Report by LST-SYS coordinator Report by LST-SYS coordinator

Report by LST-SYS coordinator - PowerPoint Presentation

avantspac
avantspac . @avantspac
Follow
352 views
Uploaded On 2020-08-05

Report by LST-SYS coordinator - PPT Presentation

MTeshima MaxPlanckInstitute for Physics Current Key ParticipantsI CTAProtoLST structure Structure LST SYS MTeshima LST STR TSchweizer LST CAM OBlanch About 50 people subscribed in CTAprotoLST ID: 798456

structure lst camera telescope lst structure telescope camera design prototyping electronics cost cta proto ifae mpp elements current fpi

Share:

Link:

Embed:

Download Presentation from below link

Download The PPT/PDF document "Report by LST-SYS coordinator" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

Report by LST-SYS coordinator

M.Teshima

Max-Planck-Institute for Physics

Slide2

Current Key Participants-I

CTA-Proto-LST structure

Structure

LST SYS

M.Teshima

LST STR

T.Schweizer

LST CAM

O.Blanch

About 50 people subscribed in CTA-proto-LST

Slide3

Current key participants-II

Institutes/members

MPP;

P.Collin

, T.Schweizer, E.Lorenz,

R.Mirzoyan

, M.Teshima, R.Wagner,

D.Fink

,

O.Reimann

, H.Wetteskind,

C.Jablonski

Telescope structure, Camera, MC

IFAE;

O.Blanch

,

M.Martinez

,

D.Mazin

,

J.Cortina

,

M.Barcelo

,

Camera, Telescope Bogie, Physics

LAPP;

G.Lammana

,

G.Deleglise

,

L.Brunetti

Camera support arch structure, Driving system

IN2P3;

P.Vincent

,

P.Brunetti

,

F.Touissenel

,

Electronics

CEA;

P.Micolon

Alternative telescope design

CIEMAT;

E.Carmona

M.C. dedicated to CTA-LST

UCM;

J.A.Barrio

,

J.M.Miranda

Electronics

INFN Italy;

M.Mariotti

, R.

Paoletti

Mirror, Electronics

ETH/Zurich;

A.Biland

,

AMC

Japan;

H.Kubo

,

R.Orito

,

S.Inoue

,

R.Enomoto

FPI, Electronics, Mirrors, Physics

Maybe about 30 people are really interested in CTA-Proto-LST

Slide4

Current Key participants

For individual elements

CTA-STR (Structure and optics)

Telescope structure MPP, CEA

Telescope Bogie MPP, IFAE

Telescope Arch LAPP, MPP

Telescope Drive LAPP

Mirrors INFN, Japan

AMC ETH,

U.Zurich

CTA-CAM

Camera Structure MPI, IFAE

Cooling MPI, CIEMAT?

FPI MPI, IFAE, Japan

Winston cone ??

Readout Electronics INFN, Japan, IN2P3

Trigger IFAE

Slide5

Options for technologies

Telescope Structures

MPP+MERO+LAPP Design (full CFRP

Space frame structure)

CEA alternative (CFRP mirror mount, steal under-structure and pit)

Camera

Sealed camera with low weight, low power consumption

FPI

Hamamatsu R8619, Electron Tube XXXX (not yet delivered)

Readout

Dragon,

Nector

, (Target?)

Slide6

Project Plan

Baseline Design Doc (BDD)

Detail Design

Technical Report

Prototype of elements

Prototype Report

Final Design Doc

 Prototyping of LST (beginning of 2013)

Slide7

Resources-I

PP budget will support a part of the following actions

Testing CFRP elements (Only critical elements)

Design by MERO (2nd / 3rd iteration)

FPI development of PM with Hamamatsu

Missing significant part of prototyping

Individual groups must look for the resources

Slide8

Resources-II

Problem: We can not enjoy the cost reduction in the mass-production. Everything must be very close to the market price. No big discount from industries.

Rough estimation by M.T.

(Total LST Proto project may cost about 8-9MEuro)

Structure (3MEuro)

Telescope Structure Prototyping

2000KEuro

Foundation

500KEuroDriving sys/Motors  500KEuro?

Camera (2.5MEuro)

PMTs

for Proto-Camera (3000PMTs)

1000KEuro

Readout Electronics (3000ch)

1000KEuro

Slow control, LV, HV, etc (3000ch)

300KEuro

Cooling /Humid. Control

200KEuro

Optics (1.5-2MEuro)

Mirrors (400m2)

1000KEuro

AMC (400 units)

400KEuro?

Others (1MEuro)

Local labors, Calibration system, Online System, UPS, Shipping, contingency

Slide9

Resources-III

We need to define the specification/requirements and design of LST

asap

, and then estimate the cost for

for development (

PMTs

,

Mirrros

, CFPR tubes, electronics, etc.)

for Prototyping (the first telescope)

for Mass production (7 more telescopes)

For examples, offers for 3000PMTs and 150,000PMTs are quite different

Slide10

Critical Path

We need the dedicated MC for LST

For the optimization of F/D and FOV

Structure will require

F/D = 1.2, FOV=4 degrees, 2ton cameras

If the requirements exceed these numbers, the current design will experience the significant change/modification

Slide11

Risks

I do not see any significant risks at a moment, but we need to list up all possible risks at least before starting prototyping.

Slide12

Cost estimate

It is now on-going by T.S. and O.B.. They will deliver us reliable numbers with our best knowledge.

We need three costs

Cost for developments/prototyping elements

Cost for prototyping LST

Cost in the construction phase (mass production)