Natalie Parks PE American Structurepoint Inc Utility amp Railroad Coordinator June 11 2015 Todays Topics Basic INDOTLPA Program Key People Utility Coordination Process Submittals ID: 776191
Download Presentation The PPT/PDF document " LPA – Utility Coordination" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.
Slide1
LPA – Utility Coordination
Natalie Parks, P.E.
American
Structurepoint
, Inc.
Utility & Railroad Coordinator
June 11, 2015
Slide2Today’s Topics
Basic INDOT/LPA Program
Key People
Utility Coordination Process
Submittals
Agreements
Work in Contract
Case Studies
Utility Company Comments
Slide3INDOT/LPA Program
Mission:
To provide Stewardship and Technical assistance to Local Public Agencies through excellent education and collaborative relationships, to plan, build and maintain a superior transportation system that promotes economic growth, ensures safety and complies with all local, state, and federal regulations.
Slide4INDOT/LPA Program
INDOT is Involved on an LPA Project When Federal Dollars are Spent
District LPA Project Manager to secure federal funds.
District Utility
Coordination
when
there is a reimbursable utility relocation.
Must follow federal regulations for utilities CFR 645
(http://www.fhwa.dot.gov/programadmin/utility.cfm
Must follow 105 IAC 13
Utility Accommodation Policy (July 2013)
INDOT Design Manual
LPA Design Guidance Document - Chapter
8
Slide5LPA Utility Coordination
Key people
LPA Employee in Responsible Charge (ERC)
LPA Design Project Manager
Utility Coordinator
Utility Personnel
INDOT Project Manager
Right-of-Way Manager
Slide6LPA Utility Coordination
Responsibilities of Key People: LPA ERC
According to LPA guidance document (1-1.04), “overseeing Utility and Railroad relocatio
n work”
Slide7LPA Utility Coordination
Responsibilities of Key People: LPA ERC
Review
and approve requests form utility coordinator for time extensions/adjustments
Concur with, approve, and sign reimbursable and subordination agreements
Review and sign Notice of Plan Approval
Review and sign Notice to Proceed
Approve and pay all invoices
Remember: They have not gone through this training
Slide8LPA Utility Coordination
Responsibilities of Key People: Project Manager/Designer
Work with the utility coordinator to identify critical points
Communicate all plan changes to the utility coordinator
Responsible for watching cash flow
Signs the work plan as the project manager
Slide9LPA Utility Coordination
Responsibilities of Key People: Utility Coordinator
All of the responsibilities already discussed in other sessions
No Utility Oversight Agent…
Work with Project Manager to establish objectives for utility coordination deliverables
Work with Project Manager to develop the risk report
Periodically review project funding with Project Manager for
reimbursables
Provide quality assurance review of work plan for compliance
Agreements & Invoice review
Provide guidance on the use of SUE
Slide10LPA Utility Coordination
Responsibilities of Key People: District Utility Coordinator
Provide oversight only when a utility is reimbursable
Submits agreement to Central Office for P.O.
Submits agreement to Central Office for FMIS authorization
Does not provide general process oversight
Does not sign notice to proceeds, notice of plan approval, work plans
Does not review invoices from utilities for reimbursement
Slide11LPA Utility Coordination
Ultimately the Utility Coordinator and the Design PM are both responsible for ensuring 105 IAC 13 is followed.
Business decisions are made between the Design Team and the ERC
Slide12LPA Utility Coordination Process
Process is the same – (105 IAC 13)
Research – 1 to 2 weeks
Initial Notice – 1 to 2 months
Verification Plans – 2 to 4
months
Conflict Analysis – 2 to 4 months
Work Plan Development – 1 to 6 months
Reimbursable Agreements – 2 to 4 months
Notice to Proceed/Construction
Slide13LPA Utility Coordination Process
Follow the 105 IAC 13 rules and allow the appropriate time for responseCopy project owner representative on all submissionsInclude INDOT PMInclude MPO if funding is coming from that agencyINDOT’s District Utility Coordinator is involved in a LPA projects Utility Coordination process, only when there are Reimbursable Agreements. Do NOT use “minor” unless it is a minor project
LPA Utility Coordination Process
Slide14Research Phase:Many municipalities do not have a permit programRely more on:Indiana 811Field visitsField surveysUse previous project information if availableTalk to the LPA utility/engineering dept.
