/
MISUSE OF EARNED VALUE MANAGEMENT MISUSE OF EARNED VALUE MANAGEMENT

MISUSE OF EARNED VALUE MANAGEMENT - PowerPoint Presentation

tatyana-admore
tatyana-admore . @tatyana-admore
Follow
448 views
Uploaded On 2017-10-04

MISUSE OF EARNED VALUE MANAGEMENT - PPT Presentation

RESULTS IN ERRONEOUS CONCLUSIONS   Charles F Lappenbusch Jr MBA CCP EVP PSP Presentation to Seattle Section AACE International March 9 2017 Over 30 years of financial and project ID: 593114

evm earned bac cost earned evm cost bac cpi spi payment wbs project progress eac amp schedule fixed introduction actual measures element

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "MISUSE OF EARNED VALUE MANAGEMENT" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

MISUSE OF EARNED VALUE MANAGEMENT RESULTS IN ERRONEOUS CONCLUSIONS 

Charles F. Lappenbusch, Jr. MBA, CCP, EVP, PSPPresentation to Seattle Section, AACE® InternationalMarch 9, 2017Slide2

Over 30 years of financial and project management Director of Development for a new town

Cost control processes, monitoring and integration with Critical Path Scheduling, Earned Value Management, and Risk Analysis.

What you don’t know about me.

BIOGRAPHY

Charles F. Lappenbusch, Jr.,

MBA,

CCP

, EVP, PSPSlide3

This is Earned Value!Slide4

PURPOSE:EVM within CONTEXT OF PROJECT CONTROLSCOMPLETION DATE? COMPLETION COST?INFORMATION FROM THE NOISE

INTRODUCTIONSlide5

PURPOSE:EVM IS INTEGRATION SCOPE, RESOURCE (COST),

SCHEDULE & RISKCOMMON TERMSEXTENSION OF PI

START THE CONVERSATION

CRITIQUE

INTRODUCTIONSlide6

ASSUMPTIONS:SCOPEBUDGET at COMPLETION (BAC)CRITICAL PATH METHOD (CPM)WORK BREAKDOWN STRUCTURE (WBS)

INTRODUCTIONSlide7

FOCUS:EVM KEY PERFORMANCE INDICATORS (KPI)COST PERFORMANCE INDICATOR (CPI)SCHEDULE PERFORMANCE INDICATOR (SPI)

TOTAL FLOAT (TF)INTRODUCTIONSlide8

FOCUS:EVM a PROJECT CONTROLEVM to CALCULATE EAC

EARNED VALUE (EV) vs EARNED PAYMENT (EP) 

INTRODUCTIONSlide9

TAKE A-WAY:WBS - INTEGRATOREVM – PROJECT CONTROLEVM NOT FINANCIAL CONTROL

EVM KPIs DEPEND UPON ALIGNMENT OF DD, PV, EV, AC,

TFEV vs EP

INTRODUCTIONSlide10

INTEGRATES:SCOPERESOURCE(COST) SCHEDULERISK

EVM BENEFITSSlide11

COMPARE UNLIKE ACTIVITIES COMMON NUMBER LOOK AHEAD TOOL

ADDS DEPTH & INSIGHT EAC IN LIEU OF DETAIL ESTIMATEKPI

TRENDING ANALYSISEVM

BENEFITSSlide12

SUMMARYMEASURES PROGRESS OBJECTIVE MEASUREMENT COMPARES PROGRESS

TO THE SCOPE, RESOURCE (COST), SCHEDULE & RISK PLANS

EVM BENEFITSSlide13

EVM FOUNDATION WBS WBS WBS WBS

BAC

CPM

PMB

DATA DATES (DD)

PLANNED VALUES

(PV) Per DDsSlide14

EAC = AC + (BAC –EV)/CPIEAC = AC + [(BAC – EV) / (EV/AC)]

EAC = AC + [(BAC – (%C*BAC)/ (%C*BAC)/AC)]EVM EACSlide15

EAC = AC + (BAC –EV)/ (SPI*CPI)EAC = AC + {(BAC – EV) / [(EV/PV) * (EV/AC)]}

EAC = AC + {[(BAC – (%C*BAC)/ {[(%C*BAC)/PV)]* [(%

C*BAC)/AC)]}}

EVM

EACSlide16

DATA DATE (DD)PLANNED VALUE (PV)EARNED VALUE (EV)

 ACTUAL COST (AC) TOTAL FLOAT (

TF)

