Download Presentation The PPT/PDF document "Steering Committee July 18, 2017" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.
Slide1
Steering CommitteeJuly 18, 2017Tammy Bader, SJRWMDRegional Water Supply Plan Team
www.cfwiwater.com
CFWI RWSP Team UpdateSlide2
CFWI RWSP Team UpdatesScheduleBEBR UpdateWebsite UpdateAgricultural DemandsNext StepsQuestions2Slide3
ScheduleUpdate the ECFT Model to better represent current and future hydrologic conditions in the CFWI Area to assist in planning and future regulatory applications2020
Key Components
Start
End
Regional Water Supply Plan
ECFTX Model Completion
1/1/2015
12/30/2017
Develop population and water demand projections – tabular and spatial distribution 1/1/201512/31/2017Per Guiding Principle 3 – Develop consistent rules (Regulatory Team)4/1/201612/31/2016Update water conservation and reclaimed water estimates and options4/1/201612/31/2018Update water supply and water resource development project options 12/15/20178/16/2018Evaluate and assess water sources12/31/20179/8/2018Produce Draft 2020 Regional Water Supply Plan (first internal draft 6/4/2019) 4/30/201910/9/2020Conduct public workshops and meetings on the Draft 2020 Regional Water Supply Plan2/03/202010/20/2020Governing Board Approvals10/13/202010/20/2020
3Slide4
BEBR StatusParcel level population for CFWIContract executed March 27, 2017Project schedule of 7 monthsFinal deliverable October 31, 20174Slide5
Website Update
Change basics tab to reflect current CFWI news and happenings
5Slide6
Water Demand Methods for PlanningAgriculturalFSAID IV acreage and water demand projections in CFWI planning area (373.709, F.S.)Incorporate North Ranch Sector PlanMonthly time series generated with AFSIRS6Slide7
Next StepsFinalize water demand projections in CFWIWater demand projections outside CFWIWorkshop on projections – Nov/DecBegin update to AWS projectsDevelop outline for RWSP Draft initial RWSP chapters7Slide8
Questions?8