/
Forthcoming work on the beam Forthcoming work on the beam

Forthcoming work on the beam - PowerPoint Presentation

tatyana-admore
tatyana-admore . @tatyana-admore
Follow
407 views
Uploaded On 2016-10-23

Forthcoming work on the beam - PPT Presentation

Lau and Niels NA62 TD meeting 17 March 2014 Outline Complete the crane consolidation in TCC8 Reinstall frontend after alignment checks Consolidation of T10 target Close up roof shield above front ID: 479561

system tcc8 ventilation crane tcc8 system crane ventilation t10 separation vacuum target beam test magnets double consolidation work wall

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "Forthcoming work on the beam" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

Forthcoming work on the beam

Lau and Niels, NA62 TD meeting, 17 March 2014Slide2

Outline

Complete the crane consolidation in TCC8

Reinstall front-end after alignment checks

Consolidation of T10 target

Close

up roof shield above front

end of beam

New location for fast valve, move 2

magnets

Double separation wall

Temporary modifications to ventilation system

Prepare final ventilation system renovation

Complete vacuum

All the rest

…..Slide3

Crane consolidation

The mechanical work on the TCC8

crane has been completed.Still some remaining work on the

electrical distribution.

The crane delivery is foreseen for

end March (possibly March 18

th

).The new crane has no ‘guirlande’, but is powered via a rail.This makes the air separation between TCC8 and ECN3 much easier.Quite some work depends on the availability / reliability of the TCC8 crane!Slide4

Reinstall beam front end

Due to asymmetric profiles and

slightly low kaon rate, the

alignment

of the beam front end

has been verified in detail.

This included an insert in T10.This required dismantling of the roof shield and of the TCX dump and of the first QNR quadrupole.Also one MTR dipole in next tothe TAX had to be turned by 180o. The TCX and magnets have to be reinstalled, as soon as the crane

is availableSlide5
Slide6

Contrôle 3D (AT401).

 

T10 insert

At some stage

…..

Now

Ecart Alti. : +0.16mm

Ecart radial: -0.25mm (coté Salève)Slide7

QNR

TCX

Both are self-aligning

Reinstallation as soon as

the

TCC8 crane is available againSlide8

T10 target consolidation

All the mechanical parts of the T10 target will be replaced

Specification in EDMS document 1267311The shielding itself will be preserved

Replace target box with identical spare

Different target materials were studied, but stay with Beryllium

Replace the T10 collimator

The TBIU unit will be replaced with a new box, containing

- a BSI (Titanium foil for intensity measurement) - Two BSPH, two BSPV (split foils) - BBSH and BBSV (SEMP profile scanners) - Two halo foils with slits of 145x2.5 mm (one horizontal, one vertical)

All this will be properly aligned and testedSlide9

Close roof shield

Once the alignment of T10 and the from end is done, the roof shield will be completedSlide10

Fast valve relocation

Now that we have agreed to install only one fast valve, it was deemed to install it as far downstream as possible, i.e. just upstream of GTK3.

The 32 cm of longitudinal space required implied a displacement of the two last achromat-2 magnets by 32 cm.

The magnets

will be reinstalled

soon (requires

TCC8 crane).Slide11

Double separation wall

The order has been placed with

Sarvadon

. Also a separation will be made in GHN300Slide12

Ventilation system for 2014

With the double separation wall in place, the air separation between ECN3 and TCC8 should be OK, apart from leaks between the ventilation units.

CV will take care of the pressurization of the double wall.

Therefore we will STOP the ventilation in TCC8 in the technical run at the level of the double wall with dampers. This should rather efficiently stop the

air flow from TCC8 into ECN3.

With those measures the operation of the ventilation system should be

close to the final version, apart from the bad shape of the ventilation units.Slide13

Ventilation system for 2015+

The study of the final ventilation system is in progress.

Information will be made available on EDMS doc 1354745.

Installation is foreseen during the first half of 2015, before the start of the 2015 physics run.Slide14

Remaining work on vacuum system

The beam line vacuum remains to be remounted and leak tested, following the various modifications.

The control is being implemented by the vacuum group

The expansion vessel next to the RICH remains to be connected.

T

he blue tank vacuum is on track. The planning for commissioning is tight due to late closing of the tank (detector arrival) and one should be aware that commissioning can take more time e.g. in case of leaks. As discussed before.

It is important to close the tank as early as possible

.Planning:Pumping test for K12, leak test, final test of control system (probably) fits with NA62’s proposed vacuum test in July - August 2014. Performed jointly by EN/MEF and TE/VSC (knowledge transfer).

Final test with full gas load = pumping before & during physics run.Will be

executed

by EN/MEF,

but

under the expert eye of TE/VSC.Slide15

Other issues

The GL vs

I curve of QNL magnets will be measured and parameterised.This should lead to an even better understanding of the optics of P42 (and K12).

We have also a better understanding of the gradients in QNR magnets.

Understand / confirm orientation (H/V) of 4-jaw

collimators.

Consolidation and realignment of T4 target (late Summer).

Replace 200 mm head by a 180 mm head (slightly better for T10 flux).The gas extraction and the H2 infrastructure must be installed → see next slideThe RP monitoring system will be completed.Minor improvements to the side shielding of the K12 TAX.Install a fence at

the entrance to the dump tunnel.Cesar upgrade, details still to be finalised.Not discussed here: infrastructure not directly related to beam (rack cooling,

etc

)Slide16
Slide17

To be updated after crane renovation in TCC8

TCC8 & ECN3 planning SBA (January)Slide18

L.Gatignon, SPSC112, 14-01-2014

Experimental Area Status

18