/
PROJECT MANAGEMENT  & PROJECT MANAGEMENT  &

PROJECT MANAGEMENT & - PowerPoint Presentation

test
test . @test
Follow
456 views
Uploaded On 2018-03-07

PROJECT MANAGEMENT & - PPT Presentation

ITS BOTTLENECKS A CASE STUDY OF RO PROJECT SEPTEMBER 04 2015 DANIYAL ALTAF PTEROU P 1930 1 What is a project Definition A project is a temporary endeavor undertaken to create a unique product service or result ID: 641845

process project improvement system project process system improvement time identify bottlenecks efficiency management cost bottleneck analysis production case contract

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "PROJECT MANAGEMENT &" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

PROJECT MANAGEMENT & ITS BOTTLENECKS

A CASE STUDY OF RO PROJECT

SEPTEMBER 04, 2015

DANIYAL ALTAFPTE/ROUP - 1930

1Slide2

What is a project? Definition:“A project is a temporary endeavor undertaken to create a unique product, service or result.”

The temporary nature of a project means that it has a definite beginning and endingEfforts that have no defined end date or definition of “done” are not projects, they are on-going operations!

Projects end in only one of two ways:The project’s objectives have been reachedThe project is terminated because its objectives will not or cannot be met, or when the need for the project no longer exists.

2Slide3

REVERSE OSMOSIS PROJECTReverse osmosis unit was a sublet project in order to make it easy to manage.Project assigned on the basis of two types of contractsLump sum contractUnit Price contract3Slide4

Bids were requested by contractorsDifferent companies were both technically and commercially evaluated.Upon evaluation, the approved contractor was called for contract signing.Contract defines the scope of the project which the contractor is bound to complete.Lump sum contract – HYDROTECH Engineering & SIEMENSUnit Price contract (with contingency) - DESCON EngineeringBidding is an offer (often competitive) of setting a price one is willing to pay for something or a demand that something be done.

4Slide5

Project attributesA project: Has a unique purpose.Is temporary.Is developed using progressive elaboration.Requires resources, often from various areas.Should have a primary customer or sponsor.The

project sponsor usually provides the direction and funding for the project.Involves uncertainty.

5Slide6

6Slide7

Advantages of using formal project managementBetter control of financial, physical, and human resources.Improved customer relations.Shorter development times.Lower costs.Higher quality and increased reliability.Higher profit margins.Improved productivity.Better internal coordination.Higher worker morale (less stress).7Slide8

Phases of a projectProjects are normally broken down into “phases”Ease of managementPlanning

Control.

8Slide9

Project execution phases 9Slide10

Common Trends Along The PM Lifecycle10Slide11

The triple constraint of a project

11Slide12

Key elements of Project Management Framework

12

SCOPE

TIME

COST

QUALITY

PROCUREMENT

RISK

COMM.

HRSlide13

Project ManagerAssigned byto

responsible for13Slide14

Project Manager Responsibilities & Competencies

Leadership

Team Building

MotivationCommunicationInfluencingDecision Making

Political and Culture Awareness

Negotiation

Trust Building

Conflict Management

Coaching

Leading Without Direct Authority

14Slide15

15 Project Manager job functions

Define scope of project.

Identify stakeholders, decision-makers, and escalation procedures.

Develop detailed task list (work breakdown structures).Estimate time requirements.Identify required resources and budget.Evaluate project requirements.Identify and evaluate risks.

Prepare contingency plan.

Identify interdependencies.

Identify and track critical milestones.

Participate in project phase review.

Secure needed resources.

Manage the change control process.

Report project status.

15Slide16

Suggested skills for Project Managers

16Slide17

PM tools & techniquesProject chartersScope statementsWBS cost estimates and earned value managementGantt charsCritical path analysis

17Slide18

BottlenecksIn this presentation:Causes of bottlenecksEffects of bottlenecksHow to avoid?How to handle?Neck of the traditional bottleIn project management:any point of congestion within an organizational system that hinders the flow of work across the various processes that make up the system.

18Slide19

In simple terms, it is a resource whose capacity is lower than the demand placed on it. lot of work in progressQueuesincrease in the overall project life cycle time and project cost

.Identification:by a detailed analysis of the processes involved within the organization (system). 19Slide20

Primary causesResource inefficiencyOutdated technologyLack of resourcesImproper communicationBreakdowns

Poor maintenance schedule20Slide21

Case study – bottle neck at RO project Change of system to compensate for time

21Slide22

Case study – bottle neck at RO project Delayed material delivery22

1

st priority to jobs essential for commissioning of plant

2nd shipment delivered 15 days before…3rd shipment delivered just one day before completion dateSlide23

Lessons I learned through observation and common sense.Do not expect to achieve mechanical tolerances in civil works. Be practical.

Design and fabrication drawings should be completed in all respects

23Slide24

Effects of bottlenecksIn a project environment, the following are the main effects of bottlenecks:Reduction in overall production efficiencyIncreased backlogsIncreased cost of storageConstraint challenge

24Slide25

Reduction in overall production efficiencyEfficiency is the rate at which time, effort and cost is properly usedExample: Spindle machine working at 50%. All other machines will produce at a lesser rate to compensate for reduction in efficiency of spindle machine. As a result, overall production efficiency reduces to 50%.1

25Slide26

Increased backlogs of workAs project managers, what we should strive for is process efficiency and optimization, not maximization.

2

26Slide27

Increased storage costThis is very common in the manufacturing environment where goods are produced. Development of production philosophies such as lean manufacturing and just in time production. 327Slide28

Solving bottlenecks in a project environment:Series of stepsProblem Identification (Process analysis)Aim for overall process improvement not individual station efficiency“If it

ain’t broke, don’t fix it”Schedule and maintenanceTechnological improvement

28Slide29

Problem Identification (Process analysis)The first step in solving bottlenecks is to determine their cause.Duty of a project manager – permanently solve the problem1

29Slide30

The easiest way to identify the root cause is to conduct a critical process analysisQuick pointers that can help identify bottlenecks:processes that take the most time processes with the most reworkProcesses which the staff complains the most about

30Slide31

Case study – Problem at RO project Communication gap between client and contractorRemedy advised: Make sure up-to-date drawings are being used on site

31Slide32

…Process analysisThe systematic steps that are required in process analysis are:

PROCESS IMPROVEMENT32Slide33

System improvement, not individual process improvementAlways aim for a holistic system improvement instead of a part or process improvement.The challenge with individual process improvement is that while they often improve the particular process, they do not have an effect on the overall system.Let’s not forget: the output or efficiency of a bottleneck would determine the output or efficiency of the overall system.

233Slide34

If it ain’t broke, don’t fix itThis quote applies to bottlenecks: if it is not a bottleneck, there’s no need to improve its efficiency. Doing so would only cause your organization to incur more expenses.

3

34Slide35

Schedule and maintenanceLack of a proper maintenance schedule or wrong timing for maintenance can lead to a bottleneck. 4

35Slide36

Technological improvementSometimes the technology we have can no longer compete with the modern standard, automatically causing a bottleneck.If it is just a process that requires technological improvement, then it is a bottleneck and can be treated in isolation.

536Slide37

ConclusionProject Management is not easy.The devil lies in the details

Prevention is better than cureNever take “Risk management” for grantedDetailed planning prevents bottlenecks

Drawings should be ready with the best possible detail37Slide38

References:Project management body of knowledge (PMBOK)http://www.investopedia.com/WikipediaGoogle ImagesPlant Project Engineering Guide book for Mechanical Engineers – CASTI

38