/
Chiller design and purchase Chiller design and purchase

Chiller design and purchase - PowerPoint Presentation

terrificycre
terrificycre . @terrificycre
Follow
347 views
Uploaded On 2020-06-19

Chiller design and purchase - PPT Presentation

by Elena Perez Rodriguez Index Introduction Technical specification Design and configurations Purchase documents Price list and adjudication formula Risk matrix Conclusion 24112010 Thermosiphon project ID: 781240

project thermosiphon chiller 2010 thermosiphon project 2010 chiller operation power configuration circuit adjudication brine spare option mitigation price maintenance

Share:

Link:

Embed:

Download Presentation from below link

Download The PPT/PDF document "Chiller design and purchase" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

Chiller design and purchase

by Elena Perez Rodriguez

Slide2

Index

Introduction

Technical specification

Design and configurationsPurchase documentsPrice list and adjudication formulaRisk matrixConclusion

24/11/2010

Thermosiphon project

2

Slide3

Introduction

This presentation will go through both the technical and purchase documents.

These documents and the annexed can be found in

EDMS 1078475

24/11/2010

Thermosiphon project

3

Slide4

Technical specification

Overview of the design and the technical specification document

24/11/2010

Thermosiphon project

4

Slide5

Technical specification

24/11/2010

Thermosiphon project

5

Slide6

CHILLER UNIT(S)

BRINE

Scope of the tender

6

Primary

water

Chiller and brine : design, selection & purchase of components, refrigerants for chiller, construction, skids, installation, connection and commissioning

Thermosiphon

condenser and piping

Spares

(1 year & 10000 h)

Electrical design, functional analysis, electrical/control components, cabling and electrical/control cabinets

Documentation and labeling

Terminal blocks, PLC and

software (UNICOS)

Fluid for the brine

Slide7

General conditions for tendering

24/11/2010

Thermosiphon project

7

Documents to be sent with the

tender

Slide8

Delivery schedule

Thermosiphon project

8

March 2011

April 2011

September 2011

October 2011

December 2011

Slide9

Technical requirements

Chiller units

Two circuits in cascade (high and low temperature).

Refrigerant to be chosen by contractor.

24/11/2010

Thermosiphon project

9

Operation regimes

Nominal operation

Emergency situation

Cooling power in the Thermosiphon condenser

180 kW

50 kW

Temperature at the inlet of the Thermosiphon

condenser

-70

°

C

-20

°

C

Temperature at the outlet of the Thermosiphon

condenser

-65

°

C

-15

°

C

Maximum pressure drop

4

bar

4

bar

Brine circuit

Mono-phase liquid C

6

F

14.

Materials shall be compatible with fluorocarbons.

Slide10

Chiller configuration A

24/11/2010

Thermosiphon project

10

C3F8 condenser

180 kW

-70 °C

liquid

tank

USA15

cavern

Surface

C6F14 brine circuit

Primary water

25°C

CHILLER 3

50% power for nominal operation

ATLAS ID

Detector

UX15

cavern

Back-up

50 kW

-20 °C

Brine circuit

Redundant pumps

CHILLER 2

50% power for nominal operation

CHILLER 1

50% power for nominal operation

Slide11

P&I for the configuration A

24/11/2010

Thermosiphon project

11

Slide12

24/11/2010

Thermosiphon project

12

Chiller configuration B

liquid

tank

USA15

cavern

Surface

C6F14 brine circuit

Primary water

25°C

CHILLER 4

100% power for nominal operation

Redundant

CHILLER 5

For emergency situation

ATLAS ID

Detector

UX15

cavern

C3F8 condenser

180 kW

-70 °C

Back-up

50 kW

-20 °C

Brine circuit

Redundant pumps

CHILLER 6

For emergency situation

Slide13

P&I for the configuration B

24/11/2010

Thermosiphon project

13

Slide14

Configurations:

advantages and disadvantages

24/11/2010

Thermosiphon project

14

Configuration A

Configuration B

Comments

Not impact on

operation

for

preventive

maintenance

Higher

r

isk of impact on operation of

preventive

maintenance

Mitigation : use

of the brine circuit.

Circuit

redundancy

Not impact on operation for

single

failures

Mechanical redundancy

Impact

on operation

for

failures in

no-duplicated components.

Impact

on operation

in

case

of degradation

of the

circuit .

Mitigation : use of the HAUG station.

Power requirements:

Standard power 160 kW

Diesel power 75 kW

Power requirements:

Standard power 205 kW

Diesel power 50 kW

Depends

on

electrical

services in Point 1.

Balanced operation of compressors.

Unbalance operation of the

compressors.

Mitigation : schedule

for running the emergency chiller units.

Easier operation and control logic ?

More complicated operation and control logic ?

This is not for sure

Less spare parts required ?

More spare parts required ?

