/
Electrical network: Electrical network:

Electrical network: - PowerPoint Presentation

sherrill-nordquist
sherrill-nordquist . @sherrill-nordquist
Follow
378 views
Uploaded On 2017-03-20

Electrical network: - PPT Presentation

18 kV network review and status of the SPS consolidation plan D Bozzini on behalf of ENELHT With the contribution of ENELOP section members and in particular G Fernqvist G Cumer ID: 526800

network sps joints failure sps network failure joints case ba4 failures analysis cables substations procedure cable ti8 consolidation pulsed

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "Electrical network:" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

Electrical network:18 kV network review and status of the SPS consolidation planD. Bozzini on behalf of EN-EL-HTWith the contribution of EN-EL-OP section membersand in particular G. Fernqvist, G. Cumer & C. Jach

ATOP Days - Session 4 - Technical infrastructure Slide2

OutlinePART I Major events on HV electrical cable network in 2008 Major events on HV cells in 2008 Historical trend of failures on the SPS 18 kV network CASE 1: The 2008 SPS joints crisis CASE 2: BQ1 Compensator CASE 3: RESTO 1PART II SPS Consolidation, status and future program BE-TI8 network layout SMB: what do we do? Failure location on HV cables networkCONCLUSIONS Slide3

Major Events on HV Electrical cables Network SPS 18 kV network6 cable failures on the 18 kV network (Including the 4 ones mentioned by P. Sollander)2 on the pulsed TI8 network, stop of the SPS machine (2001)3 on the pulsed network, operation of SPS possible in open loop (1970)1 failure on the SMB1, redundant network available (1970)BEQ1 CompensatorFailure on a 18 kV cable head of the BEQ1 feeder in BE substation, fortunately not in operation during failure period (

2003

)

RESTO 1

Meyrin

Elastimold

18 kV elbow connector on a transformer powering the general services of

Resto

1. (

2001)

Near miss failure detected tanks to the preventive maintenance and the reinforced visual inspections of the installation by the operation section.Slide4

Major Events on CERN HV cellsME24 cell explosion ( 1995)10 days stop of the machines feed through the ISOLDE loopSE18 near miss ( 1995)Preventive action takenProblem limited to FLUAIR cell type on Meyrin substations and SE18Monitoring of temperature and humiditySystematic Partial Discharge (PD) corona effects measurementsVisual inspection inside cells whenever accessible Comments: In the past 5 years, 2 similar accidents and 3 near miss !

ME59

switch closing failure during auto-

tranfer

exercise (

 19

68)

Design life time 25 years, continuous operation at CERN 41 years !

Comments: Remember the 29 July 2006, same type of

equipment !

ME9 Jura substation (

 19

68) critical installationSlide5

Historical trend of failures on the 18 kV SPS networkNature of the failures A) Aged cables, made with XLPE affected by water-treeing effect B) Not directly the cable but the accessories (joints, terminals)

Remarks for 2008

4 out of 6 failures affected recently installed SPS network segments (

 2001)

2 remaining failures on old cablesSlide6

CASE 1: SPS joints crisis (1) - FailuresSlide7

CASE 1: SPS joints crisis (2)- AnalysisSlide8

CASE 1: SPS joints crisis (3) - AnalysisAnalysis of the jointsConclusions of ALL 8 joints examined

ASSEMBLY PROCEDURE NOT FOLLOWED

POOR QUALITY OF WORKSlide9

CASE 1: SPS joints crisis (4) - RepairCorrective actionsRepair of all joints that failedPreventive actionsReplacement of all jointsImprovement of the shielding continuity across the joints 2 new joints for each repair/replacement

Now we have 80 joints instead of 40Slide10

CASE 1: SPS shield currentsPreventive action68/80 joints have a reinforced shield continuityModified assembly procedure approved by joint manufacturerStandard

Reinforced shield continuity

Signs of heating confirmed by the conclusions of the joints analysis

This triggered a campaign to measure shields currents

Sources and reasons not yet fully understood

100 A/divSlide11

CASE 2: BEQ1 compensator – 18 kV cable terminal failureConclusionASSEMBLY PROCEDURE NOT FOLLOWEDPOOR QUALITY OF WORK

Failure on a 18 kV cable terminal

Date of installation 2003, place BE, Indoor

Discharge to ground without load

Analysis by third party (

Cellpack

Laboratory, DE)

Outcome of the analysis

Length of insulation dimensions not done according to the procedure

Use of inappropriate tooling (knife) causing serious weaknesses on the insulationSlide12

