Marcello Losasso CERN CERN 2526 June 2015 2 HiLumi LHC Project the background Jul10 Mandate to L Rossi by DAT to set up FP7Design Study Nov10 Application FP7HiLumi LHC Design Study ID: 572915

cern lhc project meeting lhc cern meeting project ideasquare lumi review losasso general presentation design fp7 amp 14international mqxf

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "The HL-LHC project: info day for industr..." is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

The HL-LHC project: info day for industry

Marcello Losasso- CERN

CERN – 25-26 June 2015 Slide2

2

Hi-Lumi LHC Project: the background

Jul-10

Mandate to L. Rossi by D.A.T. to set up FP7-Design Study

Nov-10Application FP7-HiLumi LHC Design StudyDec-10Institution of the HL-LHC as a project inside D.A.T.Mar-11Approval FP7-HiLumi LHC Design StudyApr-11CERN kick-off meeting of DSNov-11Start of FP7 DS and 1st General Meetign @ CERNJul-12Document CERN-ATS-2012-236 describing HL-LHC for EU strategyJul-12Decision MQXF (IT quad) aperture 150 mmNov-122nd General Meeting @ FrascatiMay-13HL-LHC 1st Priority in EU strategy update(Council @ Brussels)May-13International Review on CollimationJun-13First partial insertion iof HL-LHC in the MTPOct-13RLIUP (Review of LHC and Inj Upgrade Plans by CMAC)Oct-13First HL-LHC detector ECFA workshopNov-13HL-LHC Project kick-off and 3rd General meeting @ DaresburyMay-14International Review on CC @BNLJun-14MTP CERN incorporate HL-LHC budgetOct-14International Review on MQXF NbSn Conductor @ CERNNov-144th General Meeting @ KEK Nov-14Preliminary Design Report (PDR)Dec-14International Reviews on MQXF and MBH design @CERNMar-15Cost & Schedule Review @ CERN by CMACSlide3

3

The largest HEP accelerator in construction, and its plan is

embedded

into the general LHC plan

Interaction Region (ITR)Matching Section (MS)Dispersion Suppressor (DS)ATLASCMS> 1.2 km of LHC !!Complete change and new lay-out TASQ1-Q2-Q3D1All correctorsHeavy shielding (W)Complete change and new lay-outTAND2CCQ4All correctorsQ5 (Q6 @1.9 K?)New MQ in P6New collimatorsModificationsIn IP2: new DS collimation with 11 TIn IP7 new DS collimation with 11 TCryogenics, Protection, Interface, Vacuum, Diagnostics, Inj/Extr… extension of infrastr.Slide4

4

Many

points

around

the ringSlide5

5

On March

15, on occasion of the completion of C&S review, CERN had informed the ILO network about the Hi-

Lumi LHC project and notified about the upcoming event to inform EU industries. On end of April, invitation letters have been sent to industries and ILOs. The answer has been encouraging: we have here represented more than 100 industries and academic, from almost 20 EU countries, with 146 officially registered attendants. More than 80 B2B meeting have been requested.The technical sectors here represented are those of close interest to Hi-Lumi: superconductivity, cryogenics, power electronics, electrical engineering, mechanics.Other sectors here not mentioned could be included, if and when necessary, in future discussions.M.Losasso cern fp/ktSlide6

6

WHERE: Meeting is in

IdeaSquare

and in 13-2-005.

but Coffee breaks and lunch are only in IdeaSquare.AIM: to connect CERN with all these potential industrial partners, fostering collaboration, technical exchange, deployment of EU commercial potential. Providing a structured environment for debate, communication and exchange on information and ideas on important topics of the Hi-Lumi project. Developing a dialog between all stakeholders.Investigating bridging solutions between industrial, scientific and commercial concerns to be included in our future CfTDisseminating technical requirements on components and equipment's object of the project scope. M.Losasso cern fp/ktSlide7

7

AGENDA

Welcome & Event presentation

: 9h00 – 9h15

Hi-Lumi project presentation: 9h15 – 10h00Coffee break (served in IdeaSquare) 10h00 – 10h30Procurement presentation: 10h30 – 11h00Technical presentation on Cryogenics, Magnet components, Electronics instrumentation, UHV, Cryostats, Collimators, High precision assembly and manufacturing technology, Q&A: 11h00-13h00Business lunch (served in IdeaSquare): 13h00 – 14h15IdeaSquare presentation: 14h15- 14h30 B2B meeting (in IdeaSquare) and ILOs meeting (in 160-1-009) 14h30-15h30Coffee break (served in IdeaSquare) 15h30 – 15h45B2B meeting (in IdeaSquare) and ILOs meeting (in 160-1-009) 15h45-17h00Closing 17h00M.Losasso cern fp/ktSlide8

8

This event will take place simultaneously in the auditorium 13-2-005 (

Meyrin

site) and at

IdeaSquare (building 3179, Point 1)close to the Globe. Slide9

9

Distribution of registered industry/countries to Hi-LUMI info day

M.Losasso cern fp/ktSlide10

10

have a good Hi-

Lumi

info day! M.Losasso cern fp/kt