/
Locational Net Benefit Analysis Locational Net Benefit Analysis

Locational Net Benefit Analysis - PowerPoint Presentation

yoshiko-marsland
yoshiko-marsland . @yoshiko-marsland
Follow
454 views
Uploaded On 2017-05-14

Locational Net Benefit Analysis - PPT Presentation

Working Group October 19 2016 Webinar drpwgorg Agenda Time Topic 900915 Introductions 915930 B Schedule of Reports 930945 C Update on deferability criteria Grid services 61b ID: 548169

lnba report cost final report lnba final cost avoided term long der grid working costs ica locational draft services

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "Locational Net Benefit Analysis" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

Locational Net Benefit AnalysisWorking Group

October 19, 2016

Webinar

drpwg.orgSlide2

Agenda

Time

Topic

9:00-9:15

Introductions

9:15-9:30

B. Schedule

of Reports

9:30-9:45

C. Update on deferability

criteria

Grid services (6.1.b)

9:45-12:00

E. Long-term refinement topics and interim report

12:00-12:30

F. Summarize/wrap-upSlide3

ICA and LNBA Working Group Background

ICA and LNBA WG Purpose

-

Pursuant to the May 2, 2016, Assigned Commissioner’s Ruling (ACR) in DRP proceeding (R.14-08-013), the Joint Utilities are required to convene the ICA WG to:

Refine ICA and LNBA Methodologies and Requirements

Authorize Demonstration Project A and Project B

CPUC Energy Division role

Oversight to ensure balance and achievement of State objective (ensure adequate stakeholder representation in consensus statements, keeping WG activities on track with Commission expectations/needs, demonstration project results review, quality control on deliverables)

Coordination with both related CPUC activities and activities in other agencies (IDER CSF WG, CEC and CAISO interagency matters, interconnection/Rule 21/SIWG, other proceedings that may impact or be impacted by locational value calculation such as AB 350/IRP and LTPP/TPP/RPS)

Steward WG agreements into CPUC decisions when necessary

More Than Smart role

Engaged by Joint Utilities to facilitate both the ICA & LBNA working groups. This leverages the previous work of MTS facilitating stakeholder discussions on ICA and LBNA topics. Slide4

Schedule – tracking progress

 

May

June

July

Aug

Sep

Oct

Nov

Dec

Jan

Feb

Mar

Apr

May

Jun

CPUC DELIVERABLES

Demo B

Report

 

x

 

 

 

 

Draft

Final

 

 

 

 

 

 

WG Report

 

 

 

 

 

 

Draft

Final

 

 

 

 

 

 

Long Term Refinement Report

 

 

 

 

 

 

Draft

Final

 

 

 

 

Draft

Final

SHORT

TERM DELIVERABLES

6.1.a

LNBA Maps

X

6.1.b

Grid services

X IDER

LONG TERM REFINEMENT

6.2.1 (A) long-term location-specific benefits

X

X

6.2.1 (B) Smart inverters

X

X

6.2.1

(C) Alternatives to avoided cost method

X

X

6.2.1 (D)

DER avoided cost in same substation

X

X

OTHER: data

X

XSlide5

Schedule of reports

Category

Report

Oct

Nov

Dec

Deadline

Lead Author

LNBA & Demo B

Short-term

IOU Final Report for Demo B

11/15-11/16 (tentative)

– Final WG meeting to discuss issues before Dec. report

12/16

: final

report submitted

Dec. 31*

Each IOU, individually

(3 reports)

WG Final Report on LNBA / Demo B “short term” topics

11/30

-Draft to WG

12/8:

final

stakeholder comments due

12/16

: final

report submitted

Dec. 31*

MTS on behalf of WG

Long-term Refinement

WG Interim Status Report on LNBA “long-term refinement” topics

10/26

:

comments on scope due

10/31

: draft to WG

11/7

: final

comments due

11/10:

