Stretched Stretched

Stretched - PowerPoint Presentation

phoebe-click
phoebe-click . @phoebe-click
Follow
377 views
Uploaded On 2018-01-08

Stretched - PPT Presentation

wire for HLLHC Brainstorming meeting 11122015 What happens if a wire breaks All the protection brackets must be open The broken wire is removed The cWPS are cleaned with dryair The wire is reinstalled ID: 621487

device wire installed stretching wire device stretching installed protection lhc tasks majority area radiation high brackets side supported top

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "Stretched" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

Stretched wire for HL-LHC

Brainstorming meeting 11/12/2015Slide2
Slide3

What happens if a wire breaks:

All the protection brackets must be open

The broken wire is removed

The

cWPS are cleaned with dry-airThe wire is re-installed:From the fixed stretching device, the wire is unrolled in the protection brackets, and through the sensorsOnce at the second stretching device, the wire is cut, fixed on the weight interfaceThe weight is set on a vertical elevator that goes down, applying tension load very slowly to the wireA displacement test of the wire is done to check that everything is okAll the protection brackets are closed.

Can be done remotelySlide4

For HL-LHC:High radiation area: the majority of tasks will have to be done remotelySlide5

For HL-LHC:High radiation area: the majority of tasks will have to be done remotely

O

ne stretching device on Q1 side will be supported on the top of the cylinder in which Q1 will be installed

The second stretching device will be installed after Q5, where the level of irradiation is far lower.Slide6

For HL-LHC:High radiation area: the majority of tasks will have to be done remotely

O

ne stretching device on Q1 side will be supported on the top of the cylinder in which Q1 will be installed

The second stretching device will be installed after Q5, where the level of irradiation is far lower.

We should foresee an easy procedure of dismounting the wire and its protection if a magnet has to be removed (or if an additional crab cavity has to be installed)The wire will be accessible (on the transport side)Slide7

Different problems must be solved:Installation of the wire

Putting easily the wire under tension

Protection of the wire

Object of this meeting

A first concept was proposed a few years ago by Michel:

Shall we go ahead?

With which tests or tasks?

What are the alternatives?