CASE 3: RESTO 1 - Elastimold 18 kV elbow connector failureFailure on a 18 kV Elastimold connector Date of installation 2003, place Bdg 500, Indoor Discharge to ground, circuit was on load Analysis by third party (Cellpack Laboratory, DE)Outcome of analysis Preparatory dimensions not done according to the procedure Use of inappropriate tooling (knife) causing serious weaknesses on the insulation

Conclusion

ASSEMBLY PROCEDURE NOT FOLLOWED

POOR QUALITY OF WORKSlide13

SPS Consolidation - Status on March 200918 kV cable network (SMB not included) and substationsMarch-09

Segment

Length

Stable

Pulsed

[m]

Done

Done

BE-B3

350

350

350

B3-B4

1300

1300

1300

B4-B5

1350

1350

1350

B5-B6

1260

 

 

B6-B7

550

550

550

B7-B1

1100

 

 

B1-B2

1520

 

 

B2-BE

1100

1100

 

Total [m]

8530

4650

3550

Done [%]

 

55

42Slide14

SPS Consolidation – Short term work planFrom March 2009 till December 2010Install cables between BA6-BA6 (2X), BA1-BA2 (2X), BA2-BE (1X)Digging  6.6 kmPrepare renovation of substations BA4 and BA2Define and implement scheme for parallel coupling of the BE-TI8 antenna with BE-BA4 pulsed loop

During shutdown

2010-2011

Commissioning of installed cables

Renovation

and commissioning of substations in BA4 and BA2

Installation and commissioning of parallel coupling BE-TI8 with

BE-BA4 pulsed loopSlide15

SPS Consolidation – Mid term work planBy the end of shutdown 2012Installation and commissioning of cables between BA4-BA1 (2X)Digging  1.1 kmRenovation and commissioning of substations BA1 and BA3By the end of shutdown 2013

Renovation and commissioning of substation BA6Slide16

BA4-TI8 network layoutSituationPower line added in 2004 to power the CNGS experimentOn this line we also have the SPS stable network for BA4Not being part of a loop -> no redundancy for powering CNGS and SPS pulsed network in BA4Consequences

If a fault appears on this line (ex: joint to be replaced), one week of shut down minimum

Remedies

Implement

possibility to operate the TI8 line in // to the SPS pulsed loop from BE to BA4Slide17

SMBConsequencesIf a fault appears on this line, one week of shut down minimum of the affected segmentHow to proceed?1) Receive guidelines whether to include these circuits in the EN/EL SPS consolidation mandate or:2) as recommended by the ATC on 27th Oct. 2006 study and find procedures for a fast repair and shorten DTTR

Situation

Old power lines affected by water treeing effect

(

 1970)

Failure rate going up with the time

Operation is not 100 % redundant (see 4

th

ATC minutes 27

th

October 2006)

Fully operated by TE-EPC, maintained by EN/ELSlide18

Failure location on HV networkCurrent procedureAs soon as a failure is detected, ERDF (Electricite Reseau Distribution France) is contacted and they intervene on average within three days to precisely localize the failure.Technique In most of t he cases reflectometry coupled with a pulsed surge generator.LimitsTime of intervention depends on availability of ERDF. Also to consider that EDF network diagnostic has priority with respect to CERN

.

How to improve

EN/EL has almost all the equipment to perform the same type of diagnostic

A bit old but can be upgraded with a dedicated budget

Today there are weaknesses on expertise, but if necessary on a short mid term period we can envisage to set up a EN/EL team for such diagnostic

What is needed?

Dedicated personnel, time for set-up and time for training on real casesSlide19

CONCLUSIONFailures6 out of 8 major failures or near miss are related to bad assembly of HV componentsFor the SPS, except for the “joint crisis”, 2008 as not been a bad year, 2 faults due to aging cables. One affecting SMB. But…remember what we saw on the video!Cells and substations: let us not underestimate the status of ME59 and ME9Serious problem of HV components assembly qualityIdentification of specialized firms in ongoing with good resultsIn-house expertise must be improved in

order to follow the execution of repair

High currents in SPS shields

Require more time to investigate the sources of these currents

Consolidation of SPS 2009-2010 (assuming LHC will run over the winter)

Installation of cables on two segments (BA5-BA6 and BA7-BA1)

Re-configure substations in BA2, BA4 and improve the TI8 network layout

Require solid budget and availability of sufficient and fully qualified personnel

SMB: We need to know now what to do

Failure location: there is room for improvement of the MTTR