final report submitted

Nov. 10

MTS on behalf of WG

WG Final Report on LNBA “long-term refinement” topics

Jun. 30

MTS on behalf of WGSlide6

5. Interim Report Process10/12: Initial Scoping Documents Submitted for four topics

10/19: WG MeetingPresent Initial Scoping Documents

Present Comments on Initial Scoping Documents

10/26: Stakeholder Written Comments on Initial Scoping Documents

11/1: Draft Interim Status Report Shared with WG

11/10 Interim Status Report Submitted

6Slide7

Update on deferability criteria and grid services (6.1.b)Slide8

Long-Term RefinementsLNBA Working Group MeetingOctober 19, 2016

8Slide9

Agenda6.2(1)(A): Locational Benefits Over Long-Term Horizon

6.2(1)(B): Locational Grid Services Provided By Advanced Smart Inverter Capabilities6.2(1)(C): Alternatives Avoided Cost Method

6.2(1)(D): Effect on Avoided Cost of DER Working “in Concert”

9Slide10

6.2(1)(A): Locational Benefits Over Long-Term Horizon

Based on experience, explore whether/how probability estimates could be made that undetected needs will arise the during distribution planning period

procurement of DERs will avoid future upgrades beyond the distribution planning period

Key questions:

What is uncertainty within 10 year planning window and what are key drivers of uncertainty?

What are “undetected needs”?

Is it appropriate to estimate system needs/projects/costs beyond 10 year planning window?

Can DER deployment mitigate these costs?

What is the possible magnitude of these costs

What are possible approaches to this issue?

How should these be reflected in LNBA refinement?

10Slide11

6.2(1)(B): Locational Grid Services Provided By Advanced Smart Inverter Capabilities

11

Examples of seven functions identified by SIWG: (i) Disconnect/Reconnect, (ii) Limit Max Real Power, (iii) Set Real Power, (iv)

Freq

-Watt Mode, (v) Volt-Watt Mode, (vi) Dynamic Reactive Current Support, (vii) Schedule Power Values and Modes

Key questions:

Any additions/subtractions to the seven functions?

Which grid services enabled by each function?

Which grid services enabled by smart inverter functions are included in LNBA and which are not?

What new methodologies are needed? Slide12

6.2(1)(C): Alternatives Avoided Cost Method

12

Key questions:

What are alternative methods?

“Deferral Value” based on Long-Run Incremental Costing?

“Present Value” of alternative expansion plans including cost of customer interruptions

“Reliability Differentiated Rates”

“Annual Deferral Value”

What are strengths/weaknesses/typical applications for each?

What are data needs for each?

What are some improvements to LNBA?

Include full set of costs and benefits

Use dynamic models

Use marginal distribution costs

Link ICA/LNBA and DER procurement and load forecasting

Optimize subject to GHG constraints and minimizing ratepayer cost

Test cost-causation hypothesisSlide13
Slide14

Process to Achieve LNBA

The process of determining the locational impacts of a DER (or portfolio of DERs) requires three steps: (1) determining the impact of the DER on the electric grid [using ICA]; (2) translating that impact into cost—whether an avoided cost (i.e

., a reduction in overall cost of providing electricity via the electric grid) or an increased cost—for each of the components listed above; and (3) aggregating, into a single present value of locational net benefit impact, the identified costs across all value components, for the life of the DER being evaluated. Slide15

PG&E Distribution Resources Plan: Chapter 2 – Distribution Resources Planning Page 64 Slide16
Slide17

Example of Substation Capacity Deferral

17

EE?Slide18

6.2(1)(D): Effect on Avoided Cost of DER Working “in Concert”

18

Determine method for evaluating effect on avoided cost of DER working “in concert” (e.g. using a DERMS) in the same electrical footprint of a substation.

Key questions:

What are upgrades can be avoided/deferred?

If requirements for avoiding/deferring DERs are technology neutral, DER working in concert don’t require modification in avoided cost methodology itself.

Enhancement is required in determining how aggregation/coordination of resource changes which costs are avoided and to what degree.

DERs working in concert will perform differently than the same DERs without coordination (e.g. increased reliability/diversity).

Fewer resources may be needed if working in concert

DERs in concert may complement each other such that avoided costs are greater than the sum of their independent avoided costs

LNBA WG should review assumptions on how DERs interact, including through DERMS, and the impacts on benefits/costs to ratepayers