LPA Utility Coordination Process
Slide15Initial Notice:Do not need to contact Phil Ivy or Troy BoydProvide an aerial view of the project areaRequest information regarding any property interestsBring utilities to the table around verification plans to discuss Right-of-Way needsEstablish need for replacement property if the right-of-way acquisition causes the subordination of compensable property rights
LPA Utility Coordination Process
Slide16LPA Utility Coordination Process
Tracings Submission should
include:
Utility Work Plan/Relocation Drawings from each utility or Letter of No Conflict
LPA/Utility Reimbursement Agreement for each reimbursable utility
Utility FMIS authorization letter or e-mail
Utility
Certification
Note: a certification must be signed by an oversight agent if there exceptions. Forward LPA certifications need OSA signatures to Steve Robinson
Utility Special
P
rovisions
Slide17LPA Utility Coordination Process
Reimbursable Agreements
Use the INDOT LPA Agreements as established by INDOT General Counsel
Should build in approximately 4 months into the schedule when agreements are needed
Should submit to INDOT prior to sending to utilities
Should submit to LPA Counsel prior to sending to utilities
Remind LPA that the agreement is approved by INDOT General Counsel and all revisions must be approved by them
Slide18LPA Utility Coordination Process
Plan Approval
Prepare Notice of Plan Approval and provide to LPA ERC for signature
Some utilities will need approval prior to beginning permitting. This is especially important for RR permits.
Prepare
Notice to
Proceed
If right-of-way staking and clearing will be done before the letting, then prepare NTP when that work has been scheduled
If Contractor will do right-of-way clearing and staking, then prepare NTP once project has been successfully
awareded
NOTE: This is a result of utilities being “gun shy” due to the number of LPA projects that have been delayed
Slide19LPA Utility Coordination Process
Construction
Still on Point
Coordinate utilities with LPA personnel as needed
Suggest the use of an advanced right-of-way clearing and staking contract
Suggest the use of consultant utility relocation oversight
Slide20Escalation Chain
Become well educated in ALL state and federal documents
Concurrently contact:
Supervisor/UAR of Utility
Design Project Manger
LPA ERC
INDOT District LPA project manager
INDOT
Central Office – Kenny Franklin, Statewide Director
Slide21Escalation Chain
DOCUMENT
EVERYTHING
Slide22Reimbursable Relocations
Too
often a local public agency will find out TOO late in a project that there is an sizeable REIMBURSABLE utility that negatively impacts the project
Utility coordinator should provide a list of all confirmed reimbursable utility relocations at the end of Stage 1.
One (1) large reimbursable utility can create a critical cost that may have a severe impact such that a LPA cannot move forward with their project.
Or worse, become a burden afterward
Slide23LPA Utility Relocation Agreements
When is an LPA/Utility agreement required?
Only when a utility relocation is required due to being in
direct conflict
. There are 3 scenarios:
Reimbursable:
When a utility has a compensable land right
When a municipal utility is located in the right-of-way of a project owned by same municipality
Reimbursable : Work in Contract - The utility relocation is constructed as part of the road contract.
Non-reimbursable: Work in Contract -
T
he utility agrees to include the utility relocation as part of the road contract. These bid items should be identified as “non participating” and 100% of the successful bid will be paid up front by the utility company.
Slide24LPA Utility Relocation Agreements
Municipal Agreements
Reimbursable – LPA will usually push for municipal water & sanitary work to be in contract
Agreement is required if the Utility Board is a separate entity from the Board of Public Works (or the “owner” of the project)
Agreement is NOT required when the two entities are the same
Non-reimbursable – the LPA can opt to have the work done in contract to upgrade, etc., but this will not be reimbursable
Work in-contract Agreement
The utility will pay 100% of the cost
Slide25Work in Contract
Early on (Stage 1) ask the utility companies to consider including their relocations in the LPA project.
