PRESENTATION FOR OBTAINING ENVIRONMENT CLEARANCE For Proposed Residential cum commercial building on plot bearing Old S. No. 218 (New S. No. 194) H. No. 13, 15, 16 Old S. No. 219 (New S. No. 193) H. No. 1, 4, 6, 8,9, 10, 12 Old S. No. 227
"PRESENTATION FOR OBTAINING ENVIRONMENT CLEARANCE" is the property of its rightful owner. Permission is granted to
download and print the materials on this website for personal, non-commercial use only, and to display it
on your personal computer provided you do not modify the materials and that you retain all copyright
notices contained in the materials. By downloading content from our website, you accept the terms of this
agreement.
Presentation Transcript
01
PRESENTATION FOR OBTAINING ENVIRONMENT CLEARANCE
For Proposed Residential cum commercial building on plot bearing Old S. No. 218 (New S. No. 194) H. No. 13, 15, 16 Old S. No. 219 (New S. No. 193) H. No. 1, 4, 6, 8,9, 10, 12 Old S. No. 227 (New S. No. 28) H. No. 3, Old S. No. 228(New S. No. 27) H. No. 6, 7 & Old S. No. 229 (New S. No.22) H. No. 1,12,13 Village Navghar, Tal. & Dist. Thane, Maharashtra To
“STATE EXPERT APPRAISAL COMMITTEE – 2” (SEAC-2 MMR) Proposed By
M/s. Gujarat Realtors AQURA ENVIRO PROJECTS PVT. LTD. (AEPPL)
Environmental Engineers & Consultants
NABET & QCI Letter vide No. QCI/NABET/ENV/ACO/21/1739 dated 17th May 2021 1<br>
02
PROJECT BACKGROUND 2 Development of Residential cum Commercial building on plot bearing Old S. No. 218 (New S. No. 194) H. No. 13, 15, 16 Old S. No. 219 (New S. No. 193) H. No. 1, 4, 6, 8, 9, 10, 12 Old S. No. 227 (New S. No. 28) H. No. 3, Old S. No. 228(New S. No. 27) H. No. 6, 7 & Old S. No. 229 (New S. No.22) H. No. 1,12,13 Village Navghar, Tal. & Dist. Thane, Maharashtra
As per the Development Plan of MBMC, the proposed site u/r falls under Residential Zone and have reservations for Housing for Dis-housed , Garden & H.S & P.G.
Earlier PP had owned only survey no. 229, Hissa No. 13 admeasuring area 3380.00 Sq. Mt. Based on this PP obtained CC, vide No. MBMC/MNPA/NR/394/2018-2019, dated17/04/2018, for this Survey No. 229 Hissa No. 13 for Construction area 6,047.53 Sq. Mt. and work upto plinth level was completed.
Now PP has obtained development rights for Old S. No. 218 (New S. No. 194) H. No. 13, 15, 16 Old S. No. 219 (New S. No. 193) H. No. 1, 4, 6, 8, 9, 10, 12 Old S. No. 227 (New S. No. 28) H. No. 3, Old S. No. 228(New S. No. 27) H. No. 6, 7 & S. No. 229, H. No. 1 & 12.
PP amalgamated Survey No. 229, Hissa No. 13 with the aforesaid new survey numbers.
Now the total potential is crossing more than 20,000 Sq. Mt. hence the work on Survey 229, Hissa No. 13 is stopped since Feb 2021.
PP has submitted revised proposal to MBMC dated 09.04.2021 proposing the development on the entire amalgamated land.
At present rest of the site is a vacant & construction for the proposed project has not yet started.<br>
03
3 PROPOSED PROJECT
AREA STATEMENT
As per Approved plan vide no. M.B.M.C./…/30032021-2022 dated 24.12.2021<br>
04
4 AREA STATEMENT<br>
05
5 CONSTRUCTION AREA DETAILS OF PROPOSED PROJECT<br>
06
6 PROJECT DETAILS<br>
07
7<br>
08
8 APPROVAL LETTER<br>
09
9 APPROVAL LETTER<br>
10
10<br>
11
11<br>
12
12<br>
13
13<br>
14
14<br>
15
15 15<br>
16
16<br>
17
17<br>
18
18<br>
19
ENVIRONMENTAL MANAGEMENT PLAN<br>
20
ENVIRONMENTAL MANAGEMENT PLAN<br>
21
ENVIRONMENTAL MANAGEMENT PLAN<br>
22
22<br>
23
23 WATER SAMPLING RESULTS<br>
24
24<br>
25
25 WATER CALCULATIONS<br>
26
26 WATER BALANCE DIAGRAM: NON-MONSOON SEASON Treated water = 671 KLD
Reuse for Flushing & Gardening = 291 KLD (43%)
Excess water to M.B.M.C = 145 KLD (22%)
Excess to municipal sewer line = 235 KLD (35%) All Quantities are in KLD<br>
27
27 WATER BALANCE DIAGRAM: MONSOON SEASON All Quantities are in KLD<br>
28
28<br>
29
SOLID WASTE CALCULATION 29 SWM would include collection, transportation and disposal in a manner to cause minimal environment impact.
Source Segregation & Collection of waste into bio-degradable waste and non-biodegradable waste.
Biodegradable waste would be transferred to Organic Waste Composter (OWC) Systems for further treatment.
Non-biodegradable waste would be further segregated as recyclable and non- recyclable.
Recyclable material will be sold to authorized vendors and rest will be disposed off into the garbage collecting vehicles of the local Authorities.
Excess compost will be handed over to authorized vendor/MBMC.
At Solid waste Management Location, separate bins for collection of E- Waste & Biomedical waste (due to COVID 19 Pandemic situation) would be provided & they would be handed over to respective authority for disposal on regular basis.<br>
30
30<br>
31
ENERGY CALCULATIONS – AGAINST CONVENTIONAL BASE CASE<br>
32
ENERGY CALCULATIONS – AGAINST CONVENTIONAL BASE CASE<br>
33
TERRACE AREA CALCULATIONS<br>
34
34<br>
35
ENVIRONMENTAL MANAGEMENT PLAN (CONSTRUCTION PHASE) 35<br>
36
ENVIRONMENTAL MANAGEMENT PLAN (CONSTRUCTION PHASE) 36<br>
37
ENVIRONMENTAL MANAGEMENT PLAN (OPERATION PHASE) 37<br>
38
ENVIRONMENTAL MANAGEMENT PLAN (OPERATION PHASE) 38<br>
39
ENVIRONMENTAL MANAGEMENT PLAN (OPERATION PHASE) 39<br>
40
ENVIRONMENTAL MONITORING PLAN After occupancy, a Society will be formed under the supervision of developer.
The Operation and Maintenance of EMP facilities will be handed over to society after society formation.
Environmental management cell will be appointed.
Monitoring Committee monitor Environmentally sensitive parameters as per schedule
Six months monitoring report will be prepared and will be internally assessed for continual progress, allotment of funds and for safety of environment and health of people 40<br>
41
41 BUDGETORY ALLOCATION FOR ENVIRONMENT MANAGEMENT PLAN – CONSTRUCTION PHASE<br>