Samy Chemli ENMEF November 2012 Hardware Baseline Approved ECR ECR under approval ECR approval closed Test Procedures Installation Procedures Open Items Approved ECR LHCJSMEC0001 ID: 212504
Download Presentation The PPT/PDF document "LHC Hardware Baseline" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.
Slide1
LHC Hardware Baseline
Samy Chemli EN-MEF
November 2012Slide2
Hardware Baseline
Approved ECR
ECR under approval
ECR approval closed
Test
Procedures
Installation Procedures
Open ItemsSlide3
Approved ECR
LHC-JSM-EC-0001
Released
2012-03-14
R2E shielding for LHC Points 1, 5 and 8
A.L. Perrot, R2E Project
The level of flux of hadrons with energy in the multi MeV range expected from the collisions at the interaction Points 1, 5 and 8 induce Single Event Errors (SEE) of the standard electronics present in many of the control equipment. Such events perturb the LHC. It is proposed to install additional shielding to protect the equipment that cannot be moved. This process is foreseen in two phases as the beam current and luminosity rise. Phase I consists in installing shielding in the RBs, UJs around Point 1. Phase II consists in installing shielding in US85 and in the RRs around Points 1 and 5. It is proposed to perform Phase I during the 2011-2012 Christmas break and Phase II during the Long Shutdown 1 (LS1). This ECR documents these two phases.Slide4
Approved ECR
LHC-TCDQ-EC-0003
Released
2012-04-04
Upgrade of TCDQ Collimator
Wim Weterings, Brennan Goddard
This ECR includes the following proposed changes in IR6:
• Increased length of the TCDQ collimator system from 6.85 m to 10.40 m.
• Modify the composition of the absorber blocks of the TCDQ.
• Improve the design of the VMTAB large displacement bellows.
• Changed positions of the BPMs in this regionSlide5
Approved ECR
LHC-VC5-EC-0001
Released
2012-08-21
CMS Central Chamber Diameter Reduction
M.A.
Gallilee
This Engineering Change Request (ECR) is concerned with the reduction in diameter of the CMS central beryllium chamber. The request is for a reduction in inner diameter from 58 mm to 43.4 mm.
This change has been studied in depth from an engineering perspective, and approved by both the LEB Working Group, and the LHC Machine Committee. This document
summarises
the effects of this changeSlide6
Approved ECR
LHC-VC1I-EC-0001
Released
2012-08-17
Reduction of ATLAS VI Chamber Diameter
M.A.
Gallilee
This Engineering Change Request (ECR) is concerned with the reduction in diameter of the ATLAS VI chamber. The request is for a reduction in inner diameter from 58 mm to 47 mm.
This change has been studied in depth from an engineering perspective, and approved by both the LEB Working Group, and the LHC Machine Committee. This document
summarises
the effects of this change.Slide7
Approved ECR
LHC-VC1-EC-0002
Released
2012-08-17
Material Change ATLAS VA & VT Chambers
M.A.
Gallilee
This Engineering Change Request (ECR) is concerned with the change of material of the ATLAS VA and VT chambers from stainless steel to
aluminium
AA2219. The change has no effect on aperture.
This change has been studied and accepted by the CERN BE/RF and BE/ABP-ICE.Slide8
Approved ECR
LHC-XAFP-EC-0001
Released
2012-07-06
Space Reservation in the LSS1 for the ATLAS Forward Physics Project (AFP)
D.
Macina
The ATLAS Forward Physics Project (AFP) is part of the ATLAS Upgrade Project and requires the installation of movable detectors at about 210 m on either side of IP1. Therefore, with this ECR, ATLAS requests to reserve the space between Q5 and Q6 (from 200.253 m to 221.379 m) for the integration of AFP.Slide9
Approved ECR
LHC-LJ-EC-0027
Released
2012-10-11
Protection of equipment located in UJ14 and UJ16
A. L. Perrot for R2E
The level of radiation expected from the collisions at the interaction point 1, and more precisely the flux of hadrons with energy in the multi MeV range, will induce Single Event Errors (SEE) of the standard electronics present in many of the control equipment located in UJ14 and UJ16. Such events would perturb the LHC, possibly leading to critical situations for the machine elements. It is furthermore proposed to relocate part of the equipment installed in UJ14/16 into UL14/16 and US15, where the amount of radiation is reduced. The relocation of the SEE sensitive equipment identified by the RADWG is foreseen for the first LHC long shutdown. This ECR documents this implementationSlide10
Approved ECR
LHC-LJ-EC-0026
Released
2012-10-11
Protection of equipment located in UJ56
A. L. Perrot for R2E
The level of radiation expected from the collisions at the interaction point 5, and more precisely the flux of hadrons with energy in the multi MeV range, will induce Single Event Errors of the standard electronics present in many of the control equipment located in UJ56. Such events would perturb the LHC, possibly leading to critical situations for the machine elements. It is furthermore proposed to relocate part of the equipment installed in UJ56 (almost all first floor racks) into the UL557 bypass gallery, where the amount of radiation is reduced. The relocation of the SEE sensitive equipment identified by the RADWG is foreseen for the first LHC long shutdown. This ECR documents this implementationSlide11
Approved ECR
LHC-DQS-EC-0001
Released
2012-10-24
Replacement of the Original, 200V Arc Chambers by the 1050V Dipole Version on the Energy Extraction Switches of the LHC Main
Quadrupole
Circuits
K.
