Download Presentation The PPT/PDF document "Village of east aurora sycamore street ..." is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.
Slide1
Village of east aurora sycamore street water improvementsSlide2
Introductions
Clark Patterson Lee
26 Mississippi Street, Suite 300
Buffalo, NY Steven R. Tanner, P.E. – Senior Associate, Phone: (716) 218-4741 Email: stanner@clarkpatterson.comKim Vongries, P.E. – Project Engineer, Phone: (716) 218-4734 Email: kvongries@clarkpatterson.comVillage of East AuroraMatt Hoeh – Superintendent, Department of Public WorksEmail: Matt.hoeh@east-aurora.ny.us, phone: (716) 652-6057Bryan Gazda – Village AdministratorEmail: Bryan.gazda@east-aurora.ny.us, phone: (716) 652-6000Slide3
Project area
South St.
Sycamore St.
Oakwood Ave.Linden Ave.Slide4
Project components
New 8” Class 52 Ductile Iron Pipe and Fittings
New water services to the Right-of-way, including new curb stop and curb box, and connect to existing service lines
Services under the road shall be directionally drilled to limit street disturbanceInstall new fire hydrants and removal of oldRemoval of 5 trees as recommended by independent arborist hired by the villageTunneling under remaining trees along the alignmentSome areas of sidewalk to be replaced
Driveway aprons to be replaced if impactedSlide5
Project schedule
Advertise to bid: second week of February
Bid opening: March 10, 2017
Village award of bid: March 20, 2017Estimated start of construction: Mid-April, 2017Project substantially complete: end of July, 2017Restoration complete and ready for final payment: end of august, 2017Slide6
During construction
Driveway access may be limited from time to time - contractor will be required to notify residents in advance.
There will be dust. Contractor is required to minimize this, however, construction work is dirty work.
Water should only be shut down when the contractor switches the service from the old main to the new main, and notifications will be made. Shut down should last no longer than 4 hours.Accidents do happen. contractor can hit unmarked or incorrectly located services. They will notify residents if home and proceed with repairs.Slide7
Project drawingsSlide8
Project drawingsSlide9
Project drawingsSlide10
Project drawingsSlide11
Project drawingsSlide12
contacts During construction
Clark Patterson Lee
Kim Vongries, P.E. – Project Engineer
Phone: (716) 218-4734 Email: kvongries@clarkpatterson.comSteve Tanner, P.E. – Senior AssociatePhone: (716) 218-4741 Email: stanner@clarkpatterson.comClerk of the Works: To be DeterminedVillage of East AuroraMatt Hoeh – Superintendent, Department of Public WorksEmail: Matt.hoeh@east-aurora.ny.us, phone: (716) 652-6057Bryan Gazda – Village AdministratorEmail: Bryan.gazda@east-aurora.ny.us, phone: (716) 652-6000Slide13
Questions?