APA Doublet Assembly and Ash River Dan Wenman August 26 2019 Outline Installation of fixture Week of June 24 th Week of August 12 th Assembly of the APA Pair Still to do Documentation August 26 2019 ID: 772248

assembly apa august doublet apa assembly doublet august ash river lab sciences 2019 physical beam actuator pins stabilizer pendant

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "APA Doublet Assembly and Ash River" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

APA Doublet Assembly and Ash River Dan WenmanAugust 26, 2019

Outline Installation of fixture:Week of June 24thWeek of August 12th Assembly of the APA Pair Still to do Documentation August 26, 2019 Physical Sciences Lab | APA Doublet Assembly at Ash River 2

Week of June 24th Inspection of towerAs inspected the tower was not perfectLeaned to the North ~2cm The south column leaned to the west ~1cm Installation of the ladder structure and actuator stand Ladder and actuator stand was anchored as far north as possible Discovered that the “button” on the back of the pin assemblies interfered and did not allow for full retraction.Note: More accommodation fo r construction of tower is needed. August 26, 2019 Physical Sciences Lab | APA Doublet Assembly at Ash River 3 N W “Button” that needed to be shortened

Week of June August 12th Survey and adjustment of the stabilizer pinsModified pin assemblies were installedAll stabilizer assemblies were adjusted to their nominal position and the stabilizer rails were adjusted to be vertical Pins positions were surveyed Lowest pin on the South side did not have enough adjustment, so it had to be removed and slots increased. All pins were adjusted. Second survey indicated that two pins were still out of positionPins were adjusted and resurveyed. All pins within 1mm except 2 pins were ~2mm east and west. August 26, 2019 Physical Sciences Lab | APA Doublet Assembly at Ash River 4 Image of survey process. Kyle Zueg operated the survey instrument

Week of August 12th Actuator standAll the wiring for the actuator stand was routed and connected by Kantor ElectricCharles Cadeau programmed the drive. Initially could control directly from the drive, but not the pendant Charles found that the pendant was provided with a jumper between the up and down switches. Down limit, up limit, and PD cable position switched have been set.Slow zone LED did not work and is being replaced. August 26, 2019 Physical Sciences Lab | APA Doublet Assembly at Ash River 5 Down limit, PD cabling position, Slow Zone, and up limit switches Drive box Pendant Disconnect

APA doublet assembly APA frames were staged on the West wallBottom APA transferredLifted with two straps. (Method for DUNE TDB) August 26, 2019 Physical Sciences Lab | APA Doublet Assembly at Ash River 6

APA doublet assembly Bottom APA transferredPositioned on the actuator stand.Actuator beam guide did not have enough compliance and the guide was loosened to increase compliance but not removed. The bottom APA was stabilized. August 26, 2019 Physical Sciences Lab | APA Doublet Assembly at Ash River 7 Actuator beam lower guides

APA doublet assembly Top APA transferredlifted with Lifting beamLinks installedRolled into position on segmented beam and stabilized. August 26, 2019 Physical Sciences Lab | APA Doublet Assembly at Ash River 8 Lifting beam Beam to beam connection Segmented beam

APA doublet assembly APA pair connectedA minor interference with two PD cable hold-downs was discovered and hold-downs were removed.Initially shoulders of link screws hung up on link hole. It was easy to see and fix. Must make sure link screws are fully engaged. August 26, 2019 Physical Sciences Lab | APA Doublet Assembly at Ash River 9 Links Link screws

Still to do ActuatorModify the constraint for lowering of the actuator beam. Several ideas are being considered.Pendant Switch up and down buttons and pot direction Replace red LED and set “slow zone” switch Improve Operation Manual Move stabilizer brakes to the scissors lift sideHave APA move the PD cable anchorsIncrease adjustment range of stabilizers for DUNE August 26, 2019 Physical Sciences Lab | APA Doublet Assembly at Ash River 10

Documentation Mechanical drawings and analysis documents are on EDMSElectrical schematics will be put on EDMS August 26, 2019 Physical Sciences Lab | APA Doublet Assembly at Ash River 11

Back up slides August 26, 2019Physical Sciences Lab | APA Doublet Assembly at Ash River 12

APA Assembly Fixture –Ladder Frame August 26, 2019 Physical Sciences Lab | APA Doublet Assembly at Ash River 13 Bottom Frame Top Frame Middle Frame

Stabilizer August 26, 2019Physical Sciences Lab | APA Doublet Assembly at Ash River 14

Standoff for lifting the bottom APA August 26, 2019Physical Sciences Lab | APA Doublet Assembly at Ash River 15