/
Spectrometer Solenoids and Coupling Coils Spectrometer Solenoids and Coupling Coils

Spectrometer Solenoids and Coupling Coils - PowerPoint Presentation

marina-yarberry
marina-yarberry . @marina-yarberry
Follow
376 views
Uploaded On 2017-09-28

Spectrometer Solenoids and Coupling Coils - PPT Presentation

Primary Activities and Risks Going Forward Spectrometer Solenoids Completion of SS2 magnetic mapping Completion test and mapping of SS2 Shipping and installation of SS1 and 2 Coupling Coils ID: 591540

cold mass system training mass cold training system shield control risks assembly mitigation magnet cryostat coil fnal cooling circuit

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "Spectrometer Solenoids and Coupling Coil..." is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

Spectrometer Solenoids and Coupling Coils

Primary Activities and Risks Going Forward

Spectrometer Solenoids

Completion of SS#2 magnetic mapping

Completion, test and mapping of SS#2

Shipping and installation of SS#1 and 2

Coupling Coils

Test of

MuCool

coil at FNAL

Cryostat parts fab at LBNL

Winding at Qi

Huan

Cryostating

at FNAL

Test of first CC assembly

Coil Prep at LBNL

Cryostating

at FNAL

Test at FNAL

RFCC IntegrationSlide2

Spectrometer Solenoid Update

Steve

Gourlay

For Steve

Virostek

Lawrence Berkeley National LabSlide3

Topics

Latest

magnet training results

Summary of 2nd magnet progress

Control system upgrade

Risks

and mitigationSlide4

MICE Cooling Channel Layout

Spectrometer Solenoid #1

Spectrometer Solenoid #2Slide5

Current

Progress (1

st

magnet)

The first magnet (designated SS#2) has been successfully trained to full flip and solenoid mode currents

Current was maintained at full flip mode for a period of 24 hours with no quench

All five power supplies were used at various ramp rates and under computer control

Numerous improvements and fixes implemented on control and power supply systems

Improved cold mass heater control loop worked well

Cold mass is being held at 4K and full of

LHe

in preparation for upcoming 3D magnetic mappingSlide6

Working on Both Magnets

Assembly

Training

completeSlide7

Recent Training Runs

HTS lead failure

After warmup, HTS lead replace and cooldown

After

warmup

, control sys

mods

, and

cooldown

Vent line

blockage

Target training current achieved (283 A)Slide8

Final Training ProgressionSlide9

2nd Magnet Progress

The

cold

mass/shield assembly is

complete, MLI wrapped and suspended in

the vacuum

vessel

Installation

of the

cryocooler

tower

is

complete

First stage cooler connections to the thermal shield are being installed

Vacuum vessel end plates are now being welded

LBNL mechanical technicians playing a key role in

assembly (instrumentation, MLI wrap, HTS leads)Slide10

2

nd

Magnet ProgressSlide11

Control

System

Upgrade

A control system review was held at LBNL on December 11

th

and 12

th

, 2012

The LBNL/MICE team

developed improvements from the

numerous

review panel recommendations

The

current system is more

robust

and capable

of

protecting the magnet from potential

failures

A secondary goal

of the upgrade was

to move closer to the final system

to

be operated in the MICE hallSlide12

Control

System

Upgrade

Several

of the

primary upgrades

:

Stand

alone PID controller for the cold mass heater circuit

with current

monitor

Alarm

handler to the control software

Gas

bottle backup

system prevents

negative cold mass

pressure;

improved durability of

PRV’s

New current shunts

directly measure the current

in each coilSlide13

Power Supplies and Control

Power Supplies

New 500 A supply for center and end coils

5 supplies fully integrated

System verified during recent training runs

Control rack

Many upgrades installed

New

heater control

loop

UPS addedSlide14

Upcoming Tasks

3D magnetic bore mapping of first unit using CERN developed system to begin later in May with iron shielding disk in place

Second

unit assembly

to

be

completed

in

next two to three weeks

After vacuum

pumpout

of 2

nd

magnet,

cooldown

and training to start in June

Shipping of fully commissioned magnets to RAL planned for July and SeptemberSlide15

Risks and Mitigation

SS controls operational readiness

certification

Lack of a complete, fully operational and integrated control system led to previous system failures

Some risk remains as the final system to be implemented at RAL is still being developed

Mitigation: numerous upgrades have been implemented and testing during SS#2 training; additional improvements are under way, and the system will be tested during SS#2 mapping and SS#1 training/mappingSlide16