Dahlerup
-Petersen
The proposal concerns the replacement of the 128 existing arc chambers which are presently equipping the LHC
quadrupole
extraction switches (DQSQF/DQSQD) by the type of arc chambers which are in used on the extraction switches of the 8 LHC main dipole circuits (DQSB, also 128 units). This change will remove a major obstacle for operating the LHC machine up to nominal beam energy while at the same time maintaining the extraction discharge time constants of 9.5 s which were introduced in these 16 LHC circuits at the same time as the implementation of the
nQPS
system for operation up to 3.5
TeV
.Slide12
Approved ECR
LHC-QBBI-EC-0002
Released
2012-10-24
Modification of the Interconnection Thermal Screen
A.
Musso
The interconnections thermal screens (TSs) are presently welded in-situ during installation. The proposed change foresees to fix them mechanically avoiding welds in underground areas, by means of a screwed clamp.Slide13
Approved ECR
LHC-Y-EC-0007
Released
2012-10-24
Creation End-of-Zone Door for Material Transfer between USC55 and the Point 5 Bypass
C.
Bertone
Changes are proposed to improve access to the LHC point 5 bypass tunnels for large and heavy items. The changes include an increase in the size of the existing passage in the wall between USC55 and the bypass, the installation of a new ‘end-of-zone’ door for wide material passage and relocation of some wall-mounted equipment in the area of the passage.Slide14
Approved ECR
LHC-S-EC-0007
Released
2012-11-23
Modification of the LHC UJ43/UJ47 Chicanes.
M.
Galofré-Vilà
On the 26th of January 2011, during the execution of a LHC regular drill, we identified an access problem while crossing the UJ-47 chicane (located 2,440 meters from PM 45) with Fire Brigade intervention electrical powered tractors and trolley (
Pefra
®). The inaccessibility via the chicanes compromise Fire Brigade operational deployment in case of emergency intervention. In order to restore the accessibility the ECR propose modification on UJ-43 & UJ 47 to grant the access.Slide15
Hardware Baseline
Approved ECR
ECR under approval
ECR approval closed
Test
Procedures
Installation Procedures
Open ItemsSlide16
ECR Under Approval
LHC-LJ-EC-0028
Under Approval
Version 0.2
New BPM and vacuum bellow in the area between the VAX and the TAS in IP 1 and 5.
J. Bosch, M.A.
Gallilee
This Engineering Change Request (ECR) proposes to modify the current BPM layout by combining them and to introduce a longer bellow in the area between the VAX and the TAS equipment of Interaction Points 1 and 5Slide17
ECR Under Approval
LHC-VAM-EC-0001
Under Approval
Change of the Warm Module in ALICE at 9 m left of the IP.
G. Schneider
The low pressure gauges of the ALICE vacuum system are installed today at about
20 m from
the IP. An additional vacuum gauge is proposed at the level of the Central Compensator Magnet (MBWMD) about 9 m left of the IP. This will require a new warm module as part of a new vacuum assembly of type VAMAPSlide18
ECR Under
A
pproval
LHC-QBBI-EC-0001
Under Approval
Protective half shells for the vacuum lines
C.
Garion
This ECR is related to the installation of protective half shells for the LHC cold vacuum line interconnections.Slide19
ECR Under
A
pproval
LHC-LV-EC-0001
Under Approval
TDI vacuum
sectorization
C4L2/C4R8
E. Page
To reduce the length of the vacuum sectors A4L2.C and A4R8.C and to minimize the intervention time while optimizing the vacuum performances, the TDI
sectorization
, part of the LHC base line, is proposed to be implemented during LS1. This document describes the new layoutSlide20
ECR Under
A
pproval
LHC-CIP-EC-0003
Under Approval
Change of the Interlocking of Powering and Access Systems
J.
