/
Module 11 -Cost Estimation Module 11 -Cost Estimation

Module 11 -Cost Estimation - PowerPoint Presentation

stefany-barnette
stefany-barnette . @stefany-barnette
Follow
445 views
Uploaded On 2018-02-01

Module 11 -Cost Estimation - PPT Presentation

This module covers how to estimate project costs including Equipment costs combination of procurement and installation including construction costs associated with the microgrid equipment Design costs costs for AampE to perform a detailed design as well as a portion of the engineerin ID: 627018

equipment costs installation building costs equipment building installation cost microgrid design storage bldg overhead engineering system generation controls total chp 2013 buildings

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "Module 11 -Cost Estimation" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

Module 11 -Cost Estimation

This module covers how to estimate project costs including:Equipment costs – combination of procurement and installation (including construction) costs associated with the microgrid equipmentDesign costs – costs for A&E to perform a detailed design as well as a portion of the engineering analysis necessary to design a microgridEngineering costs – costs to do detailed engineering analysis of the performance and controls for the microgridOverhead costs – costs associated with other entities such as city or military personnel, regulatory agencies, etc. necessary to install the microgridIf overhead costs are not known, these costs are factored into the 25% contingency cost factor to estimate overall costs for a project

1Slide2

Elements of cost estimation

To simplify the cost calculation, the cost components are broken down into the following categories:Installation Costs – costs to procure and install all equipment involved in conceptual designs including construction firm overhead costsCost for construction overhead for installation can be optionally be calculated separately from equipment procurement costs and then tabulated as long as this is done consistently throughout the estimation processDesign and Engineering Costs – costs for detailed A&E firm design plans, and engineering involved in installation, testing and final implementation of conceptual design. Estimated to be 25% of the total installation costsContingency Costs – Additional 25% contingency added to account for unanticipated costs associated with the conceptual design such as base or city planning related costs.

Overall Construction Costs – Sum of installation, design and engineering as well as contingency costs. Approximately 1.5X of installation costs

If any of these costs are more directly known, for example design costs are $350K, from an estimate from an A&E firm, these costs can be substituted for this formula used to estimate these costs.

2Slide3

Installation costs

Installation costs include the following cost componentsDistribution Infrastructure CostsGenerator CostsCyber Security and Controls CostsRetrofit Costs (if needed)CHP, PV and Energy Storage (if included)Labor for installation

3Slide4

Distribution infrastructure costs

Distribution infrastructure costs are all costs associated with connecting clusters of buildings together using underground or overhead conductors. This includes:Cabling – costs of conductors (overhead (OH) or underground (UG))Trenching and Conduits – trenching, duct bank and conduit costs for UG cables; OH conductors would be costed for pole structuresManholes – access to buildings and connections for UG systemsTransformers – it may be necessary to install transformers to connect building loads to the microgrid if existing transformers cannot be used; transformers are also needed to step up voltages from generators to medium voltage levels

4Slide5

Generator costs

Generator costs are all costs associated with providing N-1 redundant generation to individual buildings or clusters of buildings. This includes:Generators – Natural gas, diesel, microturbines, fuel cells, etc. which supply the main energy source to the microgridATS – Automatic transfer switches to connect and disconnect backup generators from critical building loadsParallel Switchgear – In some cases more expensive parallel switchgear is required to connect multiple generators togetherAdditional Fuel Storage – Additional fuel tanks to supply diesel fuel to diesel engines for longer duration outages; can also use propane storage for natural gas engines; some engines are rated for other sources like JP or biofuels during emergency conditions

5Slide6

Retrofit costs

Retrofit costs are all costs associated with upgrading building service equipment to meet the DBT, such as raising equipment for flood conditions. This includes:Relocation of Service equipment – Switchboards, panelboards, transformers, and wiring to be above the DBT for the buildingNew Equipment – if equipment cannot be relocated, additional or duplicate equipment must be provided

Demo/Restructuring – Any costs associated with demolition and restructuring of the existing building structure in order to be able to supply power to meet the DBT

6Slide7

Example of retrofits

Flood Zone

Raise equipment above flood zone

Install additional

Backup generation

Building

Building electrical infrastructureSlide8

CHP, PV and energy storage costs

CHP, renewables and energy storage are all costs associated with utilizing any of these opportunities with the conceptual designs to provide additional benefits. This includes:CHP – combined cooling, heating and power; excess heat of building used to supply building heating and cooling relieving electrical requirements and making system more reliableRenewables – use of renewables to offset generation use to reduce fuel requirements and emissionsEnergy Storage – use of energy storage to provide non-interruptible power to certain loads or other applications such as smoothing PV and ramp rates of generators to make system more efficient

