MICE CONSTRUCTION PROJECT MICE CONSTRUCTION PROJECT

MICE CONSTRUCTION PROJECT - PowerPoint Presentation

bethany
bethany . @bethany
Follow
344 views
Uploaded On 2022-06-08

MICE CONSTRUCTION PROJECT - PPT Presentation

in the US Alan Bross Fermilab May 7 2013 Outline Project Team Scope of Effort Execution Plan Phase I amp II Deliverables Some historical context Schedule details Critical Dates L2 Management Team ID: 915235

ral mice schedule 2013 mice ral 2013 schedule resource bross loaded review alan step test deliverables complete amp ship

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "MICE CONSTRUCTION PROJECT" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

MICE CONSTRUCTION PROJECTin the US

Alan Bross

Fermilab

May

7

, 2013

Slide2

Outline

Project Team

Scope of Effort

Execution PlanPhase I & II DeliverablesSome historical contextSchedule detailsCritical DatesL2 Management TeamOrganizational Implementation Moving ForwardConclusion

Alan Bross | MICE Resource Loaded Schedule Review (RAL, May 7-8, 2013)

2

Slide3

L2 Management Team

Alan Bross | MICE Resource Loaded Schedule Review (RAL, May 7-8, 2013)

3

Magnet Fabrication

Spectrometer solenoids and Coupling Coils

RF Fabrication

201 MHz cavities & components

Vacuum vessels

Detector

Trackers

Trackers to be integrated with SS when they arrive at RAL

Cerenkov

Magnetic shielding

Partial return yoke

US component integration

US liaison for installation and commissioning

Likely stationed at

RAL

+

LiH

absorbers (Fermilab)

Slide4

Scope of Effort

Detectors (Complete)

Two fiber trackers with readout & cryogenics

Two Cherenkov detectorsAbsorbersLiH Disk (complete)LiH WedgesTwo superconducting spectrometer solenoidsTwo large-aperture (1.5m), 2.5T SC solenoids, Coupling Coil Magnet (CCM)CCM Prototype will be used in MuCool Test Area Two needed for MICE Step VIRF SystemEight 201 MHz cavities with tuners and vacuum vesselsIntegrated with CCM

RF power components (through NSF MRI)Commercial productsMagnetic Analysis and stray-field mitigation

Design and engineering of partial return yoke

Alan Bross | MICE Resource Loaded Schedule Review (RAL, May 7-8, 2013)

4

Slide5

Deliverables StepIV

:

Fiber Trackers

Alan Bross | MICE Resource Loaded Schedule Review (RAL, May 7-8, 2013)5

Slide6

Deliverables Step IV: LiH

Deliverables

Detector components (Complete)

Absorbers: LiH disks (complete) and wedgesIn process of establishing a CRADA with STFC which will allow us to ship the LiH to RAL (through Y12)Since 6Li enriched, considered nuclear material

Alan Bross | MICE Resource Loaded Schedule Review (RAL, May 7-8, 2013)

6

Slide7

Step IV Deliverables: SS

Alan Bross | MICE Resource Loaded Schedule Review (RAL, May 7-8, 2013)

7

Cryogenically the magnet now operates to spec

Approximately 3 W heat load (=original calc.)

Total cooling capacity

»

6.5 W

SS2 - Vetted

SS1 nearing completion

Ship

SS2 in July ‘13

SS1 in Sept. ‘13

Slide8

Step IV Deliverables: Magnetic shielding

Alan Bross | MICE Resource Loaded Schedule Review (RAL, May 7-8, 2013)

8

Analysis to determine if partial yoke can contain stray fields in the hall so that there are no effects on any equipment

YES

Engineering design of yoke

Conceptual design complete

Performance looks excellent

Full design work initiated

Shield sections: 100mm [4”] thick

Backing plates: 50mm [2”] thick

(front & back at vertical joint)