Wenninger
, I.
Romera
Ramìrez
, T.
Ladzinski
This document describes modifications to the interlocking of powering and access system for the LHC after LS1. The link between the LHC Access Safety System and the LHC Software Interlock System, currently based on the TIM infrastructure, will be replaced by a more robust solution, even though the communication will still mostly rely on software.Slide21
ECR Under
A
pproval
LHC
-
BPMWI
-
EC
-
0001
Under Approval
BPM for Gated Tune Measurement in IP4
C.
Boccard
This Engineering Change Request (ECR) describes the proposed installation of one additional pair of BPMs for gated tune measurement in 6R4. This draft ECR will help to identify the cost, the effort, impact on the machine performance and expected improvement of beam diagnostics.Slide22
ECR Under
A
pproval
LHC
-
VPN
-
EC
-
0002
Under Approval
Non Evaporable Getter Cartridges Installation in the ADT (transverse damper) Area of the LSS4 of LHC
G.
Bregliozzi
This ECR describes the position of the Non Evaporable Getter (NEG) cartridges that will be installed in the LHC accelerator during the Long Shutdown 1 (LS1) in the ADT area of the Long Straight Section 4Slide23
ECR Under
A
pproval
LHC
-
VPN
-
EC
-
0003
Under Approval
Non Evaporable Getter Cartridges Installation in the VAX Area of LSS2 and LSS8 of LHC
G.
Bregliozzi
This ECR describes the position of the Non Evaporable Getter (NEG) cartridges that will be installed in the LHC accelerator during the Long Shutdown 1 (LS1) in the VAX area of the Long Straight Section (LSS) 2 and 8.Slide24
ECR Under
A
pproval
LHC
-
Y
-
EC
-
0008
Under Approval
Additional Radiation Vetoes in Access Locations Leading to the Injection Lines and Beam Dump Transfer Galleries
S.
Roesler
This modification introduces additional Radiation Vetoes in four regions of the LHC accelerator which today are partly classified as Supervised and Simple Controlled Radiation Areas and partly as Limited Stay Radiation Areas and, thus, allows a separate control of these areasSlide25
ECR Under
A
pproval
LHC
-
VVG
-
EC
-
0001
Under Approval
Sector Valves Upgrade
J.
Chauré
Cette ECR présente le projet d’amélioration du temps de fermeture des vannes de secteur du LHC et l’introduction d’accumulateurs d’air comprimé dans le tunnel à proximité des vannes de secteurSlide26
ECR In Work
LHC
-
BBC
-
EC
-
0001
In Work
LHC Long Range Beam-Beam Compensator Prototype – Powering Aspect
V.
Montabonnet
,
R.
Steinhagen
Installation of the powering circuits for the LHC Long-Range Beam-Beam Compensator (LHC-BBC) prototypes to assess the physics performance, operation of these compensators. The aim of the LHC-BBC is to improve physics performance of the LHC by mitigating the deteriorating effects of long-range beam interactions around the two high luminosity insertions in view of the LHC High-Luminosity project Slide27
ECR In Work
LHC
-
QBBI
-
EC
-
0003
In Work
Consolidation of the 13kA Splices of the Main Circuits in the LHC
S. Le
Naour
A large campaign of consolidation of the LHC machine, called LS1 (Long Shutdown 1), will be held from spring 2013 to autumn 2014 to ensure continuity of the main
busbars
(13kA) in the interconnects between the magnets around the machine. At each connection from the current lead of DFBA to the other current lead, one or two copper shunts will be soldered at each side of the spliceSlide28
Hardware Baseline
Approved ECR
ECR under approval
ECR approval closed
Test
Procedures
Installation Procedures
Open ItemsSlide29
ECR Approval Closed
LHC-DQ-EC-0003
Approval closed
Voltage-Adjustable Trigger Introduction for Discharge in the Quench Heater Circuits of the LHC Main Magnets to use at Heater Circuit Qualification
K.
