon design plans & updated traffic

Is the wall feasible?Is the wall reasonable?Publish final noise study results and noise wall locations in 2018

Solicit input from benefited property owners & renters (voting process)

Include approved noise walls into final plans

NEPA

and

Preliminary DesignFinal Design9Slide10

10

Traffic and Environmental Studies

Final Environmental Assessment and Finding of No Significant Impact (FONSI) completed in June 2016 documented the

Preferred Alternative

design

Project

design changes

under environmental review

Revised project

design now incorporated into 2016

Constrained Long Range Plan by the National Capital Region Transportation Planning Board

(October 2017)

Results of the traffic and environmental reevaluations and the Final Design Noise Analysis will be posted to Transform66.org (Spring 2018)Slide11

11

Bicycle and Pedestrian Trails

Shared use trails along I-66 that integrate with County and Park

trails

New crossings of I-66 improve and expand bicycle and pedestrians routes

11 miles of new bike trails by

I-66

EMP

Over 7 miles of new bike trails by others

8 permanent count stations along the trail

11 bridges improved with additional bicycle and pedestrian

facilities

Example

Cross Sections at OverpassesSlide12

Proposed Trail Design

12

Trail Inside Noise

Wall

Near

homes

, the trail will be on the I-66 side of the noise wall

Improved separation between the trail and the highway continue to be explored

Along I-66, concrete barrier with fence will separate the trail from the roadway

Potential Noise Wall

Trail outside Noise

W

all

Trail without Noise WallSlide13

13

What’s Next

Continue to Refine Final Design

Develop Draft Corridor Aesthetics (CA) Plan

Begin Early Construction Activities

Complete Environmental Re-Evaluation

Begin Right of Way Acquisition

Complete Noise and Traffic Analyses

Dunn Loring

EC Lawrence Park

Proposed (Sample) Noise Wall TreatmentsSlide14

Key

Upcoming Milestones14

Milestone

DateDesign Public HearingsNovember 13, 14 and 16, 2017Begin Right of Way AcquisitionLate 2017Begin ConstructionLate 2017Park and Ride Milestone (960 spaces near Gainesville)Summer 2019Route 28 Signalization (Remove 4 traffic signals from Route 28)Summer 2020

Express Lanes OpenDecember 2022Slide15

15

Preparing for Construction

Pre-construction condition surveys underway for nearby properties

Construction start-up

in Fall

2017 within existing right of way

Construction ramp-up

in Spring

2018

Construction to take place throughout the 22.5 mile corridor for duration of project

No lane closures on I-66 during peak periods

Public will be kept informed through Transform66.org, social media, TV, radio, print media, roadway signage

Provide advance construction information to adjacent communities and address issues of concern – Good Neighbor policySlide16

How to Make Comments

Deadline: November 29, 2017

16

Submit written Comment Sheet Record comments with court reporterRegister to speak (3 minutes per speaker)Submit online comments at Transform66.orgEmail your comments to Transform66@VDOT.Virginia.govMail comments to: VDOT Northern Virginia District 4975 Alliance Drive, Attn: Susan Shaw, P.E.

Fairfax, VA 22033

TTY/TDD: Dial 711Slide17

17

THANK YOU