15” x 50

lb

/

ft

S-beams. Bolted into

floor, 100 mm away from wall

Floor template for pre-drilling holes

Slide9

Step IV

Deliverables: MICE 201 MHz Production Cavity Test

Production component system test

Fixturing

Integration/assembly

T

uner control testing

Vacuum and alignment

Alan Bross | MICE Resource Loaded Schedule Review (RAL, May 7-8, 2013)

9

Ports, supports

and tuners

Fall 2013

Slide10

Step IV Deliverable: Prototype Coupling Coil Magnet (

MuCool

)

The first Coupling Coil Magnets (CCM) is considered a prototype and will be used in the MuCool program, but will test MICE hardwareCold mass produced at Qi Huan Co (Beijing) & prepped at LBNLFirst complete, 3 more to be fabricated. All SC in handNew test facility (Solenoid Test Facility) completeORC and commissioning starting in 2 weeksCryostat fabrication at LBNLFinal assemblyAt Fermilab with Technical Division (detailed plan under development)

Alan Bross | MICE Resource Loaded Schedule Review (RAL, May 7-8, 2013)

10

Slide11

MICE RFCClite

Test in MTA

Alan Bross | MICE Resource Loaded Schedule Review (RAL, May 7-8, 2013)

11

Slide12

Step VI deliverables: MICE Coupling Coil Magnets with integrated RF (RFCC)

The MICE cooling channel requires two Coupling Coils

Plan to build 3 windings

2 Cryostats Four vacuum vesselsHold two RF cavities eachEight 201 MHz cavitiesComplete save for EPRF power couplers, tuners, etc.Alan Bross | MICE Resource Loaded Schedule Review (RAL, May 7-8, 2013)12

Slide13

Resource Loaded Schedule

Slide14

Major Milestones

Alan Bross | MICE Resource Loaded Schedule Review (RAL, May 7-8, 2013)

14

SS#2 Ready to Ship – July `13

CCM Prototype Tested

and ready to move to the

MuCool

Test Area (MTA)

for Testing with RF in the

RFCC_Lite

Configuration

– April `15

SS#1 Ready to Ship – Sept `13

RFCC#1 Ready to

Ship – Sept `16

RFCC#2 Ready to

Ship – Nov `17

US FY13 FY14 FY15 FY16 FY17 FY18

Does not include contingency

Slide15

Step IV: Spectrometer Solenoids

Alan Bross | MICE Resource Loaded Schedule Review (RAL, May 7-8, 2013)

15

Slide16

Step VI: RF

Alan Bross | MICE Resource Loaded Schedule Review (RAL, May 7-8, 2013)

16

Slide17

Step VI: RFCC

Alan Bross | MICE Resource Loaded Schedule Review (RAL, May 7-8, 2013)

17

RFCC-Lite

Slide18

Magnetic Mitigation

Alan Bross | MICE Resource Loaded Schedule Review (RAL, May 7-8, 2013)

18

Slide19

US Risk Register I

Alan Bross | MICE Resource Loaded Schedule Review (RAL, May 7-8, 2013)

19

Slide20

US Risk Register II

Alan Bross | MICE Resource Loaded Schedule Review (RAL, May 7-8, 2013)

20

Slide21

Now Add Contingency and Stretch

Alan Bross | MICE Resource Loaded Schedule Review (RAL, May 7-8, 2013)

21

13-05-02-MAP-WBS5-

Only.mpp

Almost achieves FY18

completion – BUT…

23,918 K$

17,716 K$

2

4,383 K$

Sums of then-FY K$

Slide22

Under These Assumptions…

Note: no approved NSF Funding for Ops &

Exp

beyond FY13DOE Operations & Experimental support still under developmentAlan Bross | MICE Resource Loaded Schedule Review (RAL, May 7-8, 2013)22

Slide23

Conclusions

We now have a complete RLS for the US-MICE construction project

Some more work to be done

Contingency and risk included and we have shown impact on MICE schedule given US funding constraintsUS carries majority of the technical riskWe will know much more in 4-5 monthsExpect both spectrometer solenoids to be completeTesting of first CCM cold mass completeBegin testing of MICE production cavity in MTAAlan Bross | MICE Resource Loaded Schedule Review (RAL, May 7-8, 2013)23