8Slide9

Example CHP benefit analysis

Location

CHP Size (kW)

Peak Electric Load (kW)

Electric Savings ($2013)

Natural Gas Savings ($2013)

CHP NG Costs ($2013)

O&M Costs ($2013)

Net Savings ($2013)

Installed System Cost ($2013)

Payback (Years)

Bldg

A

100

142.7

$70.6k

$33.0k

$73.9k

$8.0k

$21.7k

$221.0k

11

Bldg

B

37.5

56.4

$40.7k

$16.7k

$30.0k

$6.1k

$21.3k

$81.0k

4

Bldg

C

15

20.7

$9.9k

$5.6k

$9.0k

$1.5k

$5.0k

$27.0k

6

Bldg

D

100

142.7

$62.6k

$33.0k

$75.2k

$8.0k

$12.4k

$224.9k

19Slide10

Example PV benefit analysis

Service

Usable

PV Output

(kW)

System

Cost

Energy

Value

Payback:

(years)

Bldg A

550

$2635k

$156.6k

10.5

Bldg B

360

$1724k

$102.5k

10.5

Bldg C

300

$1437k

$85.4k

10.5

Bldg D

240

$1150k

$68.4k

10.5

Bldg E

210

$1006k

$59.8k

10.5Slide11

Cyber security and control costs

Cyber security and control costs are all costs associated with providing cyber security and controls to individual buildings or clusters of buildings. This includes:Control infrastructure – Costs to install communications infrastructure necessary for microgrid controls (including monitoring, cyber security and protection)Control Center – Laptops, pagers, etc. with different levels of access to monitor and control microgrids Generator Controls – Local as well as overall supervisory controls involved with synchronization, startup and outputs of generators and isolation devicesSystem Protection – Devices involved in detecting and clearing faults which may occur within microgrids

11Slide12

Microgrid Element Costs

12COST ESTIMATE WORKSHEET

Equipment/Approach

Equipment and Installation Costs ($K)

Construction Overhead(20%) ($K)

Design

Overhead

(12.5%) ( $K)

Engineering Overhead

(12.5%) ($K)

Total

Costs

($K)

Total Costs with Contingency (25%) ($K)

Pin and Sleeve

 

 

 

 

 

 

Building rewiring

10

2

2.52.5

1721.5Pin and sleeves1022.52.51721.5Portable GeneratorsCost

    2 x Cost     

  Individual Building Hardening      Building rewiring

1022.52.51721.5Building GeneratorsCost  

  2 x Cost

  

   

  Microgrids

 

  

  

 Controls100202525170215Fiber Optic Communications50

106.256.2572.5090Building rewiring100201313146

182GeneratorsCost    2 x CostTrenching and Cable50/1000 ft

    100/1000ft     

  

PV  

   

 Installed Costs

 

  

 3.50/kW 

PPA    0.12/kWhr    

    Batteries      

Installed costs    4.25/kW    

    CHP     

 Installed costs 

  

 2.25/kW 

MA Incentive 

   (0.75/kW)       

 Fuel Storage

2/1000 gal   4/1000 gal     

   Slide13

Example system

13Slide14

Example system load data

14Slide15

Example system with microgrid

15Slide16

Cost calculations for example microgrid

16Slide17

Another example microgrid

17

900 kW

New Diesel

Generation

Utility Power

Dedicated

Microgrid

Feeder

(Existing Conduit)

Other

Loads

100 kW Solar PV Array

50 kW Microturbine

200 kW Diesel Generator

600 kWh Battery Storage System

Tie to Storage

Resources

Critical Building Loads

Breaker

Breaker

SubstationSlide18

Cost spreadsheet with engineering, design and contingency costsEquipment

Equipment and Installation costs ($K)

Construction OH (20%) ($K)

Design OH (12.5%) ($K)

Engineering OH (12.5%) ($K)

Total Costs ($K)

Total Costs with Contingency (25%) ($K)

 

 

 

 

 

 

 

Microgrid Breaker

100.0

20.0

12.5

12.5

145.0

181.3

Underground Feeder

530.0

106.0

66.3

66.3

768.5

960.6

Microgrid

Controls

375.0

75.0

46.9

46.9

543.8

679.7

Misc Equip

250.0

50.0

31.3

31.3

362.5

453.1

 

 

 

 

 

 

 

Total w/o Generation

1255.0

251.0

156.9

156.9

1819.8

2274.7

 

 

 

 

 

 

 

Generation

 

 

 

 

 

 

1600 kW New Generation

1200.0

240.0

150.0

150.0

1740.0

2280.0

 

 

 

 

 

 

 

Total w/generation

2455.0

491.0

306.9

306.9

3559.8

4554.7

18