/
Accelerated Bridge Construction Accelerated Bridge Construction

Accelerated Bridge Construction - PowerPoint Presentation

myesha-ticknor
myesha-ticknor . @myesha-ticknor
Follow
419 views
Uploaded On 2016-05-07

Accelerated Bridge Construction - PPT Presentation

Bunker Creek Bridge Durham NH By Elizabeth Kinney Advisor Dr Charles Goodspeed Background Originally built in the 1930s Various repairs through the year Substructure mostly original Considerations ID: 309975

site beams concrete current beams site current concrete roadway bridge precast kips daily minimal work area accomplished lane project

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "Accelerated Bridge Construction" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

Accelerated Bridge Construction

Bunker Creek Bridge, Durham NH

By: Elizabeth Kinney

Advisor: Dr. Charles Goodspeed

Background:

Originally built in the 1930’s

Various repairs through the year

Substructure mostly originalConsiderations:High Traffic Volume/Truck RouteLong DetourEnvironmentally Sensitive Area

Oyster River

Bunker Creek

RT 4

Project Concepts

Use ABC methods to complete project as quickly and efficiently as possible using mostly precast/prestressed concrete members

Initial Site Work - minimal daily lane closures

Site Preparation

Column Installation

Bridge Replacement – Full Road Closure

5 to 14 days

Remove current bridgeInstall new bridgePost Site Work- minimal daily lane closuresStone Wall InstallationShoulder Widening on roadway

Columns

Pilecaps

NEXT D Beams

Roadway Widening

Drilled Shaft 1

ft

outside of current roadway.

Cast in place with early high strength concrete.

Shaft will need to extend to +40’ in order to create a moment connection to bedrock. Surrounding soil is clay/silt mixture.

Precast offsite

Current NH truck limit for 8 or more axles is 150 kips without special permits.

Design without cutout was 176 kips, but with cutouts is 148 kips (using 7

ksi concrete)

SIDE VIEW

CROSS SECTION

Granite blocks stacked vertically and tied into bank in order to create a steeper slope that remains within current bank width.

Area will be filled in using geotextiles.

After compaction, a wider shoulder can be added and guard rails moved outwards.

4- 10’ wide NEXT 32 D beams will be used. Due to Flange width, no additional concrete is needed for deck.Beams will be prestressed, precast off site.

Shear connections between the four NEXT 32 D beams will be accomplished with a Tongue and Groove Shear Key that is sealed with a polymer.

Post tensioning will be done using DYWDAG bars. Due to 2% hunch needed in roadway, a coupler will be cut/welded to match the slope. Computer modeling foresees negligible stresses across the center from the hunch, however laboratory tests still need to be accomplished.

NEXT 32D

Carbon Fiber-Reinforced Polymer (CFRP) grid will be used on top and bottom of flange in place of traditional Temperature and Shrinkage Steel.

Portsmouth

Durham