Download Presentation The PPT/PDF document "Resources" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.
Slide1
Resources,Scheduleand RiskManagement
Pierre Bonnal
CERN
DG-DI Projects Support
Office
1
st
HiLumi
LHC Collaboration Meeting
16
th
to 18
th
November 2011Slide2
OutlineRationale
Project Management Best Practice
Resource and Cost Management
Schedule ManagementRisk ManagementConclusion
2011-11-17
Pierre Bonnal — Resources, Sched. & Risk Mngt
2Slide3
RationaleLimited resources optimized sharing
Public
funding
transparent reportingHow and when we intend to use the moneyThen, what was bought with this moneyFunding agencies generally want to know:Technical feasibility
regular reviews + reports
Financial feasibility cost estimate + budget
Time feasibility master / co-ordination schedules
Uncertainties risk register + mitigation
measures
2011-11-17
Pierre Bonnal — Resources, Sched. & Risk Mngt
3Slide4
How to proceed?Implementing best practices
in
matter
of large-scale project management,appropriately2011-11-17
Pierre Bonnal — Resources, Sched. & Risk Mngt
4Slide5
2011-11-17
Pierre Bonnal — Resources, Sched. & Risk Mngt
5Slide6
2011-11-17
Pierre Bonnal — Resources, Sched. & Risk Mngt
6Slide7
Starting Point Scope of WorkClear description of the
deliverable
(
s)PBS = Project/Product Breakdown StructureClear description of the activities to perform
WBS = Work Breakdown Structure
This
is an on
-
going exercise
Some WP Holders
have already
received a
draft WBS for comments
2011-11-17
Pierre Bonnal — Resources, Sched. & Risk Mngt
7Slide8
Resource Management Budgeting
This requires discussions with
WP
Holders, Project Leaders,
Departmental Planning Officers
to agree upon a
resource
management approach
2011-11-17
Pierre Bonnal — Resources, Sched. & Risk Mngt
8Slide9
Resource Management EVM
This requires discussions
with
WP Holders,
Project
Leaders
,
D
epartmental
Planning Officers
to agree upon
an EVM reporting approach
Reporting
2011-11-17
Pierre Bonnal — Resources, Sched. & Risk Mngt
9Slide10
Schedule ManagementA4-format
Master Schedule
to be released soonCo-ordination Schedules:Design + Procurement Co-ordination Schedules responsibility of the Work Package Holders
Installation Co-ordination Schedule EN-MEFto be embedded in LS2 and LS3 installation schedules
HW + Beam Commissioning Schedules in due time
2011-11-17
Pierre Bonnal — Resources, Sched. & Risk Mngt
10Slide11
Risk Management Risk Register
Identifying risks
(threats + opportunities)Evaluating their likelihood × impactImpact on Performance*
* incl. safety + facility integrityImpact on Schedule
Impact on ResourcesSetting-up
mitigation
measures
Risk: effect of uncertainty on
objectives
(ISO 31000:2009 § 2.1
)
2011-11-17
Pierre Bonnal — Resources, Sched. & Risk Mngt
11Slide12
Management Systemthat:Fulfills PM best practices
Is useful to project members
Is painfulness to feed, to update
2011-11-17Pierre Bonnal — Resources, Sched. & Risk Mngt
12Slide13