/
LPA – Utility Coordination LPA – Utility Coordination

LPA – Utility Coordination - PowerPoint Presentation

jane-oiler
jane-oiler . @jane-oiler
Follow
347 views
Uploaded On 2018-11-03

LPA – Utility Coordination - PPT Presentation

Natalie Parks PE Utility amp Railroad Coordinator American Structurepoint Inc June 22 2016 Todays Topics Basic INDOTLPA Program Key People Utility Coordination Process Submittals ID: 711536

lpa utility reimbursable work utility lpa work reimbursable project coordination relocation contract cost indot erc process review manager utilities

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "LPA – Utility Coordination" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

LPA – Utility Coordination

Natalie Parks, P.E.

Utility & Railroad Coordinator

American

Structurepoint

, Inc.

June 22, 2016Slide2

Today’s TopicsBasic INDOT/LPA Program

Key PeopleUtility Coordination ProcessSubmittalsAgreementsWork in Contract

Case Studies

Utility Company CommentsSlide3

INDOT/LPA Program

Mission:

To provide Stewardship and Technical assistance to Local Public Agencies through excellent education and collaborative relationships, to plan, build and maintain a superior transportation system that promotes economic growth, ensures safety and complies with all local, state, and federal regulations.Slide4

INDOT/LPA Program

INDOT is involved on an LPA project whenfederal dollars are spent District LPA Project Manager to secure federal funds.

District Utility

Coordination

when

there is a reimbursable utility relocation.

Must follow federal regulations for utilities CFR 645

(

http://

www.fhwa.dot.gov/programadmin/utility.cfm

)

Must follow 105 IAC 13

Utility Accommodation Policy (July 2013)

INDOT Design Manual

LPA Design Guidance Document – Chapter

8Slide5

LPA Utility Coordination

Key peopleLPA Employee in Responsible Charge (ERC)

LPA Design Project Manager

Utility Coordinator

Utility Personnel

INDOT Project Manager

Right-of-Way ManagerSlide6

LPA Utility Coordination

Responsibilities of Key People: LPA ERC

According to LPA guidance document (1-1.04), “overseeing Utility and Railroad relocation work”Slide7

LPA Utility Coordination

Responsibilities of Key People: LPA ERCReview and approve requests from

U

tility Coordinator for time extensions/adjustments

Concur with, approve, and sign reimbursable and subordination agreements

Review and sign Notice of Plan Approval

Review and sign Notice to Proceed

Approve and pay all invoices

Remember: They have not gone through this trainingSlide8

LPA Utility Coordination

Responsibilities of Key People: Project Manager/DesignerWork with the Utility Coordinator to identify

critical points

Communicate all plan changes to the Utility Coordinator

Responsible for watching cash flow

Signs the work plan as the Project ManagerSlide9

LPA Utility Coordination

Responsibilities of Key People: Utility CoordinatorAll of the responsibilities already discussed in

other sessions

No Utility Oversight Agent…

Work with Project Manager to establish objectives for utility coordination deliverables

Work with Project Manager to develop the risk report

Periodically review project funding with Project Manager for

reimbursables

Provide quality assurance review of work plan for compliance

Agreements & Invoice review

Provide guidance on the use of SUESlide10

LPA Utility Coordination

Responsibilities of Key People: District Utility CoordinatorProvide oversight only when a utility is reimbursable

Submits agreement to Central Office for P.O.

Submits agreement to Central Office for FMIS authorization

Does not provide general process oversight

Does not sign notice to proceeds, notice of plan approval, work plans

Does not review invoices from utilities for reimbursementSlide11

LPA Utility Coordination

Ultimately the Utility Coordinator and the Design PM are both responsible for ensuring 105 IAC 13 is followed.Business decisions are made between the Design Team and the ERCSlide12

LPA Utility Coordination Process

Process is the same – (105 IAC 13)

Research – 1 to 2 weeks

Initial Notice – 1 to 2 months

Verification Plans – 2 to 4 months

Conflict Analysis – 2 to 4 months

Work Plan Development – 1 to 6 months

Reimbursable Agreements – 2 to 4 months

Notice to Proceed/ConstructionSlide13

LPA Utility Coordination Process

Follow the 105 IAC 13 rules and allow the appropriate time for response

Copy project owner representative on all submissions

Include INDOT PM

Include MPO if funding is coming from that agency

INDOT’s District Utility Coordinator is involved in a LPA projects Utility Coordination process, only when there are Reimbursable Agreements.

