/
Status of the MICE RF System Status of the MICE RF System

Status of the MICE RF System - PowerPoint Presentation

trish-goza
trish-goza . @trish-goza
Follow
398 views
Uploaded On 2017-07-27

Status of the MICE RF System - PPT Presentation

K Ronald University of Strathclyde For the MICE RF team 1 MICE Project Board 17th April 2015 Content 2 Redesigned distribution network Change from STEP V design Used underfloor delivery T ID: 573541

2015 mice project system mice 2015 system project april board 17th cavity amplifier control test network llrf demonstration line

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "Status of the MICE RF System" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

Status of the MICE RF System

K Ronald, University of StrathclydeFor the MICE RF team

1

MICE Project Board, 17th April 2015Slide2

Content

2

Redesigned distribution network

Change from STEP V design

Used under-floor delivery

T

he demonstration experiment has simpler distribution requirements

Now makes sense to use ‘over air gap’ network

Status of RF drive systemPlans for test, delivery and installation of amplifiersDevelopment of LLRF controlsStatus of the LLRF resourcesMuon-RF phase determinationInitial tests with waveforms from MTA testsHardware now at Strathclyde for RF tests

MICE Project Board, 17th April 2015Slide3

MICE HPRF systems

3

MICE HPRF system requirements have changed

Fewer cavities, no coupling coil

Required operational date is Summer 2017

Enables demonstration of ionisation cooling with re-acceleration

Data campaign complete before end US fiscal year 2018

The MICE Demonstration of Ionisation Cooling requires

Two individual cavities bracketed by two thin LiH absorbers, sandwiching main absorberCavities themselves are unchangedEach cavity is 430mm long with a Q of 44,000 and is resonant at 201.25MHzThe cavities must still operate in a strong magnetic field environment

Cavities are estimated (by simulation) to deliver 8MV/m at 1MW dissipation- shunt impedance 5.9 M

W

A.

Bross

has reported on the ongoing tests at FNAL

MICE Project Board, 17th April 2015Slide4

MICE HPRF systems

4

The MICE Demonstration of Ionisation Cooling requires

Two

individual cavities bracketed by two thin

LiH

absorbers, sandwiching main

absorber

Cavities Technical DetailsEach cavity is 430mm long with a Q of 44,000 and is resonant at 201.25MHzThe cavities must still operate in a strong magnetic field environmentCavities are estimated (by simulation) to deliver 8MV/m at 1MW dissipation- shunt impedance 5.9 MW2MW peak output from RF drive amplifiers, also unchanged

LLRF requires ~10 % overhead to achieve regulation

Estimated ~10 % loss in transmission line

Power delivered to each cavity 1.62 MW,

Anticipated gradient in each cavity 10.3 MV/m

Slight uplift in gradient from 7.2 MV/m in each ‘STEP V’ cavity

MICE Project Board, 17th April 2015Slide5

RF network: STEP V/VI

5

MICE Project Board, 17th April 2015

Amplifiers installed behind shield wall

Triodes on main floor,

Tetrodes

on Mezzanine

Impact of B-fields negated by yokeLine installation planed before yoke support risersHigh power dynamic phase shifters removed 4 off 6 inch coax lines over wall

Pressurised to increase power handlin

g

Line lengths matched using 3D CAD

Manually adjustable line trimmers installed at

cavity to take up assembly errors in coax length

Flexible coax final feeds

Allows for small misalignments

10 hybrid splitters Split power for the opposed couplers of each cavity

Lines will be pressurised with 2Bar Nitrogen

Amplifiers behind Shield Wall

Distribution Network to MICESlide6

RF network: Demonstration experiment

6

MICE Project Board, 17th April 2015

Offcentre

mounting of hybrid allows neat take up of 90 degree phase

Orientation of load arbitrary- plan to align with the 6” distribution line and share mountings

Minimised length of 4” line- minimises breakdown and losses

Flexible coax

Line TrimmersHybrid Splitter

Directional

Coupler in

each line

4616 Pre Amplifier

TH116

Amplifier

500kW Load

Directional

Coupler 6 inchSlide7

RF network: Demonstration experiment

7

MICE Project Board, 17th April 2015

Propose

to have

1 load

on the hybrid splitter to each RF

cavity

absorbs unbalanced reflectionsCrane hook height fully retracted does not clash with the coax over the wall.Support for network will be from present ‘shield wall’ and from yoke supportsSlide8

