Indoor Facility Informational Meeting Indoor Facility Informational Meeting

Indoor Facility Informational Meeting - PowerPoint Presentation

calandra-battersby
calandra-battersby . @calandra-battersby
Follow
408 views
Uploaded On 2016-07-22

Indoor Facility Informational Meeting - PPT Presentation

Feb 13 2014 Background The Club has been putting money aside for nearly 15 years for an opportunity such as this A year ago we approached the Quarry Church that purchased the old lumber yard property about using one of their pole barns Due to costs of what would be needed to bring the st ID: 414958

facility city lease costs city facility costs lease work space project mahler amp asbestos pay

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "Indoor Facility Informational Meeting" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

Indoor Facility Informational MeetingFeb 13, 2014Slide2

Background The Club has been putting money aside for nearly 15 years for an opportunity such as this…

A year ago, we approached the Quarry Church that purchased the old lumber yard property about using one of their pole barns. Due to costs of what would be needed to bring the structure to code we abandoned the idea in early fall of last year.Soon after, we contacted the City about the possible use of the old bowling alley that has been sitting empty for the past 7 years.Slide3

What have we done to date?On 11/25/13, the City Council voted to allow the city

staff to work with us to see if this project could be viable.The Club hired Mahler & Associates Architecture to assist with this project. They worked on the STMA facility and were recommended to us.

On Dec 12th we hired Vieau Associates, INC through Mahler to complete the required asbestos & regulated waste report for the building…basically testing for mold and asbestos.Report came back on Dec 20th with findings of mold and some asbestos in the mastic under the tile in the building and the carpet in the old restaurant area.Slide4

What have we done to date?

Our lead architectural engineer, Graeme Mahler put together a remediation plan for the asbestos and mold which we submitted to the City for approval.City approved our remediation plan on Monday Jan 27

th, 2014.Met with the city Jan 29th to go over initial language of the possible lease.Mahler & Associates were given the go-ahead to start writing the report to show how we will be meeting building codes and overall use plan of the building on Jan 30th.With positive feedback from the City Economic Development Authority (EDA), the club has purchased used artificial turf for the facility.Slide5

What is Next?

Once completed by Graeme, submit final work plan for approval from the City.Continue to work with the City on lease language.Get on the City Council agenda for Feb 24th

for them to vote on the lease. (10yr with opt out option for City at 5yrs)March 1st lease would start if approved by City.Immediately get the remediation work completed.Complete leases with sub-tenants After remediation, start demolition and construction.Will have soccer space completed and ready to go for Late Fall training.Slide6

Costs and ways to help pay…

We are estimating this project will cost approximately $60,000-$65,000 utilizing many hours of volunteers.We do expect to raise fees by $50 per competitive player and $5-10 per Rec player to help pay operating costs.Each Competitive team would get approximately 100 hours of time during the Winter months (Oct 01 – Mar 31)

Additional time at $25 per hour Will provide Rec players free training during the Winter months.We have one other local soccer club is very interested in renting space for Winter training.Other soccer clubs and other local sports clubs may also rent space.Slide7

Costs and ways to help pay…

Sub-tenants - rent could help off set costs:Possibility there to sub-lease the old bar and restaurant areas out.We have been working with someone on possibly leasing both the spaces out.

Could be rented out for birthday parties, etc.Businesses to donate $ or materials, also will be selling banner space in the facility.Slide8

Costs and ways to help pay…

Grants:We have been awarded a $2000 grant from MYSA to help pay for goals and futsal balls for the facilityWe have been awarded a $2000 grant in materials from the Home Depot along with 1 day’s worth of work from some Employees.

We are in the process of writing several other grant applicationsSlide9

Costs and ways to help pay…

Will be holding several fundraising eventsDairy Queen nightPizza Ranch

Dates TBDWe will also be selling t-shirts as a fundraiserDonations – we will setting up an online session (www.rivereagles.org) or by mailing a check to MSC PO Box 1214 Monticello MN 55362We are a 501C3 so all donations are tax deductible!Slide10

How can you help?

Time!! we need:ElectriciansCarpet Layers – carpet and the turfSheet Rock experience (hanging, taping, mudding)

HVACPlumbers to check out bathrooms, etc.Insulation expertsGeneral construction, framingAnyone with a Boiler license?Many, many hours of volunteers for demolition, painting, etc.If we get on the City Council Meeting on Monday Feb 24th

at 7pm, show up and show support for them to approve the lease.Slide11
Slide12
Slide13
Slide14

PicturesSlide15

PicturesSlide16

After we are done… (concept)

155

92

TV’sSlide17

After we are done…cont

Facility will have seating areas with Cable TVs & Wi-Fi

Vending machines on siteWill need volunteers to:Be attendantsClean facility

Turf brushing, maintenance

Snow removal/grass cutting

Probable that we will have to hire a few people to do some of these things.

Other uses – Referee training, Board meetings, storageSlide18

Questions?