Benefits – Why do we recommend WIC :
Allows better overall construction coordination with the contractor in control of the scheduling
Reduces, and hopefully can eliminate, utility delays
Saves on overall construction costs (Mobilization, pavement cuts, shoring, overall efficiency…)
Eliminates claims, contractor responsible for the x, y and z location
Saves on overall construction time
“The Contractor knows where everyone went”.
Slide26Work in Contract
SECTION 5 – REIMBURSEMENT (WORK IN-CONTRACT)
Example Breakdown in Agreement:
“(a)
20
% of the cost to design and prepare construction plans, specifications and preliminary itemized cost estimate for relocation of the Utility’s facilities shall be borne by the Local Public Agency.
(b)
20
% of the cost to provide testing and inspection services for relocation of the Utility’s facilities shall be borne by the Local Public Agency.
(c) The Local Public Agency shall bear
20
% of the cost of relocating the Utility’s facilities. (See exhibit “B”). “
Slide27Work in Contract
SECTION 5 – REIMBURSEMENT
“The
cost of relocation of the Utility’s facilities (provided for in (c))
shall equal
the amount paid by INDOT to the contractor (based upon the actual units of work performed at the unit prices set out in the contractor’s itemized proposal or extra work agreement), selected in accordance with the procedure in Section 2
.”
NOTE: regardless of whether the utility is reimbursable, the LPA is agreeing to include the utility work in their contract with the Contractor, which is being bid by INDOT. INDOT will invoice the LPA for their portion of the work and the LPA will then invoice the utility for their portion of the work.
Slide28Work in Contract
SECTION 5 – REIMBURSEMENT
“The
estimated cost of relocation is $_
(See Exhibit “B” for an itemized estimate of all anticipated costs, including but not limited to, materials, labor, and equipment costs.)
The
estimated cost of non-reimbursable relocation work to the utility’s facilities is $
. The Utility has appropriated, duly made and entered of record, the sum of $
_ to apply to the cost of the project. A copy of the Utility’s official record wherein such appropriation was made is attached as Exhibit “C”. If the amount to be contributed by the utility is zero then no Exhibit “C” is attached
.”
Slide29Work in Contract
SECTION 5 – REIMBURSEMENT
When the utility is 100% reimbursable, then the amount listed is the estimated cost of non-reimbursable work would be $0.00.
When the utility is partially reimbursable, the breakdown of reimbursable to non-reimbursable work must be provided.
When the utility is non-reimbursable, the dollar amount would be equivalent to the total cost of relocation as shown in Exhibit “B”.
Some municipalities may opt to have the utility pay the 20% match. This would be done using an MOA, not this agreement.
Slide30Work in Contract
SECTION 5 – REIMBURSEMENT
Highly
recommend the use of a summary sheet when doing a Work-in-Contract agreement on a LPA project and included with Exhibit “B”
Summary sheet would include:
Breakdown of standard costs per FHWA
Total cost of relocation that is shown in the agreement
Breakdown of costs to be borne by INDOT and borne by LPA
If the cost is $100,000 then identify the cost to be borne by INDOT to be $80,000 and the cost to be borne by LPA to be $20,000
When the utility shall bear a portion of the cost, then separate that as well
Slide31Work in Contract
SECTION 5 – REIMBURSEMENT (EXAMPLE SUMMARY)
Slide32Work in Contract
The reimbursements paid for under SECTION 5: (a), (b), and (c) shall include the cost sharing that is paid with federal funds. This project shall be split in accordance with the funding established, which is typically paid with 20% LPA funding and 80% Federal funding.
How the payments are made:
Prior to the awarding of the contract, the LPA submits their 20% of the Utility Relocation per the Construction estimates.
Contractor actual cost invoices are reviewed and approved by the project manager and paid for with 20% LPA funds / 80% Federal funds.