The thermosiphon works with BOTH solutions

The HAUG station will be a back-up

Difference in costs is unknown

Slide15

Chiller configuration A

19/11/2010

Thermosiphon project

15

Standard power supply

Diesel power supply

30 kW

45 kW

45 kW

25 kW

45 + 45 kW

45 kW

45 kW

Slide16

Chiller configuration B

19/11/2010

Thermosiphon project

16

Standard power supply

Diesel power supply

25 kW

180 kW

20 kW

20 kW

30 kW

Slide17

Design

Operation and reliability

Power regulation

20 ÷ 100%

Temperature regulation20°C ÷ -70°CPrecision ± 1 K

CompressorMTBF > 40,000 hMTTR < 10 h

Chiller system

MTBF > 20,000 h

Other

Seismic requirements

(Olga Beltramello)

Sound level

(Flora Galvan)

Reliability and risk analysis

24/11/2010

Thermosiphon project

17

Slide18

Integration

24/11/2010

Thermosiphon project

18

To be approved

Will be shown in the bidders conference

Slide19

Assembly

24/11/2010

Thermosiphon project

19

Pre-assembled in metallic frames (skids)

Control and electrical cabinet will also be pre-assembled

Slide20

Assembly and commissioning

24/11/2010

Thermosiphon project

20

Slide21

Maintenance and documentation

Maintenance

Preventive maintenance plan and spare parts list provided by supplier (CERN template).

Preventive maintenance shall be done during nominal operation at full power.

DocumentationTemplates provided for: Technical dossier (STA), Functional analysis.Labeling

24/11/2010

Thermosiphon project

21

Slide22

Purchase documents

Adjudication formula explanation, options and chosen solution.

Risk matrix

24/11/2010

Thermosiphon project

22

Slide23

Adjudication: options

19/11/2010

Thermosiphon project

23

Slide24

Adjudication

formula

24/11/2010

Thermosiphon project

24

IT-3684/EN/ATLAS - DQE - DESCRIPTION AND QUANTITY ESTIMATE

Chapter 2 - Option B

CHILLER 3

Chapter

Cost

High temperature circuit

301

Compressor

 

302

Oil recuperation circuit

 

303

Primary water condenser

 

304

Heat exchagner with low temperature circuit

 

305

Brine circuit evaporator

 

306

Expansion vessel

 

307

Fluid

 

Low temperature circuit

308

Compressor

 

309

Oil recuperation circuit

 

310

Brine circuit evaporator

 

311

Expansion vessel

 

312

Fluid

 

General

313

Valves

 

314

Piping and insulation

 

315

Instrumentation

 

316

Electrical components (including cabinets)

 

317

Metallic frame (skid)

 

318

Mechanical assembly

 

319

Electrical connection

 

320

Spare parts for one year & 10000 h of compressors

 

321

Tests

 

Total price for chiller 3

 

Total price for option

B

 

 

Configuration A

Chapter

Cost

A1

Option A

 

A2

Option B

 

A3

Option F

 

Configuration B

Chapter

Cost

B1

Option C

 

B2

Option D

 

B3

Option E

 

B4

Option F

 

Spare parts

Chapter

Cost

C1

Spare compressor(s) for configuration A

 

C2

Spare compressor(s) for configuration B

 

Adjudication

price

Conf A + 1.1*Conf B + Spare comp A + Spare comp B

2

Slide25

Adjudication

Practical example

Company

Configuration A

Configuration B (penalization 10%)

Price for Adjudication

I (price)

100

100

I

(adjudication)

100

110

105

II (price)

110

80

II (adjudication)

110

88

97

III

(price)

90

100

III (adjudication)

90

110

100

24/11/2010

Thermosiphon project

25

Adjudication

price

Configuration A + 1.1*Configuration B + Spare comps

2

Slide26

Risk matrix

24/11/2010

Thermosiphon project

26

 

RISK

LIKELIHOOD

IMPACT

DECISION

HOW TO MITIGATE IT

1

The contractor lacks experience

Possible (has already happened)

Moderate

Mitigation (fill in next field )

Require a minimum number of similar references for the selected company, criteria 4.1

2

The contractor lacks resources

Possible (has already happened)

Major

Mitigation (fill in next field )

Require a minimum number of employees and turnover, criteria 5.1 and 5.2

3

The contractor missinterpretates the Invitation to Tender documents

Possible (has already happened)

Major

Mitigation (fill in next field )

Bidders conference.

Close follow up of the contract.

4

The deadlines are not respected

Likely (50% probability)

Major

Mitigation (fill in next field )

Close follow up of the contract.

5

Unexpected end of the contract

Rare (never happens)

Catastrophic

Mitigation (fill in next field )

The contractor has to have an insurance (as stated in the § 3 of the IT document).

A list of qualified companies has to be available to be able to place another contract.

6

The equipment delivered does not correspond to the required performances

Possible (has already happened)

Major

Acceptance

 

7

Maintenance plan is more expensive than expected

Likely (50% probability)

Moderate

Acceptance

 

8

Extra costs associated to the equipment

Possible (has already happened)

Moderate

Acceptance

 

9

Reliability problems of the equipment purchased

Possible (has already happened)

Major

Mitigation (fill in next field )

Bank warranty

Spare part purchased with the contract

Slide27

Conclusions

An overview of the design of the chiller has been shown.

The adjudication formula has been justified and discussed.

The risk matrix has been presented.

24/11/2010

Thermosiphon project

27

Slide28

Thank you for your attention

24/11/2010

Thermosiphon project

28

Any questions ?