RF network: Demonstration experiment

8

MICE Project Board, 17th April 2015

2

nd

TH116 amplifier moved to 3

rd

position behind wall to use the space

and ease installation in congested areaWith only 2 RF amplifiers now relatively straightforward to place auxiliary systems (cooling)Water cooling for load will need to route over the air gap on the transmission linesSlide9

RF network: Demonstration experiment

9

MICE Project Board, 17th April 2015

Offcentre

mounting of hybrid allows neat take up of 90 degree phase

Orientation of load arbitrary- plan to align with the 6” distribution line and share mountings

Minimised length of 4” line- minimises breakdown and lossesSlide10

RF network: Demonstration experiment

10

MICE Project Board, 17th April 2015

With slightly higher mounting of the RF network, work platform can be accommodated above channel

Such a platform can be useful for RF and other work

RF assemblies from hybrids to flexible lines can be prebuilt and craned in as components

Rapid assembly and servicing/accessSlide11

Implications for Power Distribution Network

11

The change to a two cavity system has some implications for the RF line loading

New experiment will demand higher power (1MW peak, 1kW average) in 4” lines under floor

Plan to implement SF

6

insulation

4” lines and components rated to 1.12MW peak in air at 1 bar (data from manufacturer/supplier)

Likely during full reflect during cavity fill we will have up to double the voltage on the line (eq. to 4MW)This will be mitigated by slow fillAlso mitigate with insulating gas

MICE Project Board, 17th April 2015Slide12

HPRF System Status

12

MICE RF systems demonstrated

N

ominal power levels 2MW, Frequency (201.25MHz) for 1ms @ 1Hz

First amplifier tested in MICE hall

Triode amplifier (output stage) remains installed

Tetrode and all modulator racks shipped to Daresbury

New higher voltage solid state crowbar testedElectrical completion of triode No. 2 will commenceTriode 2 will be tested using No. 1 tetrode and modulatorsWill use upgraded Triode No.1 modulatorEach major No. 1 subsystem will be swapped for No. 2 sequentiallyMake fault finding more rapidRemote control philosophy being developed

Will be tested during commissioning of No. 2 system

Dependent on electrical engineering resource availability

No 1 tetrode ready for re-commissioning at DL

July 2015, Triode No 2 tests with No 1 racks and tetrode

Design/Build Control Rack for No 1 racks- August 2015

Nov 2015, No 2 amplifiers tested with No 1 racks & controls

MICE Project Board, 17th April 2015Slide13

Cooling Demonstration: Preparation Programme

13

From STEP IV the project becomes increasingly focussed on RF systems

Relevant to define RF de-risking programme

First cavities expected May 2016

Opportunity to perform system shakedown

Cavity can be installed ‘upstream’ and parallel to

beamline

enclosureInstallation between ISIS run cyclesOpportunity to test vacuum pump down and clean and bake cavitySpecial transmission lines can be run from amplifier station no 1Shielding can be provided across hall near upstream SSTriode amplifier No 1 already installedRequire re-installation of entire RF amplifier chain

Aux racks, Modulator racks, SSPA, Tetrode amplifier

Require automation and control logic

Require LLRF system

Timing diagnostic: development of hardware

Tested on bench at Strathclyde

Test at MTA

MICE Project Board, 17th April 2015Slide14

Preparation Programme: Timeframes

14

Amplifier No 1 programme

Definition of controls and automation system/interfaces/interlocks

End April 2015- Draft documents under review

Amplifier no 1 automation system on PSU completion during 2015

Commission and test amplifier no 2 with automation & no 1 racks, Nov 2015

Re-Installation and test into loads at RAL with triode no 1, mid Aug 2016

Key resources, Electrical Engineering Effort 1 FTE EE, 0.5 FTE ED, 1 FTE ET, 0.5 FTE CE, 0.4 FTE MTControl and Monitoring programming: Pierrick

Hanlet

+ DL CE

RF & EE system specification/RF & EE system testing: T Stanley, C White, S Griffiths, S

Alsari

, K Ronald, CG Whyte, AR Young with consulting input from A Moss1-2 months of test operation through 2015, 2 months installation time. Team drawn from above list (minimum 2, ideally 3 required at any time)

MICE Project Board, 17th April 2015Slide15

Preparation Programme: Timeframes

15

Cavity No 1 programme

Arrival May 2016:

