Tanglewood  Area Neighborhood Street Reconstruction NSR 454A/Subproject 1 Preconstruction Tanglewood  Area Neighborhood Street Reconstruction NSR 454A/Subproject 1 Preconstruction

Tanglewood Area Neighborhood Street Reconstruction NSR 454A/Subproject 1 Preconstruction - PowerPoint Presentation

tawny-fly
tawny-fly . @tawny-fly
Follow
342 views
Uploaded On 2020-01-09

Tanglewood Area Neighborhood Street Reconstruction NSR 454A/Subproject 1 Preconstruction - PPT Presentation

Tanglewood Area Neighborhood Street Reconstruction NSR 454ASubproject 1 Preconstruction Community Meeting WBS NO N00038600014 Sam Habibi PE February 1 2018 1 OVERVIEW OF THE PROJECT 2 CONSTRUCTION PHASING AND PROJECT SCOPE ID: 772371

street project 000386 subproject project street subproject 000386 reconstruction 0001 tanglewood wbs neighborhood construction area expect driveway city service

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "Tanglewood Area Neighborhood Street Rec..." is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Tanglewood AreaNeighborhood Street Reconstruction NSR 454A/Subproject 1 Preconstruction Community MeetingWBS NO. N-000386-0001-4 Sam Habibi, P.E. February 1, 2018

1 OVERVIEW OF THE PROJECT 2 CONSTRUCTION PHASING AND PROJECT SCOPE 3 WHAT TO EXPECT DURING CONSTRUCTION 4CONTACT INFORMATION AGENDA 2

3Tanglewood NSR 454A/Subproject 1 SpringConstruction Begins 2018 2019 2020 SummerAnticipated CompletionTanglewood Area Neighborhood Street Reconstruction Project Subproject 1 (WBS NO. N-000386-0001-4)Project OverviewProject Limits

Tanglewood Area Neighborhood Street Reconstruction Project Subproject 1 (WBS NO. N-000386-0001-4)Construction Phasing NOTE: EXPECTED DATES ARE ESTIMATES, MAY CHANGE DURING CONSTRUCTION

Tanglewood Area Neighborhood Street Reconstruction Project Subproject 1 (WBS NO. N-000386-0001-4)Construction Phasing 5 Construction Sequence for a Typical Zone Legend ROADWAY UNDER CONSTRUCTION THIS PHASE 27’ 27’ 10.5’ 13.5’

Water and wastewater as needed Tanglewood Area Neighborhood Street Reconstruction Project Subproject 1 (WBS NO. N-000386-0001-4) Project Scope 6Storm drainagePavement conditions and mobility Pedestrian safety and accessibility (along Sage Road)

Tanglewood Area Neighborhood Street Reconstruction Project Subproject 1 (WBS NO. N-000386-0001-4)Project Scope – Utilties 7 Legend Proposed Storm Sewer Proposed Sanitary Sewer Proposed Water

Tanglewood Area Neighborhood Street Reconstruction Project Subproject 1 (WBS NO. N-000386-0001-4)Construction – Project Info Keep your door hanger throughout the project Lists phone numbers you need Lists the Project Number Number needed when you call or write us Meet the City PM or Inspector Will be your contact to resolve issues throughout constructionConstruction will occur within the City right-of-way City right-of-way generally extends 10 to 17 feet into your yard 8i

Tanglewood Area Neighborhood Street Reconstruction Project Subproject 1 (WBS NO. N-000386-0001-4)Construction – How to Report a Problem Contact 311Report the project number Request issue be directed to Public Works Capital Projects Be as complete as possible with your concern 9 Contact us at: pwecip@houstontx.gov

Tanglewood Area Neighborhood Street Reconstruction Project Subproject 1 (WBS NO. N-000386-0001-4)What to Expect During ConstructionPrepare for ConstructionDocument the conditions of your yard and sprinkler head locations; the contractor will do the same. Remove special landscaping features (i.e., fountains, lawn art)Find alternative parkingPlan for water service interruption Be mindful of protective barriersPotential Service Impacts: Potential water service impactsPotential parking/driveway access impactsTrash/recycling receptacle location impacts 10 !

Tanglewood Area Neighborhood Street Reconstruction Project Subproject 1 (WBS NO. N-000386-0001-4)What to Expect During ConstructionWater ServicesPotential for service interruption:Waterline replacement - notification 24 to 48 hours in advancePeriodicMay last 2 to 4 hours Accidental/Unplanned Interruption – the contractor will work quickly to restore services. 11

Tanglewood Area Neighborhood Street Reconstruction Project Subproject 1 (WBS NO. N-000386-0001-4)What to Expect During ConstructionParking and Driveway AccessShort-periods of limited access to your drivewayPark elsewhere and walk to your homeContact us immediately if needing handicapped accessShort-periods of no on-street parking Construction will alternate each side of the street on different schedulesSuggest working with neighbors on the opposite side – they may need your help when it’s their turn. 12 P

Tanglewood Area Neighborhood Street Reconstruction Project Subproject 1 (WBS NO. N-000386-0001-4)What to Expect During ConstructionDriveways13 Driveway Construction Coordination Driveway Construction Options Option 1: Replace the broken length and width of the driveway with plain reinforced cement concrete at no cost to the home owner. Option 2: Grade the subgrade to proper slope and form the driveway to meet the new grades /slope. You would see the finished dirt with proper slope. Home Owner to finish the Driveway with their desired finish at their cost.(Driveway must be finished 2 weeks after it’s been prepped by the City.)

Tanglewood Area Neighborhood Street Reconstruction Project Subproject 1 (WBS NO. N-000386-0001-4)What to Expect During ConstructionTrash/Recycling Pick-upPotential for service interruption: Construction will alternate each side of the street on different schedulesWaste receptacles should be placed on the non-affected side of the street 14

Tanglewood Area Neighborhood Street Reconstruction Project Subproject 1 (WBS NO. N-000386-0001-4)What to Expect During ConstructionTreesOur goal is to protect all trees during construction. We accomplish this by working with the City Arborist. Some trees may be trimmed as part of the project Zero curb cut design option was applied in some areas to prevent tree damage. 15

Tanglewood Area Neighborhood Street Reconstruction Project Subproject 1 (WBS NO. N-000386-0001-4)What to Expect During ConstructionRestorationRestoration of sprinkler systems, grass, etc. will be done when construction is complete.City does not approve final payment to contractor until restoration is complete.If you have concerns:Document (writing, photo, etc.)Call 3-1-1 Do not make the repairs yourself 16

Tanglewood Area Neighborhood Street Reconstruction Project Subproject 1 (WBS NO. N-000386-0001-4)Contact InformationContact us at pwecip@houstontx.gov17 Robert Merhi , Superintendent (713) 459-8675 David Garza, Construction Manager (CM&I Team) (713) 541-3530Roland Joubert, Inspector (CM&I Team)r.joubert@othon.comSam Habibi, Project Manager (COH)(832) 395-2283City of Houston Staff (Oversight)Total Contracting, Ltd (Contractor)All inquires should be directed to: Afolake Adeniyi, (832) 395-2128

Tanglewood Area Neighborhood Street Reconstruction Project Subproject 1 (WBS NO. N-000386-0001-4)IMPORTANT LINKSFor a complete listing of Frequently Asked Questions please visit:https://www.publicworks.houstontx.gov/ecd/faqs.html Today’s presentation and additional project information can be found at: https://rebuildhouston.org/community-engagement 18 i

THANK YOUGeneral Q&A Please find a breakout group at the Houston Public Works tables.