Tariff Based Competitive Bidding (TBCB)

Tariff Based Competitive Bidding (TBCB)
1 / 1
Tariff Based Competitive Bidding (TBCB) - slide 1 of 15 Tariff Based Competitive Bidding (TBCB) - slide 2 of 15 Tariff Based Competitive Bidding (TBCB) - slide 3 of 15 Tariff Based Competitive Bidding (TBCB) - slide 4 of 15 Tariff Based Competitive Bidding (TBCB) - slide 5 of 15 Tariff Based Competitive Bidding (TBCB) - slide 6 of 15 Tariff Based Competitive Bidding (TBCB) - slide 7 of 15 Tariff Based Competitive Bidding (TBCB) - slide 8 of 15 Tariff Based Competitive Bidding (TBCB) - slide 9 of 15 Tariff Based Competitive Bidding (TBCB) - slide 10 of 15 Tariff Based Competitive Bidding (TBCB) - slide 11 of 15 Tariff Based Competitive Bidding (TBCB) - slide 12 of 15 Tariff Based Competitive Bidding (TBCB) - slide 13 of 15 Tariff Based Competitive Bidding (TBCB) - slide 14 of 15 Tariff Based Competitive Bidding (TBCB) - slide 15 of 15
Tariff Based Competitive Bidding (TBCB) Expectation from Field Engineers in MSETCLs TBCB Participation Project Summit - 2025 The Electricity Act, 2003 Part VII Tariff (6 Sections) Section 61. Tariff regulations Section 62. Determination of

Related Topics

Download this presentation From Below

"Tariff Based Competitive Bidding (TBCB)" is the property of its rightful owner. Permission is granted to download and print the materials on this website for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.

Presentation Transcript

01
Tariff Based Competitive Bidding (TBCB)

Expectation from Field Engineers in MSETCL’s TBCB Participation

Project Summit - 2025<br>
02
The Electricity Act, 2003
Part VII Tariff (6 Sections)
Section 61. Tariff regulations
Section 62. Determination of tariff
Section 63. Determination of tariff by bidding process
Notwithstanding anything contained in section 62, the Appropriate Commission shall adopt the tariff if such tariff has been determined through transparent process of bidding in accordance with the guidelines issued by the Central Government.
Section 64. Procedure for tariff order
Section 65. Provision of subsidy by State Government
Section 66. Development of market MoP, GOI
Ministry of Power, Government of India, notified in April 2006 - Tariff Based Competitive Bidding (TBCB) Guidelines for Transmission Service and Guidelines for Encouraging Competition in Development of Transmission Projects

Subsequently Standard Bidding Documents (SBD) issued by MoP in the year 2008 :
Request for Qualification (RfQ),
Request for Proposal (RfP) and
Transmission Service Agreement (TSA)

Further, based-on stakeholders' consultation, an exercise of comprehensive review of above documents was taken.

MoP, GoI has notified revised documents in Aug,-2021, modifications were done in Standard Bidding Documents(SBDs) including Request for Proposal (RFP), Transmission Service Agreement (TSA) and Share Purchase agreement TBCB – Regulatory aspects<br>
03
Cost Plus (RTM) TBCB Projects on Nomination Basis Projects on Competitive Bidding
Route No Requirement of Acquiring New
Company Requirement of Acquiring Special
Purchase Vehicle Execution First, Tariff
Determination Later (u/s 62 of EA) Tariff Determination First,
Execution Later (u/s 63 of EA) Market, Interest Rate, Route
Change Risk etc. passed through No protection against MOST of
the risks Non Completion of project may lead deduction of IDC & IEDC beyond SCoD Non-Completion of project by
SCoD leads to levy of hefty LD No need to furnish Contract Performance Guarantee Contract Performance Guarantee to be furnished No need to Grant of License from
MERC License is required from MERC RTM (Cost-plus) vs TBCB<br>