I-696 Improvements Cities of Warren, Centerline, Roseville I-696 Improvements Cities of Warren, Centerline, Roseville

I-696 Improvements Cities of Warren, Centerline, Roseville - PowerPoint Presentation

mitsue-stanley
mitsue-stanley . @mitsue-stanley
Follow
366 views
Uploaded On 2018-03-13

I-696 Improvements Cities of Warren, Centerline, Roseville - PPT Presentation

April 2018November 2018 Moving Macomb Overview Project Limits Improvements Cost Anticipated Schedule Maintenance of Traffic Why is this happening next year I75 Mega Project Pavement Conditions ID: 649151

november 2018 project pavement 2018 november pavement project traffic 696 april 2019 communication costs condition current anticipated 2018construction mainline

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "I-696 Improvements Cities of Warren, Cen..." is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

I-696

ImprovementsCities of Warren, Centerline, RosevilleApril 2018-November 2018 Moving MacombSlide2

OverviewProject LimitsImprovementsCostAnticipated ScheduleMaintenance of TrafficSlide3

Why is this happening next year?I-75 Mega Project Pavement ConditionsSlide4

Current ConditionSlide5

Current ConditionSlide6

Project LimitsI-696 from I-75 to I-94Length 10 MilesSlide7

ImprovementsMainline and Ramp InlayBridge Capital Preventative MaintenanceShoulder RepairsService Drive repairs (2019)Slide8

Pavement selectionConcrete is proposedPublic Act 79 (1997) Pavement analysis must be done when pavement costs exceed $1MilCosts based on material prices and overall costs of the life cycle of the road*MDOT Pavement Design and Selection (2012) Slide9

Cost and SchedulePreliminary Budget of $87,000,000 for ConstructionConstruction is anticipated to begin April of 2018 through November 2019 (mainline completed in 2018)Open to Traffic November 2018Slide10

Maintenance of TrafficClose WB I-696 traffic for the duration of mainline project construction April-November 2018Slide11

WB I-696 ClosedSlide12

Official DetourSlide13

Anticipated Milestone DatesPlan Submittal: January 2018Job Letting: March 2018Construction Start: April 2018Open to traffic: November 2018Construction Completion: November 2019Slide14

Communication PlanSlide15

Communication PlanMoving Macomb website (MovingMacomb.org)Public Meeting (October 24th City of Warren (4-7 PM)Social Media (Twitter and Facebook)Engaging StakeholdersDistributing information to stakeholdersSlide16

Questions or CommentsQuestions or Comments regarding the Project