Do NOT use “minor” unless it is a minor project

LPA Utility Coordination ProcessSlide14

Research Phase:Many municipalities do not have a permit program

Rely more on:Indiana 811Field visits

Field surveys

Use previous project information if available

Talk to the LPA utility/engineering dept.

Establish risks with LPA ERC and Project Manager

Prepare risk analysis report

Prepare mitigation options

LPA Utility Coordination ProcessSlide15

Initial Notice:Do not need to contact Phil Ivy or Troy Boyd

Provide an aerial view of the project areaRequest information regarding any property interestsRequest copies of as-built information

Using as-built information, begin developing conflict matrix to share with LPA ERC

Meet

EARLY

and

OFTEN

In person meetings are always best, however conference calls and go-to meetings can also be used as needed

LPA Utility Coordination ProcessSlide16

LPA Utility Coordination Process

FIRST early coordination meeting should be after verification plans are submitted

Determine

WHAT

the facilities are

and

WHERE

they

are located

Determine

ROW

needs, including replacement property

Identify areas of significant concern, ask for

ballpark

estimates, and refine conflict matrix

Determine level of SUE that may be needed

Determine if a utility is eligible for reimbursement

Determine if a work-in-contract agreement can be used

Make sure LPA ERC is fully invested and understands what is neededSlide17

LPA Utility Coordination Process

Preliminary Field Check Meeting

Should NOT be the first time meeting with

utilities

Prior to meeting, review plans and identify

critical

points

and update utility conflict matrix to use

as

talking

points with the utilities

Determine where SUE work is needed and

type

(

i.e. GPR or Pothole)

Determine

WHO

will do the SUE work

Discuss any design options available

Discuss environmental concerns/commitments

Discuss with LPA ERC options moving forwardSlide18

LPA Utility Coordination Process

Work Plans

Ensure the existing information matches what

has

been

previously provided

Ensure the proposed information is consistent with discussions regarding relocation needs

Verify needs of utility before relocation begins

Review schedule with the utility and

discuss

sequencing

and/or staging

Prepare Gantt chart & overall relocation drawing

Review work plans with the LPA ERC

Review any agreements or work-in-contract opportunities with LPA ERCSlide19

LPA Utility Coordination Process

Utility Certification

Certification will require an exception if the utility is not relocated prior to letting

Includes Special Provision

Submit work plans & relocation drawings

Depending on relocation work necessary & proposed utility schedule, may need to submit the Gantt chart, overall relocation scheme, and conflict matrixSlide20

LPA Utility Coordination Process

Tracings Submission should include:

Utility Work

Plan or Letter of No

Conflict

Utility Relocation Drawings from each utility

Utility Special Provisions

Utility Certification

Utility schedules should be discussed with LPA ERC, INDOT District PM,

and INDOT

Area Engineer to establish a reasonable time set and avoid delay claims caused by utility delaysSlide21

LPA Utility Coordination Process

Plan Approval

Prepare Notice of Plan Approval

Some utilities will need approval prior to beginning permitting. This is especially important for RR permits.

