/
SPATIAL ANALYSIS TO PROMOTE SPATIAL ANALYSIS TO PROMOTE

SPATIAL ANALYSIS TO PROMOTE - PowerPoint Presentation

lois-ondreau
lois-ondreau . @lois-ondreau
Follow
376 views
Uploaded On 2017-10-02

SPATIAL ANALYSIS TO PROMOTE - PPT Presentation

RENEWABLES AND IMPROVE EFFICIENCY IAIA Montreal Canada 5 April 2017 Ms D Fischer Professor H J Annegarn Ms L Cape CO2 reduction imperative SA carbon intensive economy ID: 592293

environmental bid window energy bid environmental energy window assessment rei4p days applications eia process impacts total pre wind review case electricity renewable

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "SPATIAL ANALYSIS TO PROMOTE" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

SPATIAL ANALYSIS TO PROMOTE RENEWABLES AND IMPROVE EFFICIENCY:IAIA – Montreal Canada 5 April 2017Ms D Fischer

Professor H. J

Annegarn

,

Ms

L

Cape

Slide2

CO2 reduction imperative

SA carbon intensive economy

77% primary energy from coal

90% for electricity generation

2009, CO

2

emissions

- 9.1 tonnes/capita- global average

4.5

t/c

The National Development Plan – SA to

diversify

energy

choices as a

priority

Integrated Resource plan 2010 to 2030 -

energy mix

includes 17.8

GW

renewable energy

3 725

MW Renewable Energy commissioned by 2016 and 17.8 GW by 2030 – procured by competitive bidding

2011 Renewable Energy Independent Power Producers Procurement Process launched – REI4P

First phase – 5 bid windows

Bid requirement to have a positive Environmental Authorisation Slide3

Success of the REI4P from inception

Windows 1 – 4

Investor involvement - 889

renewable energy

applications submitted between bid window 1 to 4

P

rices reduced by

54% for wind and 76% for solar PV from

bid window 1 to 4

Over 23 000 job opportunities created for South African citizens

12 new industrial facilities established in SA

R53.4 billion in foreign investment and financing to

date

December 2016:

power purchase agreements signed for 3 922 MW

Commissioned -

2 560 MW

 

June 2016:

7

million tons of CO

2

equivalent reductions

realised

Over

20 years

a

total of 902 million tons – or the equivalent of four full years of

current

electricity emissions at

2014/2015 levels

R19.2

billion

committed towards

social economic development

initiatives

2016 no further power purchase agreements signed – reduce energy needs, costs of new grid Slide4

REI4P – Unintended consequence on EIA numbers

Bid window

Reporting period

Number of new applications

Total number of new applications per bid window

Number of amendments

S&EIR

BAR

Prior to REFIT & REI4P

Prior to 2009

2

0

N/A

Not recorded

1

2009 to 04-11-2011

250

9134120204-11-2011 to 05-03-2012 5459113233 05-03-2012 to 18-08-2013232723041304 18-08-2013 to 19-08-20149633129114Sub-total to bid window 4:634255889287Post 419-08-2014 to 07-07-20154434777 Total: 678258936364

Department structured to receive 400 applications for EA per annum – bid window 3 almost double

EIA

done 3 years prior to construction –

several amendments required

As at

March 2017 - 96

appeals received on

wind and solar authorisations

8.5

% projects receiving environmental authorisations were

preferred bidders (90 of 889)

Low success rate – time spent reviewing unsuccessful

projectsSlide5

REI4P – Quality of information submitted in EIAs – linking of REI4P to a competitive bidding process

reviewed four wind energy applications – against generally accepted impacts of the technology

Speculative nature of the EIAs reduced quality and increased amendments and appeals

 

Case study 1

Case study 2

Case study 3

Case study 4

Average

Timing of specialist studies

50%

25%

50%

25%

38%

Identification of key impacts associated with wind energy technologies

81%

81%81%71%78.5%Assessment of impacts 72%55%63%72%65.5%Environmental statement provided63%46%46%63%54.5%Identify and propose generally acceptable mitigation measures63%27%27%55%43%Site specific mitigation measures are transferred to the EMPR46%55%46%36%46%

Provide a level of site-specific assessment that exceeds that which could be achieved through a geographical assessment. 46%81%55%

46%

57%

Overall average

55%Slide6

3 SEAs

undertaken

Objective:

best locations for wind/solar/grid based on resource, environmental sensitivity, social and engineering consideration

Reduce workload associated with REI4P applications

Ensure environmental protection Slide7

SEA identified environmental instruments to reduce timeframes and address EIA shortcomings

Developed Integrated Environmental Management

Instruments

Generic EMP for electricity grid infrastructure

Pre-screening tool based on GIS layering of environmental and engineering information

Assessment protocols linked to environmental sensitivity

Gazetting REDZs and power corridors – facilitate spatial planning

Pre-screening tool allows for early identification of

specialist studies to be undertaken

Pre-screening tool identifies impacts for consideration based on environmental sensitivity

Protocols linked to site sensitivity identify the level of assessment required

Protocol identifies requirement for an environmental statement

Generic EMPR identifies mitigation measures for electricity grid infrastructure

Statements identify requirement for mitigation Slide8

Streamlining

allows for post bid authorisations

Bid Window 1

Bid Window 2

Bid Window 3

Bid Window 4

03-08-2011

Amended

17-11-2011

03-02-2012

03-05-2013

20-05-2014

04-11-2011

05-03-2012

18-08-2013

19-08-2014

111214Power purchase agreement to be signed IEM Instruments allows for shortened review timeframes Pre-assessment allows reduced review and authorisation timeframes from 300 to 147 days Appeal 90 days 8 months in total requiredShortened review timeframes allows for post bid authorisations - preferred bidder to financial close 11 months SEA Basic Assessment Process – 147 days 90 daysSUBMIT APPLICATION AND CONSULTATION DOCUMENT Pre-application (Optional)COMPETENT AUTHORITY REVIEW AND DECISION MAKING 57 daysSUBMIT BAR FOR REVIEW COMMENTING AND STATE OWNEDENTITY COMMENT PERIOD 30 DAYSSlide9

Conclusion

Programmes linking competitive bidding to EIA impacts:

Quality

Work levels

SEA – using GIS and applying pre-screening can

Improve spatial planning and implement the avoidance hierarchy

Can improve quality of information submitted to the EIA process

Can reduce workload

Achieve by:

Improving environmental information

Streamlined processes

Ability to defer EIA process by reducing potential fo

r fatal flaws 899 – 90

Spatial planning can promote renewables and improve efficiency Slide10