Dahlerup
-Petersen
In addition to the existing, operational trigger for activation of the process of discharge of the quench heater power supplies, driven by the QPS quench protection interlock or a command from the ‘QPS Expert’ platform, a new software application has been developed. It is intended for use during verification of the discharge circuits. The new facility is a software creation which allows discharges at a pre-determined voltage lower than the nominal level of capacitor charging (normally between 850V and 920V)… Application is particularly recommended after warm-up of the cold masses above 80K.Slide30
Hardware Baseline
Approved ECR
ECR under approval
ECR approval closed
Test
Procedures
Installation Procedures
Open ItemsSlide31
Test Procedure Released
LHC-DE-TP-0010
Released
2012-06-20
Internal Splices Resistance Measurements (ISRM) on Dipoles Located in S12.
G.
D’Angelo
This document describes the configuration of dipole magnet in sector 1-2, the measuring equipment and the procedure to be followed step by step in order to measure all internal splices of dipole magnet in sector 1-2Slide32
Test Procedure Released
LHC-QBBI-TP-0002
Released
2012-09-18
Visual Inspection and Geometrical Test of the US Welded Line N Splices.
S. Heck, C.
Scheuerlein
This document defines the procedure for the visual inspection and geometrical test of the US welded line N splices.Slide33
Test Procedure Released
LHC-QBBI-TP-0003
Released
2012-09-19
Visual Inspection and Geometrical Test of the US Welded Auxiliary
Busbar
Splices in Lines M1 and M2.
S. Heck, C.
Scheuerlein
This document defines the procedure for the visual inspection and geometrical test of the US welded auxiliary
busbar
splices in lines M1 and M2 that will be produced during the LS1 shutdown.Slide34
Test Procedure Released
LHC-QBBI-TP-0004
Under Approval
Version 0.2
Quality Control of the LHC Main Interconnection Splices Produced during LS1 (before Application of Shunts).
S. Heck, C.
Scheuerlein
This document defines the procedure and acceptance criteria that will be used to control the quality of the 13 kA LHC main interconnection splices to be produced during the first long LHC shut down LS1. The splice QC will be performed on the splices before applying shunts.Slide35
Test Procedure Released
LHC-QBBI-TP-0005
Under Approval
Version 0.2
Quality Control of the
Stabilised
LHC Main
Busbar
Cables before Splice Assembly
S. Heck, C.
Scheuerlein
This procedure defines the quality control and acceptance criteria for the
stabilised
13 kA LHC cables before the assembly and (re-) soldering of the main interconnection Splices.Slide36
Test Procedure Released
LHC-QBBI-TP-0006
Under Approval
Version 0.2
Quality Control Of the LHC Main Interconnection Splices Produced before LS1 (before Application of Shunts)
S. Heck, C.
Scheuerlein
This document defines the procedure and acceptance criteria that will be used to control the quality of the existing main LHC interconnection splices that have been produced before LS1. The splice QC will be performed on the splices before applying shunts.Slide37
Hardware Baseline
Approved ECR
ECR under approval
ECR approval closed
Test
Procedures
Installation Procedures
Open ItemsSlide38
Installation Procedure
LHC-QBBI-IP-0017
Under Approval
1.1 – Opening of W Bellows
G. Barlow
Procedure for opening the interconnection W bellows. Starting from a closed section until the removal of the radiation shield. This document determines the procedure for removing the W bellows, MLI, thermal shield and radiation shield of a cryostat interconnection
.Slide39
Installation Procedure
LHC-QBBI-IP-0016
Under Approval
Version 0.2
1.2 – Installation of DN200
O.
Housiaux
, J.M. Gomes de
Faria
, J-M.