Prepare Notice to Proceed

If right-of-way staking and clearing will be done before the letting, then prepare NTP when that work has been scheduled

If

contractor

will do right-of-way clearing and staking, then prepare NTP once project has been successfully awarded

NOTE: This is a result of utilities being “gun shy” due to the number of LPA projects that have been delayedSlide22

LPA Utility Coordination Process

Construction

Still on Point

Coordinate utilities with LPA personnel as needed

Suggest the use of an advanced right-of-way clearing and staking contract

Suggest the use of consultant utility relocation oversight

Review and update utility conflict matrix until all conflicts have been mitigatedSlide23

Escalation Chain

Become well educated in ALL state and federal documentsConcurrently contact:

Supervisor/UAR of Utility

Design Project Manger

LPA ERC

INDOT District LPA project manager

INDOT Central Office – Mike HoySlide24

Escalation Chain

DOCUMENT EVERYTHINGSlide25

Reimbursable Relocations

Reimbursable utilities can be

problematic

for

LPA’s

LPA may not have accounted for the

cost

(

NOTE

: This

is changing)

LPA may not have available funding in

their CN

budget

Establish all utilities in a reimbursable position before going to Stage 1 plans

Request ball park estimates from reimbursable utilities at verification plans

Work with LPA ERC to refine scope as neededSlide26

LPA Utility Relocation Agreements

When is an LPA/Utility agreement required?

Only when a utility relocation is required due to being in

direct conflict

.

There are

three

scenarios:

Reimbursable:

When a utility has a compensable land right

When a municipal utility is located in the right-of-way of a project owned by same municipality

Reimbursable:

Work in Contract

The utility relocation is constructed as part of the road contract.

Non-reimbursable

:

Work in Contract

T

he utility agrees to include the utility relocation as part of the road contract. These bid items should be identified as “non participating” and 100% of the successful bid will be paid up front by the utility company.Slide27

LPA Utility Relocation Agreements

Reimbursable Agreements

Use the INDOT LPA Agreements as established by INDOT General Counsel

Should build in approximately

four

months into the schedule when agreements are needed

Should submit to LPA Counsel prior to

sending

to

utilities

Alert INDOT project manager of reimbursable agreement and include on all quarterly reports submitted to INDOTSlide28

LPA Utility Relocation Agreements

Municipal Utility Agreements

LPA will usually push for municipal water & sanitary work to be in

contract

Reimbursable – ONLY when there is a direct conflict AND the utility is owned by the SAME political subdivision as the project owner

Non-reimbursable – Betterments or upgrades to existing facilities, utility pays 100% of the cost

A work-in-contract agreement will be required

when the signing authority for the utility is different than the signing authority for the project (i.e. Utility Board and Board of Public Works are separate boards)Slide29

Work in Contract

Benefits of

Work in Contract

Allows better overall construction coordination with the contractor in control of the scheduling

Reduces utility delays

Saves on overall construction costs (Mobilization, pavement cuts, shoring, overall efficiency…)

Eliminates claims, contractor responsible for the x, y and z location

Saves on overall construction

time

The Contractor knows where everyone

went.

”Slide30

Work in Contract

SECTION 5 – REIMBURSEMENT (WORK IN CONTRACT)

“(

a) ______% of the cost to design and prepare construction plans, specifications and preliminary itemized cost estimate for relocation of the Utility’s facilities shall be borne by the Local Public Agency.

 

(

b) _______% of the cost to provide testing and inspection services for relocation of the Utility’s facilities shall be borne by the Local Public Agency.

 

(

c)

The

Local Public Agency shall bear

100

% of the cost of relocating the Utility’s facilities. (See exhibit “B

”).”

NOTE

: For reimbursable utilities (a) and (b) should also be 100

%.

For non-reimbursable utilities (a) and (b) will be 0%. (c) will always

be 100

%.Slide31

Work in Contract

SECTION 5 – REIMBURSEMENT“The

cost of relocation of the Utility’s facilities (provided for in (c))

shall equal

the amount paid by INDOT to the contractor (based upon the actual units of work performed at the unit prices set out in the contractor’s itemized proposal or

extra

work agreement), selected in accordance with the procedure in Section 2

.”

NOTE

: regardless of whether the utility is reimbursable, INDOT is paying the Contractor the agreed upon unit price.

Before

construction begins, INDOT will invoice the LPA for their portion of the bid, including the utility work.

When

the utility is non-reimbursable, the LPA will then invoice the utility for their portion of the work

.Slide32

Work in Contract

SECTION 5 – REIMBURSEMENT“The estimated cost of relocation is $_

(See Exhibit “B” for an itemized estimate of all anticipated costs, including but not limited to, materials, labor, and equipment costs

.)

