WALO CASE STUDY WALO CASE STUDY

WALO CASE STUDY - PDF document

walsh
walsh . @walsh
Follow
343 views
Uploaded On 2021-04-14

WALO CASE STUDY - PPT Presentation

MASTIC RENEWAL OF UPPER RESERVOIR AT LA MUELA SPAIN Client Iberdrola Generaci ID: 833390

walo reservoir water upper reservoir walo upper water spain work mastic slopes challenge scheduled power plant upgrade shutdown huge

Share:

Link:

Embed:

Download Presentation from below link

Download Pdf The PPT/PDF document "WALO CASE STUDY" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

WALO CASE STUDY – MASTIC RENEWAL OF
WALO CASE STUDY – MASTIC RENEWAL OF UPPER RESERVOIR AT LA MUELA, SPAIN Client: Iberdrola Generación S.A., Head Office, Madrid, Spain Engineer: Iberdrola Generación S.A., Head Office, Madrid, Spain Background The Pump Storage Scheme at La Muela in Valencia is the biggest of its kind in Spain. The upper reservoir has a circumference of 4,800m and stores 23 million m3 of water, generating a similar amount of energy to that of a nuclear power plant. A major upgrade programme is currently underway, consisting of the construction of a new underground power house and tunnels and penstock. As a shutdown of the plant had to be scheduled to undertake the upgrade, WALO was commissioned to carry out a mastic renewal of the upper reservoir, which covers an area of 1,400,000 m2. The Challenge The particular challenge facing WALO was to undertake the work after only partly emptying the upper reservoir so the work had to be carried out above the water, a

voiding any contamination of the water
voiding any contamination of the water remaining in the reservoir. This meant that the huge amount of sediment on the slopes which was cleaned off by WALO had to be removed from the site by truck, without any of it being washed into the reservoir water below the work area. To add to the challenge, the only access to the site was via the crest road. This presented a huge logistical problem as that route could easily be blocked by just one works vehicle so the movement of materials and work teams was very restricted and had to be carefully planned. The Project After a scheduled shutdown of the Pump Storage Scheme, the upper reservoir was partly emptied so only 25% of the water was left and a new mastic coating was installed by WALO. The works consisted of cleaning the existing bituminous face by hydro-jet washing and removing the sediment on the slopes, spraying a new bitumen emulsion and applying a new mastic sealing to the 43 m long slopes which have an incline of 1:1.6