Demolis
The procedure for installing the DN200 pressure relief valves of the dipole cryostats of the LHC accelerator
.Slide40
Installation Procedure
LHC-QBBI-IP-0023
In Work
3.2 –
Découpe
soudures
manchettes
M
R. Principe
Procédure
d’utilisation
de
l’outil
de
découpe
des
soudures
des
manchettes
des
lignes
M1, M2, M3, des
interconnexions
13kA
.Slide41
Installation Procedure
LHC-QBBI-IP-0014
Released
2012-10-16
4.1 - Capture
soufflet
M
R. Principe
Procédure d’utilisation de l’outil de compression hydraulique et de l’outil de capture des soufflets des lignes M, des interconnexions 13kA. En particulier, le document explique les principes de fonctionnement du groupe hydraulique
Enerpac
et détermine le mode opératoire de l’outil de compression et la méthode pour le montage de l’outil de capture sur les soufflets des lignes M1, M2 et M3, des interconnexions 13kA.Slide42
Installation Procedure
LHC-QBBI-IP-0011
Released
2012-10-16
4.2 -
Dépose
isolation
interconnexion
R. Principe
Procédure de démontage des isolations des
busbars
principaux des lignes M1, M2, M3, des interconnexions 13kA. En particulier, le document explique le mode opératoire du démontage des isolations des
busbars
principaux des lignes M1, M2 et M3, des interconnexions 13kA.Slide43
Installation Procedure
LHC-QBBI-IP-0022
Under Approval
6.1 -
Débrasage
par Induction U /Plat de
Fermeture
R. Principe
Procédure de débrasage des
busbars
principaux pour les interconnexions 13kA. En particulier, le document explique le mode opératoire de débrasage par induction, des profils en U et des plats de fermeture, des
busbars
des lignes M1, M2, M3, dans le cadre de l’amélioration des connexions des interconnexions 13kASlide44
Installation Procedure
LHC-QBBI-IP-0015
Under Approval
6.2 –
Stabilisation
Câble
Supraconducteur
R. Principe
Procédure de stabilisation du câble supraconducteur des
busbars
principaux pour les interconnexions 13kA. En particulier, le document explique le mode opératoire de stabilisation d’un câble supraconducteur ou d’une paire de câble supraconducteur, des
busbars
des lignes M1, M2, M3, pour les interconnexions 13kA.Slide45
Installation Procedure
LHC-QBBI-IP-0013
Under Approval
8.1 -
Brasage
par induction U/plat de
fermeture
R. Principe
Procédure de brasage des
busbars
des lignes M1, M2, M3 pour les interconnexions 13kA. En particulier, le document explique le mode opératoire de brasage par induction, des plats de fermeture et profiles en U, des
busbars
des lignes M, dans le cadre de l’amélioration des connexions des interconnexions 13kA.Slide46
Installation Procedure
LHC-QBBI-IP-0025
In Work
10 –
Usinage
Busbar
pour Shunt
R. Principe
Procédure
d’usinage
des
busbars
des
lignes
M1, M2, M3
avant
brasage
de shunts, pour les
interconnexions
13kA.Slide47
Installation Procedure
LHC-QBBI-IP-0021
Under Approval
11.1 -
Brasage
Shunt
sur
Busbar
R. Principe
Procédure de brasage de shunts sur les
busbars
des lignes M1, M2, M3 pour les interconnexions 13kA. En particulier, le document explique le mode opératoire de brasage de shunts, sur les
busbars
des lignes M1, M2, M3, dans le cadre de l’amélioration des connexions des interconnexions 13kASlide48
Installation Procedure
LHC-QBBI-IP-0020
Under Approval
11.2 –
Débrasage
Shunt du
Busbar
R. Principe
Procédure de débrasage de shunts des
busbars
des lignes M1, M2, M3 pour les interconnexions 13kA. En particulier, le document explique le mode opératoire de débrasage de shunts, des
busbars
des lignes M1, M2, M3, des interconnexions 13kASlide49
Installation Procedure
LHC-QBBI-IP-0024
In Work
13.1 – Montage
boitier
isolation
busbar
R. Principe
Procédure
de montage du
boitier
d’isolation
des splices des
lignes
M1, M2, M3, des
interconnexions
13kA et 600A.Slide50
Installation Procedure
LHC-QBBI-IP-0019
Under Approval
13.2 –
Démontage
Capture
Soufflet
M
R. Principe
Procédure d’utilisation de l’outil de compression hydraulique et du démontage de l’outil de capture des soufflets des lignes M, des interconnexions 13kA. En particulier, le document explique les principes de fonctionnement du groupe hydraulique
Enerpac
, et détermine le mode opératoire de l’outil de compression et la méthode pour le démontage de l’outil de capture des soufflets des lignes M1, M2 et M3, des interconnexions 13kASlide51
Installation Procedure
LHC-QBBI-IP-0018
Under Approval
15.1 – Closing of W Bellows
G. Barlow
Procedure for closing the interconnection W bellows. Starting from replacing the radiation shield until the closing of the W
bellows.This
document determines the procedure for replacing the radiation shield, thermal shield, MLI and W bellows of a cryostat interconnection
.Slide52
Hardware Baseline
Approved ECR
ECR under approval
ECR approval closed
Test
Procedures
Installation Procedures
Open ItemsSlide53
Open Items
LHC-DE-TP-0007
ELQA Qualification of the Superconducting Circuits during Hardware
Commissionning
Under Approval. Waiting for rewriting after TETM meeting in October.