/
Paul Derwent PIP-II  ICR Paul Derwent PIP-II  ICR

Paul Derwent PIP-II ICR - PowerPoint Presentation

pamella-moone
pamella-moone . @pamella-moone
Follow
344 views
Uploaded On 2018-12-19

Paul Derwent PIP-II ICR - PPT Presentation

XX November 2017 Analysis of Alternatives Process March 2016 Letter from S Peggs to E Colby T Lavine M Procario 11817 Paul Derwent ICR Analysis of Alternatives 2 Alternative ID: 744043

linac alternatives analysis mev alternatives linac mev analysis alternative paul icr derwent pulsed 400 risk operations beam 800 existing booster factor current

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "Paul Derwent PIP-II ICR" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

Paul DerwentPIP-II ICRXX November 2017

Analysis of AlternativesSlide2

Process:March 2016: Letter from S. Peggs to E. Colby, T. Lavine

, M.

Procario

11/8/17

Paul Derwent | ICR Analysis of Alternatives

2Slide3

Alternative 1 (800-MeV SC Linac, CW-compatible; Reference Design): 800-MeV superconducting linac, constructed of CW-capable components, operated initially in pulsed mode at an average beam current (during the pulse) of 2 mA, located on the Tevatron infield, accompanied by necessary modifications to the existing Booster/Recycler/Main Injector accelerators. 

Alternative 2 (800-MeV SC Linac, pulsed, higher current)

: 800-MeV superconducting Linac, optimized for low-duty factor pulsed operations, at an average beam current of 5 mA, located on the Tevatron infield, accompanied by necessary modifications to the existing Booster/Recycler/Main Injector accelerators. 

11/8/17

Paul Derwent | ICR Analysis of Alternatives

3Slide4

Alternative 3 (Hybrid; Relocated 400-MeV NC Linac, add 400-MeV SC Linac): 800-MeV linac constructed by adding a 400-MeV superconducting linac, optimized for low-duty factor pulsed operations, at an average beam current of 20 mA, to the existing but relocated 400-MeV Linac, accompanied by necessary modifications to the existing Booster/Recycler/Main Injector accelerators. 

Alternative 4: (Relocated 400-MeV NC Linac, add 400-MeV NC Linac)

: 800-MeV linac constructed by adding a 400-MeV normal-conducting linac, optimized for

low-duty

factor pulsed operations, at an average beam current of 20 mA, to the existing but relocated 400-MeV Linac, accompanied by necessary modifications to the existing Booster/Recycler/Main Injector accelerators. 

11/8/17

Paul Derwent | ICR Analysis of Alternatives

4Slide5

Evaluation CriteriaWere defined by OHEP, for consideration by the project team and the review team

11/8/17

Paul Derwent | ICR Analysis of Alternatives

5Slide6

Review CommitteeAn independent OHEP review committee was formedAuthor / Referee model

No direct interaction with committee

11/8/17

Paul Derwent | ICR Analysis of Alternatives

6Slide7

Project Team ReportProject Team prepared a reportDescribed the 4 alternatives analyzedPrepared cost estimates and life cycle costs

Described the performance with respect to the 10 criteria

Distributed to the review committee and had two rounds of interaction

Questions and responses

Neither project nor committee made a recommendation

“The panel found that the AoA document provides a solid basis for making an alternative selection”

Final report is in pip2-docdb #10711/8/17

Paul Derwent | ICR Analysis of Alternatives

7Slide8

11/8/17Paul Derwent | ICR Analysis of Alternatives

8

Alternative/Criterion

Reference Design

Pulsed SC Linac

NC/SC Pulsed Linac

NC Pulsed Linac

Comments

Beam Power to LBNF (MW)

1.2

1.2

1.2

1.2

For MI operations at 120 GeV

 

Accelerator Complex Reliability (Risk)

Low

Low

Low

Low

Alternatives 3 and 4 ranked low based on PIP investments.

Beam Power to 8-GeV Program (kW)

80

80

80

80

For MI operations at 120 GeV

Upgrade Mu2e 100 kW

Y

Y

N

N

For > factor two increase in beam power and accelerator upgrade <$100M 

 

Platform for LBNF > 2 MW

Y

Y

Y

Y

Requires Booster replacement in all alternatives. Alternatives 3 and 4 have less flexibility, and more technical risk, in achieving >2 MW

Platform for high power, high duty factor

Y

Y

N

N

For accelerator upgrades <$100M

Interruption to operations

Minimal

Minimal

Minimal*

Minimal*

*Assuming the PIP-II shutdown corresponds to the LBNF shutdown. Alternatives 1 and 2 have the potential for an additional 7 months of operations to SBN during nights and/or weekends.

Technical Risk

Moderate

Low

Low

Low

Primary risk in Alternative 1 is resonance control. Otherwise Alternatives 3 and 4 have less inherent risk, but equalized risk at the completion of R&D.

Potential International Contributions

Yes

Yes

No

No

Pursuit of Alternative 2 would forfeit the Indian in-kind contribution of rf sources. No contributions in Alternatives 3 and 4.

Cost to DOE (construction point estimate)

$516

$628

$602

$502

Point estimate, FY2020 $M. The cost risk associated with Indian deliverables that is not incorporated into Alternatives 1 and 2 .

 

Cost to DOE (annual operating)

$9 

$8

$9

$7

Linac only, FY2025 $MSlide9

AoA Best PracticesOHEP reviewed the

AoA

process with respect to GAO Best Practices (Appendix 1 of GAO-16-22 October 2015)

Results summarized in Best Practices document under development

11/8/17

Paul Derwent | ICR Analysis of Alternatives

9Slide10

11/8/17

Paul Derwent | ICR Analysis of Alternatives

10

Alternative SelectionSlide11

11/8/17

Paul Derwent | ICR Analysis of Alternatives

11

Alternative Selection