/
Lee County Bridge Replacements Lee County Bridge Replacements

Lee County Bridge Replacements - PowerPoint Presentation

jane-oiler
jane-oiler . @jane-oiler
Follow
394 views
Uploaded On 2016-12-11

Lee County Bridge Replacements - PPT Presentation

Justin Hardee PE Lee County Engineer Overview ALDOT Policy Construction Process Status Lee Countys Bridge Inventory 2010 Bond Issuance for Bridges ATRIP Program In 2010 the Lee County Commission issued approximately 80 Million in Bonds for the purpose of replacing aging bridge ID: 500165

lee county atrip bridge county lee bridge atrip project aldot policy bond bridges contractor work funds road approach completed issuance working construction

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "Lee County Bridge Replacements" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

Lee County Bridge Replacements

Justin Hardee, P.E.

Lee County EngineerSlide2

Overview

ALDOT Policy

Construction Process

Status

Lee County’s Bridge Inventory

2010 Bond Issuance for Bridges

ATRIP ProgramSlide3
Slide4

In 2010, the Lee County Commission issued approximately $8.0 Million in Bonds for the purpose of replacing aging bridge structures in Lee County.

15 structures were originally selected to be replaced using these funds.

8 were completed with Lee County performing our own approach work before ATRIP was announced.

Bond Issuance for Bridges

Slide5
Slide6

The ATRIP Program was announced and Lee County focused on resurfacing for the first two rounds.

Round 3 we decided to utilize our bond funds to expand the impact we could have on our bridges.

Awarded 15 bridges in Round 3.

ATRIP Slide7
Slide8

Lee County committed to use our bond funds for design, right-of-way and all approach work to be performed by the county.

ATRIP was asked to fund 80% of the structure only.

Our Division expressed concerns about the County performing our own work and did not want to allow it.

ALDOT and PolicySlide9

However, in just six (6) months, working with IP Bureau, County Transportation and the ACEA, a policy was established to satisfy ALDOT about the logistics of Lee County and the contractors working on the same project and handling the traffic control and erosion and sediment control from start to finish.

ALDOT and Policy Slide10

Meanwhile, ALDOT restructured its Divisions into Regions and Lee County was transferred to the Montgomery Area of the Southeast Region.

So, our first bridge project was planned under one Division with construction and final closeout administered by the new Region under a new policy.

ALDOT and Policy

Slide11

Lee Road 10, Bridge over Chewacla

Creek

AADT = 2,400

vpd, with 15.4% trucksThis bridge closure cut off interstate access for a quarry, a paving company and a local restaurant.

No onsite detour option available. Detour was 15 miles.High priority project for Lee County.Our First ATRIP Bridge Project Slide12

Road was closed on January 26, 2014.

Required bridge was a 115’ single span on drilled shaft foundations with 1,200’ of approaches.

On March 12, 2014, Lee County began the east approach after the contractor completed the east abutment.

County and contractor working simultaneously on the project.

Our First ATRIP Bridge Project Slide13
Slide14
Slide15
Slide16
Slide17
Slide18
Slide19
Slide20
Slide21
Slide22
Slide23
Slide24
Slide25
Slide26
Slide27
Slide28

Contractor finished barrier rails on May 19th.Grooved the deck on May 20th

.

(This was their last item of work.)

Guardrail was placed by County’s local bid contractor on May 21st.ALDOT performed an inspection on May 22nd.Bridge was opened traffic two (2) days after the completion of the structure.

Opened Road May 22, 2015Slide29

1 -

Bridge Completed

3 - Currently Under Construction

1 - Project Under Contract

10 - Plan Design/Right-of-Way AcquisitionCurrent StatusSlide30

Prior to our bond issuance and ATRIP our average sufficiency rating was a 65.

After we complete these bridges our average sufficiency rating will be an 81.

Lee

County’s Bridge

InventorySlide31

Contact Information:

Justin Hardee, P.E.

County Engineer

Lee County Highway Department100 Orr AveOpelika, AL 36803

Ph: 334-737-7011Questions?