ALIGNMENTSlide17

KPI ROLLED UP OR DRILLED DOWN BASIS FOR TRACEABILITY OF KPIsTHE

USE OF ADDITIONAL FILTERSOrganization Breakdown Structure (OBS)Resource/Cost Breakdown Structures (RBD/CBS)

WBS

INTEGRATIONSlide18

RECURRING RECORDING DATE1st DAY AFTER RECORDING PERIODSEPARATES ACTUAL (HISTORY) FROM SCHEDULED DATA

PV, EV, AC, TF MUST ALIGN WITH DDTHE BASIS OF KPI TRENDING

DATA DATE (DD)Slide19

PV PER BAC, CPM, PMBPV IS FIXED TO DDPV IS IN SAME UNITS OF MEASUREMENT AS EV

PLANNED VALUE (PV)Slide20

EV IS NOT FIXED TO DDEV IS ACCOMPLISHMENT OF PVEV IS IN SAME UNITS OF MEASUREMENT AS PV

EARNED VALUE (EV)Slide21

AC IS ACTUAL RESOURCE (COST)AC SAME DD AS EVINVOICE DELAY A DISTORTION OF AC

AC ACCRUALAC

vs. EPACTUAL COST (AC)Slide22

CRITICAL PATH (CP) SCHEDULE KPIMEASURES THE CP ACTIVITIES

TF MUST BE ALIGNED WITH THE DDTF

& SPI ARE NEEDED TO ANALYZE BOTH THE FLOAT AND CP ACTIVES

TOTAL FLOAT (

TF

)Slide23

COST PERFORMANCE INDEX (CPI) CPI =EV/ACCPI = <1 – OVER BUDGETCPI = 1 – ON BUDGETCPI = 1< - UNDER BUDGET

EVM KPIsSlide24

SCHEDULE PERFORMANCE INDEX (CPI)SPI = EV/PVSPI = <1 - BEHIND SCHEDULESPI = 1 – ON SCHEDULE

SPI = 1< AHEAD OF SCHEDULENOTE: WHEN EV = PV = SPI = 1

SCHEDULE VARIANCE = $0

REGARDLESS OF SCHEDULE

EVM

KPIsSlide25

CPI, SPI, TF = 27 KPI MATRIXEXAMPLES:

1 – CPI=1.00, SPI=1.00, TF=02 – CPI=1.00, SPI=0.85, TF=0

3 – CPI=1.00, SPI=1.25, TF

=-20

4 – CPI=1.00, SPI=0.85,

TF

=+20

OBSERVATIONS

5 – CPI=0.85, SPI=1.00,

TF

=+20

6 – CPI=0.85, SPI=0.85,

TF

=-20

27

EVM

KPIsSlide26

EP DETERMINISTICPER T& C OF THE CONTRACTPV FLOATS WITH EPDD FLOATS WITH EP

EV PROBABILISTICEAC

AND KPIs

PV FIXED PER

PMB

DD FIXED PER EV

AC IS FIXED TO EV

EARNED PAYMENT (EP)Slide27

EV vs EPEVM ELEMENT

Earned Value (EV)Earned Payment (EP)

EV & EP Functions

EV is a measurement of a Project's

progress

EP is used to

determine paymentSlide28

EV vs EPEVM ELEMENT

Earned Value (EV)Earned Payment (EP)

Progress

EV measures actual progress of a

project

EP measures progress of

paymentSlide29

EV vs EPEVM ELEMENT

Earned Value (EV)Earned Payment (EP)

Data Date (DD)

EV is measured for all activities prior to the DD

EP

of several activities will most likely

have different DDSlide30

EV vs EPEVM ELEMENT

Earned Value (EV)Earned Payment (EP)

Planned Value (PV)

PV

is fixed to a specific time

period

PV moves with the EPSlide31

EV vs EPEVM ELEMENT

Earned Value (EV)Earned Payment (EP)

Actual Cost (AC)

The cost (not cash flow) to achieve the

EV

EP is cash flow and not necessarily AC. Slide32

EV vs EPEVM ELEMENT

Earned Value (EV)Earned Payment (EP)

SUMMARY

EV measures project progress.

EP measures project

payment.Slide33

ONLY AS GOOD AS FOUNDATION SCOPE, RESOURCE (COST), SCHEDULE and RISK

EVM NEEDS WBS TO INTEGRATE

MUST ALIGN

DD

,

PV,

EV,

AC

,

TF

EP MEASURES

PAYMENT

EV MEASURES PROGRESS

SUMMARYSlide34

This is Earned Value!Slide35

QUESTIONS&CRITIQUE