 

The estimated cost of non-reimbursable relocation work to the utility’s facilities is $

. The Utility has appropriated, duly made and entered of record, the sum of $

_ to apply to the cost of the project. A copy of the Utility’s official record wherein such appropriation was made is attached as Exhibit “C.” If the amount to be contributed by the utility is zero then no Exhibit “C” is attached.”Slide33

Work in Contract

SECTION 5 – REIMBURSEMENTWhen the utility is 100% reimbursable, then the amount listed

is

the estimated cost of non-reimbursable work would be $0.00.

When

the utility is partially reimbursable, the breakdown of reimbursable to non-reimbursable work must be provided.

When

the utility is non-reimbursable, the dollar amount would be equivalent to the total cost of relocation as shown

in

Exhibit

“B”.

Some

municipalities may opt to have the utility pay the 20% match.

This

would be done using an MOA, not this agreement. Slide34

Work in Contract

SECTION 5 – REIMBURSEMENTHighly recommend the use of a summary sheet when doing a Work-in-Contract agreement on a LPA project and included with Exhibit “B”

Summary sheet would include:

Breakdown of standard costs per FHWA

Total cost of relocation that is shown in the agreement

Breakdown of costs to be borne by INDOT and borne by LPA

If the cost is $100,000 then identify the cost to be borne by INDOT to be $80,000 and the cost to be borne by LPA to be $20,000

When the utility shall bear a portion of the cost, then separate that as wellSlide35

Work in Contract

SECTION 5 – REIMBURSEMENT (EXAMPLE SUMMARY)Slide36

Work in Contract

The reimbursements paid for under SECTION 5: (a), (b), and (c) shall include the cost sharing that is paid with federal funds. This project shall be split in accordance with the funding established, which is typically paid with 20% LPA funding and 80% federal

funding.

How

the payments are made:

Prior to the awarding of the contract, the LPA submits their 20% of the Utility Relocation per the

construction

estimates.

Contractor actual cost invoices are reviewed and approved by the project manager and paid for with 20% LPA funds / 80%

rederal

funds.

Any cost overruns or claims should be approved and paid for at the same percentages as the original contract.Slide37

Additional Charges and Invoices

Assist the ERC in determining if a scope change to the existing agreement, or a cost overrun requested by the utility are appropriate.

Make

sure that all scope changes and cost overruns have been approved by the ERC prior to the utility company proceeding with work. If not, and the utility does any of this work without prior approval, these charges are not reimbursable.

FHWA and INDOT will not reimburse for additional work without prior authorization.Slide38

Additional Charges and Invoices

Request that invoices be sent to

BOTH

the LPA ERC and the utility coordinator

UC can ensure the code is being followed

Allows the UC to review scope was adhered to

Allows the UC to review the total invoice and compare it to similar projects to verify invoice is reasonable

Allows the UC to verify only work that is reimbursable was invoiced

Assist

the ERC in ensuring that the charges are per the agreement and the utility invoices are correct.

If

an invoice is incorrect or inappropriate, a

dvise

the ERC

in resolving the issues with the utility.Slide39

Case StudySlide40

Project involves:

Municipal utility relocation

Right-of-way limitations

Lift station AND Booster Station

Portions of utility on documented, exclusive easement

Project owner owns the utility

Utility requires relocation due to new roundabout & MSE walls

Case StudySlide41

Is the utility reimbursable?If so, by whom?

Does the utility need to secure permanent right-of-way?If so, why?If not, why not?

Case StudySlide42

Utility Companies

Several issues utility owners have had with LPA utility coordination

Wide range of experience levels

Do not know to follow the 105 IAC 13 when federal aid projects

LPA’s often will claim their projects are Minor Projects to attempt to hold utility companies to shorter response time

Utility companies receive notification to attend a “Pre-construction” meeting when they had not received a Notice to Proceed

LPA project lettings are often delayedSlide43

Questions?