Schedule Training 101 COMPANY UPDATE Schedule Training 101 LEGAL IMPLICATIONS ACTIVITY MANAGEMENT The CPM network is used to model and communicate an efficient and balanced work plan that considers the conflicting cost time resource risk and quality requirements with the project stakeholders ID: 782028
Download The PPT/PDF document "Schedule Training 101 WELCOME" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.
Slide1
Schedule Training 101
WELCOME
Slide2Schedule Training 101
COMPANY UPDATE
Slide3Schedule Training 101
LEGAL IMPLICATIONS
Slide4ACTIVITY MANAGEMENT
The CPM network is used to model and communicate an efficient and balanced work plan that considers the conflicting cost, time, resource, risk and quality requirements with the project stakeholders. Stakeholders include the owner, field forces, subcontractors, suppliers, upper management, field management, and others.
Slide5CHANGE MANAGEMENT
All significant construction projects experience changes. Changes occur in many forms – oral or written, direct or indirect, and externally or internally initiated. Changes may require expanding the scope of may allow shrinking it.
If a change to the plan occurs, often one or more of the conflicting requirements must be adjusted, and balanced against the
rest. Project
Management techniques can help quantify the effect of added scope. The construction contract should identify which party will bear the burden of the additional cost, time, and resource adjustments. Communicating the analysis to the project stakeholders is a primary responsibility of the effective project manager.
Slide6CHANGE MANAGEMENT
An Error or Omission
Errors or omissions in scope definition of the intended deliverable(s) can become evident as change directives or excessive design clarifications are issued.
Unforeseen Events
Unforeseen events can include: inclement weather, differing site conditions (contaminated soils, harder or softer conditions, higher than anticipated ground water), unforeseen utility conflicts, additional 3
rd
party review, strikes, labor shortages, and material shortages.
General Contractor Performance Issues
General contractors can have procurement, administrative, field management coordination and performance problems.
Subcontractor Performance Issues
Subcontractors can also have procurement, administrative, field management coordination and performance problems.
Program Changes
The end user of the deliverable(s) may direct requirement change
Slide7IMPACTS OF COST
Slide8IMPACTS OF INCREASED SCOPE
Slide9Schedule Training 101
SURVEY RESULTS
Slide10Slide11Slide12Slide13Slide14Slide15Schedule Training 101
TERMINOLOGY
Slide16EXERCISE…
Slide17Terms to Know
Baseline
Schedule
Fragnet
Constraint
Critical
Path
Predecessor
Milestone
Constructability
Notice
To Proceed
Substantial
Completion
Successor
Task
or Activity
Float
or Slack
Early
Activity Start (ES)
Early
Activity Finish (EF)
Late
Activity Finish (LF)
Late
Activity Start (LS)
Slide18Schedule Training 101
PROJECT PLANNING
Slide19Ted Time…..
“Failing to plan is planning to fail”
by J.
Hinze
,
Construction Planning and Scheduling
Planning:
“what” is going to be done, “how”, “where”, by “whom”, and “when”
for effective monitoring and control of complex projects
Slide20REVIEW OWNER CONTRACT
Substantial Completion
Final Completion
Early/Phased Turnover
Coordination of Owner Items
Work Days / Hours
Holidays
Anticipated Weather Days
Slide21REVIEW CONTRACT DOCUMENTS
Building Areas
Floors
Levels
Elevations
What’s consistent? - Take Note
What’s unique? - Take Note
Site Logistics / Phasing
Slide22DETERMINE MILESTONES
Owner Milestones
Design Milestones
Other Milestones
Construction
Progress Milestones:
Foundation Complete
Structure Top-Out
Dry In
Air On
Substantial Completion
Slide23DETERMINE phases
Milestones
Change Management
Preconstruction
Procurement
Sitework & Utilities
Footings & Foundations
Structure
Interior Buildout
Building Envelope
Landscape / Site Improvements
Testing & Commissioning
Closeout
Consider this the table of contents; how the schedule will be laid out. Similar to the chapters of a book.
Slide24Schedule Training 101
SCHEDULE DEVELOPMENT
Slide25scheduling
“it’s about time”
by J.
Hinze
,
Construction Planning and Scheduling
Scheduling:
“what” will be done, and “who” will be working
relative timing of tasks & time frames
a concise description of the plan
Slide26ACTVITY OR TASK DESCRIPTION
CLEAR
CONCISE
SPECIFIC
Each task should be unique and describe the work being performed.
Each task should be able to stand alone and still convey what and where the work is being performed.
Slide27ACTVITY OR TASK DESCRIPTION
BAD: Walls
BETTER: Frame Walls
GOOD: Frame Level 1 Walls
BEST: Frame Level 1 Area B Walls
Example: L1B – Frame Interior Walls
Slide28task duration estimates
Two general rules when estimating task durations:
Overall project duration often correlates to task duration; long projects tend to have tasks with longer durations than do tasks in short projects.