Risks and Mitigation (cont’d)

SS#2 re-train and re-test

Addition of the iron shield for mapping will alter the coil forces and possibly lead to the need for some re-training

Magnet has always required re-training after warm-up and subsequent cool-down

Mitigation:

The cold mass has been maintained at 4K since the completion of the training runs, avoiding any re-training due to thermal expansion/contraction

The forces due to the shield are only a fraction of the nominal inter-coil forces

The training procedure is well establishedSlide17

Risks and Mitigation (cont’d)

SS#2 operational failure with iron shield

Some risk presented as iron shield has never been fitted to the vacuum vessel, and magnet has never been operated with the shield in place

Mitigation:

Iron shield supports designed with conservative safety factors and adequate adjustment capability; fast turnaround modifications possible using Wang NMR and/or LBNL shop

Magnetic forces on cold mass supports are only a fraction of the calculated loads present during operation with other MICE magnets in place; cold mass supports designed and load tested 10% beyond operational requirementsSlide18

Risks and Mitigation (cont’d)

SS#1 train and test

SS#1 represents a newly modified and assembled system that has never been tested in this configuration

Risk areas include: coil windings, cold leads, HTS lead connections, heat leaks, other mechanical systems

Mitigation:

The SS#1 cold mass has been previously trained to ~200 A

The design and as-built configuration of SS#1 is identical to that of SS#2

The same technician crew that assembled SS#2 is also working on completing SS#1Slide19

Risks and Mitigation (cont’d)

SS#1 operational failure with iron shield

The risks and mitigation are the same as those for SS#2

All training and testing of SS#1 will likely be carried out with the shield in placeSlide20

Coupling Coils

Steve

Gourlay

For

Allan

DeMelloSlide21

Coupling Coil Sub-assembliesSlide22

Coupling

Coil Cold Mass

Winding of cold mass coils #2, #3 and #4 by

QiHuan

Company (Beijing, China)

Preparation cold mass coils #2, #3 and #4 at LBNL

Magnetic test of cold mass coils #2, #3 and #4 at FNAL

Risks to schedule

Delay getting superconductor to China

Problem with winding process at

QiHuan

Leak in cooling pipe after pressure test at LBNL

Damage during shipping to FNAL

Problem during magnetic testingSlide23

Coupling

Coil Cryostat

Single Cavity Vacuum Vessel Exploded View

LBNL mechanical shop is in the process of fabricating the first cryostat

Estimated completion on 7-1-2013

Drawings will be updated to reflect the “as built” cryostat

Determine fabricator for the additional 2 cryostats

Risks to schedule

Delay in fabrication process

Vessel not vacuum tight

Damage during shipping to FNALSlide24

Coupling Coil Thermal Shield

Thermal shield design is nearly complete

Drawings

have been red lined but not updated

Some

SINAP parts/drawings will need to be revised for better

manufacturability

LBNL shops will

fabricate

the first thermal shield

Risks to schedule

Delay getting drawings finished

Problem with fabrication process

Damage during shipping to FNALSlide25

Cold Mass Fully Assembled (at FNAL)

Reservoir/cooling circuit installation complete

Cold mass support brackets and band installed

Cold mass wrapped with MLI

Risks to schedule

Delay getting bands fabricated

Leak in reservoir circuitSlide26

Cooling

Circuit

Finalize cooling circuit design

Create detail fabrication drawings

Fabrication of component parts

Assemble components

Risks to schedule

Delay fabrication of component parts

Unforeseen problem during assemblySlide27

CCM Prototype Assembly at FNAL

Cold mass prepared for integration with cryostat

Mount cold mass support bracket and bands

Wrap cold mass in MLI

Assemble thermal shield around cold mass

Wrap assembly in MLI

Insert cold mass into cryostat

Attach cold mass support bands to cryostat

Align magnet in the cryostat

Weld on cryostat tower and inner bore

Risks to schedule

Unforeseen problem during assembly

Vessel not vacuum tightSlide28

CCM Prototype Assembly at FNAL

Weld tower assembly to cryostat

Assemble upper cooling circuit

Attach upper cooling circuit to the cold mass cooling circuit

Risks to schedule

Unforeseen problem during assembly

Cooling circuit leak due to welding error

Vacuum leak in cryostatSlide29

CCM Prototype Assembly at FNAL

Add

cryocoolers

to cooling circuit

Coupling coil training and testing

Risks to schedule

Magnet does not get to cold enough for superconducting operation with

cryocoolers