Assume the modules

are delivered assembled from LBNL

Test tuning and prepare for vacuum operation

Require clean room, may require tuning of couplers

Require exercising of the tuners2 weeks, RF (Ronald, Stanley, Whyte, Alsari) and mechanical techniciansPrepare for evacuation, pump, gauge installation: Vacuum engineer and mechanical technicians4 weeksInstall in upstream space beside beamline

(or next to shield wall)

, install X-ray shield

2 weeks

Evacuation, Baking, estimate 2 weeks (RF and Vacuum Engineering)

Install, tune overhead RF lines, 2 weeks concurrent with evacuation (RF, Mech. Technicians)

Retest of cavity tune after bake and evacuation, 1 week

Potential to be ready around July 2016

MICE Project Board, 17th April 2015Slide16

Preparation Programme: Timeframes

16

HPRF Tests, can start late August 2016, 4 weeks for each cavity

As soon as amplifier no. 1 is available

Requires modification of the controls system development

Hitherto one rack was planned to control two amplifiers

To facilitate tests would need to build discrete control racks for each system

Seems feasible given sufficient Electrical Engineering Resource through 2015-2016

Requires LLRF controlRequires RF staffing needs addressed urgently on the software sideSecond cavity can be commissioned partially in parallel and be ready for test as soon as 1st cavity completedBenefits

Full shakedown of RF system

Pre-prepped cavities by end 2016

MICE Project Board, 17th April 2015Slide17

HPRF System Controls

17

P

lans exist (in discussion) for the controls and monitoring interfaces required for the RF system and interfacing to other vital subsystems

Will allow expedited remote control and logging to be built as soon as effort is available

Each Cavity: 17 analogue inputs, 2 analogue outputs, 4 digital inputs (2 logic states)

Each RF system: 24 digital inputs (2 logic states), 4 digital inputs (3 states), 1 digital input (8+ logic states), 22 analogue inputs (12 are high, ~MHz, speed), 3 analogue inputs

Note many of these may be reasonably logically ‘

ANDed’ outside the control logic- simplifying the system and moderating cost and build time MICE Project Board, 17th April 2015Slide18

RF Control System

RF systems will require remote, automated control system

‘State Machine’ description being evolved by MICE Team

Headline list of primary states and required conditions below

18

MICE Project Board, 17th April 2015

OFF

No conditions

ENABLEDHardware keys insertedSTANDBY Heaters NominalHardware keysRF load coolant (

3)

RF

tube coolant

(5)

Compressed AirPSU coolantMains Quality

READY

PPS

RF

Permit

HT

enclosures shut Heaters NominalCavity and Vessel pressure NominalCavity coolant NominalCavity tuner pressuresSF6 pressureHardware keys

RF load coolant (3)

RF tube coolant

(5

)

Compressed Air

PSU coolant

Mains Quality

ONNominal RF waveforms Radiation & Arc sensorsPPS RF

Permit HT enclosures shut Heaters NominalCavity and Vessel pressure NominalCavity coolant Nominal

Cavity

tuner

pressures

SF

6

pressure

Hardware

keys

RF load coolant (3)

RF tube coolant

(5

)

Compressed Air

PSU coolant

Mains QualitySlide19

LLRF systems

MICE LLRF: provide 1% amplitude, 0.5

o phase regulation

Will control tuner system

LLRF system being developed by Daresbury LLRF group

Using digital LLRF4 boards already procured

First board operating at 201MHz in tests during August 2014

Synergy with ISIS requirements for LLRF system

For new ISIS LINAC amplifier test and commissioning standSimilar installation to the MICE amplifier test standSystem is closely related to the implementation for existing Daresbury accelerators0.1 % amplitude and 0.3o demonstrated in 1.3 GHz accelerating cavitiesPower ramp programming already demonstratedBoards will be tested during the amplifier commissioning programmeLLRF system no 1 resourcesCrate build up, A Moss and DL Electronics staff

Software: Expedite recruitment of experienced XILINX programmer: Synergistic with ASTEC/DL requirements:

Exploring use of software work at ISIS building on DL practice.