You should measure task durations at the lowest level of detail that is important to you, but no lower.
Good sources of task duration estimates include:
Historical information from previous, similar projects.
Estimates from the people who will complete the tasks.
Colleagues who have managed similar projects.
RS Means and similar publications.
Slide29Task durations
Because inaccurate task duration estimates are a major source of risk in any project, making good estimates is well worth the effort expended.
8/80 rule: This rule suggests that task durations between 8 hours (or one day) and 80 hours (10 working days, or two weeks) are generally sized about right.
Tasks shorter than one day might be too granular, and tasks longer than two weeks might be too long to manage properly.
Slide30MS Project setup
Select
File, Options
,
click on
“
Schedule”
tab
For
Calendar options for this project:
“Select “All New Projects”
For
Scheduling options for this project:
select “All New Projects”
For
New Tasks Created:
select “Auto Scheduled”
For
Duration is entered in:
select
“days”
For
default task type:
select “fixed duration”
Make
sure
New tasks are effort driven
is NOT checked
Click
OK
when finished
Slide31MS Project setup
Click on
Project, Project Information
, select
06/17/16
as the
Start date
, click
OK
Click on
Save as
, type in project name such
as TRAINING_101,
click
OK
Your project is saved as
TRAINING_101.mpp
Slide32MS Project setup
Click on
Project,
Change Working Time
, populate Nonworking days as per the Owner Contract.
Click
OK
Click Save
Slide33Entering task information
Default view,
Entry
table on left,
Gantt Chart
on right
You can delete the two left-most columns, “
i
” and “task mode” by highlighting these columns and pressing the “delete” key (not needed by us)
Task numbers now in left-most column
Enter task name and duration in their field
The default is weeks or
“d”
“d” for days and “h” for hours can be used
Enter predecessor task number(s) in the “Predecessors” field
MS Project
automatically
gives start and finish dates based on critical path analysis
Slide34Entering task information
Default view,
Entry
table on left,
Gantt Chart
on right
You can delete the two left-most columns, “
i
” and “task mode” by highlighting these columns and pressing the “delete” key (not needed by us)
Task numbers now in left-most column
Enter task name and duration in their field
The default is weeks or
“d”
“d” for days and “h” for hours can be used
Enter predecessor task number(s) in the “Predecessors” field
MS Project
automatically
gives start and finish dates based on critical path analysis
Slide35Example sequence
Slide36Example sequence
Task, Duration, and Predecessor Information for Exterior Sequence”
TASK
DESCRIPTION
PREDECESSORS
DURATION
WELD/DECK/DETAIL
-
5
FRAME/SHEATH
EXTERIOR PARTITIONS 1
5
INSTALL
AIR BARRIER
2
2
INSTALL BRICK
3 1
0
INSTALL
THIN STONE
4
5
INSTALL
HORIZONTAL SIDING
5
5
INSTALL EIFS
6
5
INSTALL
ALUMINUM, GLASS, & GLAZING
7 5
Slide37Example sequence
Slide38Task relationships
Slide39Task relationships
Set up Schedule Phases
Set up Milestones
Populate Resource Sheet
Develop Schedule Activities and Logic - Assign Resources at this time.
Tie Logic between the Phases; i.e., Exterior Envelope elements to the Interior Finishes, and Air-On to Interior Finishes.
Tie Logic between like Resources, i.e., *Crew Flow the Schedule.
Tie Milestones to appropriate schedule driving activities; i.e., last structure erection activity to “Top-Out” Milestone.
Sort project by Resource and distribute to for review and buy-in on sequence and durations.
Take a break and review the story being told from a 20K foot level. Are there any glaring errors with sequence, i.e., are we installing drywall before the roof is complete?
Slide40Schedule Training 101
BASELINE
Slide41WHAT IS A BASELINE?
The
baseline of a task is a record of the task's Plan Start and Plan Finish dates prior to any changes being made to those dates.
The
original schedule created at the beginning of the project against which the project’s progress is measured.
The baseline schedule is the set of all task baselines.
Maintaining a baseline schedule provides a record of the original schedule and provides data needed to understand deviations from, AND impacts imposed on the original plan.
Slide42Why establish a BASELINE?
Setting a
baseline is important for tracking and reporting.
It
is equally important to enter each tasks Actual Start and Finish dates, particularly if different than the Baseline dates.
In the figure below I have modified a table to show the Baseline, Actual and current Start and Finish dates.
The
Baseline has been set but Actual dates have not been entered.
Slide43Why establish a BASELINE?
At this point entering any percentage of schedule or work completion will copy the current Start date to the Actual Start.
The
assumption is that if an Actual Start was not entered the task started on schedule. See the figure below.
