/
Design Project #1 Design Project #1

Design Project #1 - PowerPoint Presentation

luanne-stotts
luanne-stotts . @luanne-stotts
Follow
382 views
Uploaded On 2017-05-05

Design Project #1 - PPT Presentation

Replacement of Vehicle Bridge over Spring Creek Centre County PA Introduction to Engineering Design EDGSN 100 Section 002 The Bleeding Frogs Team 1 Joe Berg Britta Beleski David Wu Kate ID: 544975

efficiency bridge howe members bridge efficiency members howe warren cost structural design truss phase meters member deck load efficient span structurally failed

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "Design Project #1" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

Design Project #1

Replacement of Vehicle Bridge over Spring CreekCentre County, PAIntroduction to Engineering DesignEDGSN 100 Section 002The Bleeding FrogsTeam 1Joe BergBritta BeleskiDavid WuKate Barkley

Presented to:

Prof. Berezniak

Fall 2015

HOWE

WARREN

TEAM CHRISTMAS PHOTO Slide2

Statement of Problem

Due to a 100 year flood, a structurally deficient bridge allowing access to Mt. Nittany Medical Center imploded in Centre County, PA. 2Slide3

Objective

Build a new vehicle bridge which is both structurally and cost efficient in the designated area by comparing and load testing different Truss design models.3NOT THIS!!OH YEAH BABY!!Slide4

Design Criteria

Standard abutments, no piers (one span), deck material shall be medium strength concrete (0.23 meters thick), no cable anchorages and designed for the load of two AASHTO H20-44 trucks (225kN) with one in each traffic lane. The bridge deck elevation shall be set at 20 meters and the deck span shall be exactly 40 meters. Both a Warren through truss bridge and a Howe through truss bridge shall be analyzed. 4Slide5

Technical Approach Phase 1: Economic Efficiency

The bridge was put under intense evaluations in order to achieve the lowest cost possible. The bridges’ members were tested with different member thicknesses as well as different materials. The most cost efficient method was to use members with similar thicknesses and materials. In this way, the bridge was able to dodge the costs of bringing in different sized members.5WOAH, LOOK OUT!!!Slide6

Technical Approach Phase 2: Structural Efficiency

Where ever the bridge failed, the members that failed were substituted for thicker members. Different types of steel were also tried to achieve the strongest bridge (the compression ratio closest to 1.0). Tubes were stronger for compression and bars were stronger in tension. The different types of members were used in the correlating force.6WHO’S A GOOD LITTLE BOY?!?!Slide7

Results Phase 1: Economic Efficiency

7HOWEWARRENTOTAL COST$268,947.72$247,019.84# OF MEMBERS3739AVG COST MEMBERS$7,268.86$6,333.84MOST COST EFFICIENTHEY KIDS!Slide8

Results Phase 2: Structural Efficiency

Structural Efficiency is defined as the ratio of the load at which the bridge fails to the weight of the bridge. Structural efficiency of Warren = 579.3Structural efficiency of Howe = 388.878HOWEWARRENNote: Gussets.Slide9

Best Solution

The best solution for the PennDot proposal is to use the Warren Truss Bridge Design because it has the higher structural efficiency of the two bridges and it withstood more force.9Slide10

Conclusions

10BROKE AT MEMBER 27 AND JOINT 4.BROKE AT MEMBER 11 AND JOINT 6. 2716116WARREN

HOWESlide11

Recommendations

11SPECIAL THANKS TO XAVIER!!