July 15 2015 Rural Addition Program VA Code 332335 Rural addition funds means those funds reserved from the countys annual allocation of secondary state highway system construction funds as defined in ID: 589867

rural county funds funding county rural funding funds landowners board road construction secondary state 000 addition additions project highway street purpose design

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "Prospective Rural Additions Meeting" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

Prospective Rural Additions Meeting

July 15, 2015Slide2

Rural Addition Program VA Code33.2-335

"Rural addition funds" means those funds reserved from the county's annual allocation of secondary state highway system construction funds, as defined in §

33.2-324

, for the purpose of this section. If such funds are not used by such county for such purpose during the fiscal year they are so allocated, the funds may be held for such purpose for the four succeeding fiscal years. A maximum of five percent of the annual secondary state system highway construction allocation may be reserved by the local governing body for rural additions

.

"Street" means a street or highway shown on a plat that has been recorded or otherwise opened to public use and used by motor vehicles for at least 20 years and that, for any reason, has not been taken into the secondary state highway system and serves at least three families per mile.Slide3

Funding

The county has

$172,000

allocated for

FY2016

for secondary road construction. Rural addition funding is limited to 5% of this total or $8,600. FY 2017 is anticipated to be $230,000 which will generate $11,500 for Rural Additions.The total current funding available is approximately $220,000 for Giles County Rural Additions. Sky View Lane is the next project to be funded.Anticipated Funding:

2015-16

2016-17

2017-18

2018-19

2019-20

2020-21

$172,000

$229,934

$232,154

$247,326

$239,140

$239,140Slide4
Slide5

Other Funding Opportunities

Rural Addition funding can also be provided by landowners along a prospective roadway.

Revenue Sharing funds can be utilized by the County with match coming from landowners. This funding must be applied for and is limited in the

State. Pursuant to §33.2-357, Code of Virginia, every county, whether or not it has qualifying land development ordinances, may use special revenue sharing funds from its “county primary and secondary road fund” to “bring subdivision streets used as such prior to July 1, 1990, up to standards sufficient to qualify” for state maintenance

The County can issue an assessment on taxes to landowners along the street for up to ½ the cost of the project.

  No such special assessment of landowners on such streets shall be made unless the governing body of the county receives written declarations from the owners of 75 percent or more of the platted parcels of land abutting upon such streets stating their acquiescence in such assessments. Slide6

The Process

All landowners must sign the agreement to donate right-of-way.

Our staff must confirm that road is eligible.

The county must prepare an estimate to be given to the Board of Road Viewers. This is a three person board appointed by the Board of Supervisors.

The Road Viewers evaluate the cost benefit ratio and then make a recommendation to the Board of Supervisors.The Board then submits a request to the Virginia Department of Transportation and they have to verify the aforementioned and approve the project.With clearance from VDOT, the County can then locally administer the design and construction fo

the project or choose to request VDOT to administer.

Design, environmental permitting, and design approval by VDOT.

Bid, award, and construction can begin.