Slide44Why establish a BASELINE?
Since tasks can be started earlier or later than planned the Actual Start must be entered to model reality.
The
next figure illustrates the task starting a few days later than planned.
Slide45Schedule Training 101
UPDATING
Slide46Ms Project update
Enter Actual Start and Actual Finish throughout given time period between updates – typically a monthly cycle.
Save progress through the end of the period to the shared drive.
Save-As a new file, updating the file name to reflect the new data date.
Open new file.
Under Project Tab, find “Update Project”
Select “Reschedule uncompleted work to start after” and enter the new Data Date
Click OK
Slide47Ms Project update
Slide48Pull planning 101
Slide49What is Pull planning?
A tool
that strengthens our current scheduling process by helping manage risk through detailed collaborative planning and continuous improvement.
A method
of planning where the flow of activities and information are based on the request (pull) of downstream work.
A means
to ensure active involvement from all project stakeholders.
Slide50Why is it used?
Creates a more predictable work flow through collaboration and public commitments
Provides clear picture of the flow of work, handoffs, constraints, etc.
Ensures trade expertise is leveraged
Enables collective understanding
Drives quality and safety through increased accountability and awareness
Brings consistency to our planning process
Helps to eliminate rework
Removes contingency and waste
Slide51Who does it?
Hausmann Construction
Superintendents leads the process, typically with help from assistant super(s), PM, or PE
Trades
Project Manager typically focuses on big picture and has authority to make commitments
Foreman and/or Superintendent is responsible for day-to-day schedule management and provides accurate production rates and manpower to ensure commitments are realistic
Design Team and Owner
Ideally present during phase planning, kept up to date on a regular basis (OAC meeting)
Slide52How does it work?
Develop milestone plan with HCI project team
Develop
phase plan
(activities and sequence of work) as subcontractors are brought on board
Transfer phase plan activities to Microsoft Project or other scheduling program as needed/required
Develop
weekly work plan
(look-aheads) from phase plan
Hold 15-minute huddle with foremen each morning to review activities from yesterday and today
Hold weekly foreman’s meeting to review and update the weekly work plan
Update
Microsoft Project
schedule (weekly/bi-weekly) following weekly foremen meeting
Slide53Milestone plan
Develop milestone plan with HCI project team
Develop
phase plan
(activities and sequence of work) as subcontractors are brought on board
Transfer phase plan activities to Microsoft Project or other scheduling program as needed/required
Develop
weekly work plan
(look-aheads) from phase plan
Hold 15-minute huddle with foremen each morning to review activities from yesterday and today
Hold weekly foreman’s meeting to review and update the weekly work plan
Update
Microsoft Project
schedule (weekly/bi-weekly) following weekly superintendents meeting
Slide54Milestone sticky note
Milestone
Target / critical date
# durations
Slide55Phase plan
Identifies all tasks that must be completed to enable a milestone to be met
Tasks organized on boards identifying the flow of work from week-to-week
Used to build or validate / update the Microsoft Project schedule
Each phase plan typically represents a 3-6 month period
The boards: one column = one week
Task durations limited to 5-15 days (no float / contingency!)
Developed and maintained collaboratively by HCI and trades
Revisited regularly, updated as needed
Trade foremen and project managers required to attend the phase plan sessions
Examples: Top-out, dry-in, lobby finishes, commissioning, etc.
Slide56Phase plan sticky
Task & area
Predecessor
Duration (days)
Slide57Weekly work plan
Breaks down 5-15 day phase plan activities into one day tasks
Each board represents one week, each column represents one day
Developed and updated collaboratively once a week at foreman’s meeting
Reviewed (not modified) daily with foreman each morning (15 minute huddle)
Weekly updates used to inform / update
the Microsoft Project schedule
Must be regularly compared to phase plan / Microsoft Project schedule
to ensure dates and milestones are being met
Trade foremen required, project managers welcome to join weekly update meetings
Examples: Form pier caps 1-5, rebar for pier caps 1-5, pour concrete for pier caps 1-5
Slide58Weekly work plan sticky
Task & area
Predecessor
Crew size
Slide59Root-cause analysis
Why
didn’t we finish that activity?
The material wasn’t delivered.
Why
wasn’t material delivered?
We were waiting on shop drawings.
Why
were we waiting on shop drawings?
Because the manufacturing detail had not been secured.
Why
not?
We changed manufacturers three weeks ago.
Slide60Team meetings
Milestone planning meeting
:
HCI project team
Project scope overview
Review project milestones
Review / define the phases of work
Phase planning meeting
:
HCI and applicable trades
General process overview
Review milestones
Develop phase plan – (particular phase identified prior to meeting)
Weekly work plan meeting
:
HCI and applicable trades
Review applicable phase plan(s)
Break down phase plan tasks into one day activities