Completion of system No 1 by end 2015-

test at DL then RAL

19

MICE Project Board, 17th April 2015Slide20

Timing System, Desired Specification

We wish to know the difference between

Transit time of any of our

muons

(in essence through ToF1)

A zero crossing of the RF system in any cavity- choose the first cavity

Use

tracker measurement of trajectories to project forward to each cavity in

turnLLRF phase (0.5o) stability specification is ~3x stricter than the resolution desired for the RF timing system <20ps or <0.4% of the RF cycleIn turn specification for RF timing is ~3x stricter than ToF resolution 50ps ~1%Should mean the timing accuracy is ~1% of RF cycle, defined by ToFs resolutionStability, and/or accurate knowledge, of all parameters in the system will be important

Long cable runs, with dielectric insulated coaxial lines?

Phase relationship between the cavity fields and the signals on the test ports

Relationship between

ToF

signals and actual

Muon

transit

MICE Project Board, 17th April 2015

20Slide21

Overview of Timing Critical Elements

Sketch illustrates relationships of key components in the Demonstration experiment

Work in progress: Mathematical tests of digitiser interpolation

Test sensitivity to vertical resolution, temporal sample rate, noise

Work to be undertaken: Test TDC/Discriminators in 201.25 MHz environment

ToF

1

Cavity 1

RF Amp 1

LLRF

Beamline

HPRF

RF Drive

LLRF Feedback

TDC’s (

ToF

)

TDC’s (RF)

Digitisers

Datarecorders

RF

Clock

Trigger

Discriminators (RF)

Discriminators (

T

oF

)

ToF

Signals RG213

201.25 MHz LLRF MO

MO Signal (RG213)

Computers

RF Amp 2

HPRF

Cavity 2

RF Drive

Cavity 2 (RG213)

Cavity 1 (RG213)

MICE Project Board, 17th April 2015

21Slide22

‘Sub’

Nyquist digitisation

To acquire at Nyquist

on 200MHz would demand a sampling rate of ~1-2G.Sa/sec, for 1msDemands ~1 to 2MB per acquired channel, > 7.2GB/hr (assuming an 8 bit digitiser)400

m

s window presently being acquired at MTA- requires minutes of time to record traces

Fourier domain signal reconstruction

The Fourier transform of the

undersampled data maps the signal into its ‘unaliased’, relatively low frequency rangeWe may then retransform to the time domain to determine the time evolution of the signal at some arbitrary point in timeMust satisfy Nyquist on the linewidth- for our cavity natural linewidth is ~5kHz, effective linewidth is ~10kHz, so sampling rate ~few hundred k.Sa/sec should be sufficientWe assume 20M.Sa/sec, with 1ms we now have about 20kB per 8 bit recorded channel, data rate of ~72MB/hr per channel

MICE Project Board, 17th April 2015

22Slide23

Comparison of rebuilt 20M.Sa/sec subsampled oscilloscope signal with

5G.Sa/sec recording: LeCroy 625Zi

MICE Project Board, 17th April 2015

23

Visit to FNAL brought 100’s GB of data

Strathclyde has been processing these real traces using subsample Fourier domain reconstructionSlide24

T

iming hardware and Tests

Use TDC and discriminators used in ToF

system

TDC’s

CAEN V1290

25

ps

multi-hit25ps bin size maps to 7ps uncertainty (assuming Uniform PDF)LeCroy 4415A discriminatorsNeeds to be tested in RF environment (alternatives available)Use of same electronics as ToF mitigates systematic uncertainty & driftTDC hardware, discriminators and crates now assembled at Strathclyde.RF connection boards being fabricated to allow tests at RF frequenciesTo make efficient integration into DAQ ideally use VME digitisers for the sub-sample reconstructionAt present continue to use fast, 8 bit, DSO’s to capture signal

Plan to use CAEN V1761 digitisers

1GHz

, 4G.Sa/sec, 10 bit, 2 Channel

instrument

Capable of 57.6MS/Ch

24

MICE Project Board, 17th April 2015Slide25

Summary

25

MICE Project Board, 17th April 2015

Substantial redesign of distribution network

Mitigates installation conflicts (both schedule and potential physical)

Eliminates most of the 4” line

Control/Automation requirements defined in draft form

Needed to expedite control rack construction

Expedited construction of control rack No 1 can enable full system and conditioning in late 2016Will debug system ahead of operation in summer 2017LLRF staffing issue has emergedKey software expertise has left DaresburyRequire to address this urgently as also required to allow system test in late 2016

Possible solution based on development of DL system at ISIS

Fourier domain reconstruction progressing with REAL pick off data from MTA

Some variation in offset to understand

Hardware to test TDC approach largely assembled