Any cost overruns or claims should be approved and paid for at the same percentages as the original contract.
Slide33Additional Charges and Invoices
Assist the ERC in determining if a scope change to the existing agreement, or a cost overrun requested by the utility are appropriate.
Make sure that all scope changes and cost overruns have been approved by the ERC prior to the utility company proceeding with work. If not, and the utility does any of this work without prior approval, these charges are not reimbursable.
FHWA and INDOT will not reimburse for addition work without prior authorization.
Slide34Additional Charges and Invoices
Request that invoices be sent to
BOTH
the LPA ERC and the utility coordinator
UC can ensure the code is being followed
Allows the UC to review scope was adhered to
Allows the UC to review the total invoice and compare it to similar projects to verify invoice is reasonable
Allows the UC to verify only work that is reimbursable was invoiced
Assist the ERC in ensuring that the charges are per the agreement and the utility invoices are correct.
I
f an invoice is incorrect or inappropriate, a
dvise
the ERC
in resolving the issues with the utility.
Slide35Case Study
Slide36Project involves:Municipal utility relocationRight-of-way limitationsLift station AND Booster StationPortions of utility on documented, exclusive easementProject owner owns the utilityUtility requires relocation due to new roundabout & MSE walls
Case Study
Slide37Is the utility reimbursable?If so, by whom?Does the utility need to secure permanent right-of-way?If so, why?If not, why not?
Case Study
Slide38Case Study
Case Study
Case Study
Slide39Case Study – Existing
Pipeline Company has a 14” diameter gas pipeline that crosses an existing road that the LPA is proposing to add a lane.
Existing pipeline has a casing pipe that extends 5 ft. beyond the existing paved shoulder.
New pavement will extend beyond the end of the casing.
Pipeline Profile: The top of the pipeline is 6 ft. below the proposed pavement.
Existing pipe is structurally inadequate for the loading
without
a casing pipe.
Pipeline Company requested 100% reimbursement.Claim – Lose the ability to access the end of the casing pipe, therefore will not be able to slide the pipe out for future maintenance.They proposed 2 possible options and relocation costs: Option #1: Bore and install a new pipeline with thicker walls under the new wider pavement.Option #2: Open cut pavement, remove the existing casing, and provide maintenance to the existing pipeline, and install a no-load slab over pipeline.
Case Study
Exercise
Slide41What costs are reimbursable? Option 1: New pipe bored in placeOption 2: Remove CasingInspect and provide maintenance to coating under casing.Install no-load slab Note: Current Industry Design Standards no longer recommend a casing pipe be used due to cathodic corrosion.
Case Study
Slide42INDOT’s Response:Pipeline is in conflict with the roadway improvements due to the inadequate structural capacity of the pipe.Option 1: Only the segment of the pipeline between the existing roadway right-of-ways is within an easement with property interests, and therefore is eligible for reimbursement.Option 2: Removing the casing and inspecting the pipe’s outer wall coating is a maintenance item, and therefore is not reimbursable.Neither of these options proposed by the utility company will allow for future maintenance.
Case
Study
Slide43INDOT’s Response:Therefore only the no-load slab over the section of pipeline within the easement is reimbursable.It is the Utility Company’s decision on either boring and installing a new line, or open cutting and removing casing, and installing the no-load slab.The Utility Company should coordinate with LPA’s contractor to schedule open cut when road is shutdown.
Case Study
Practical Exercise
Slide44Utility Companies
Several issues utilities have had with LPA utility coordination
Wide range of experience levels
Do not know to follow the 105 IAC 13 when federal aid projects
LPA’s often will claim their projects are Minor Projects to attempt to hold utility companies to shorter response time
Utility companies receive notification to attend a “Pre-construction” meeting when they had not received a Notice to Proceed
LPA project lettings are often delayed
Slide45Subconsultant Utility Coordinator
When to use a
subconsultant
when your firm is prequalified?
1.) Relatively low experience level
2.) Difficult project
3.) Many reimbursable utility relocations
4.) Accelerated project development schedule
Slide46Questions?