/
Resources Management Resources Management

Resources Management - PowerPoint Presentation

calandra-battersby
calandra-battersby . @calandra-battersby
Follow
384 views
Uploaded On 2017-10-29

Resources Management - PPT Presentation

Dr Ahmed Elyamany Outline Definition of Resources Resource AggregationLoading Problems Associated with Resource Resource Leveling Resource Scheduling What a resource Any thing that is used by an activity to get the work done such as Material Equipment Labor Money ID: 600665

resources resource scheduling leveling resource resources leveling scheduling activities activity usage time units project period duration constrained smoothing week

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "Resources Management" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

Resources Management

Dr. Ahmed ElyamanySlide2

OutlineDefinition of ResourcesResource Aggregation/LoadingProblems Associated with ResourceResource LevelingResource SchedulingSlide3

What a resource?Any thing that is used by an activity to get the work done, such as: Material, Equipment, Labor, Money, …..Slide4

Resources ClassificationResources can be:Consumable (Money, Material,……)Non Consumable (Labor, Equipment,…)Resources can be:Key or constrained resources

(Skilled labor, Equipment,……)

Secondary or

non-constrained

resources (Labor, …)

General resources, used by all activitiesSlide5

Duration-Driven ScheduleAll CPM scheduling techniques are duration driven schedulesBasic units: activities, durations, relationshipsAssumes resources are available whenever neededDifference between:Working datesCalendar datesSlide6

Optimum Resource UsageNeed of resource is fixed along the project construction timeImpossible to achieve because of activities overlapWork volume = Area = resource units x timeResource demandResource availableSlide7

Resource HistogramGraphically represents resource needsRelation between resource units and timeProcedure:Draw the networkDraw the bar chartDetermine the points where activities start and/or finish.Slide8

Preferred Resource UsageSlide9

Resource Aggregation/LoadingThe summation, on a period-by-period basis, of the resources required to complete all activities based on the schedule carried out in the previous stageThe results are usually shown graphically as a histogramA separate graph will be required for each resourceSlide10

Resource Aggregation/LoadingConsider the following activitiesResource limit = 10 units /weekActivity

Duration (week)

Resources (units/week)

A

B

C

D

E

2

3

2

5

2

Shown in the histogramSlide11

Resource Aggregation/LoadingResource LimitSlide12

Problems Associated with ResourceResource Fluctuation (Resource leveling)Resource Over allocation (Resource Scheduling)

High hiring and firing

Less hiring and firingSlide13

Resource Leveling (Smoothing)Unconstrained resource scheduling (Constrained time)Resource LevelingResource unconstrained (No limits on resources)Time (Project completion) constrained; project duration not be delayedReduce the difference between the peaks and the valleysAverage resource usageThe objective is to smooth the use of the resources to avoid the resource fluctuationSlide14

Resource Leveling (Smoothing)Slide15

Resource Leveling (Smoothing)Slide16

Resource Leveling (Smoothing)Heuristic Method ProcedurePrepare a complete activity scheduleDraw a bar chart based on ES timingsDraw the FF as dashed line beside the upper side of the bar and the TF beside the lower sidePut the resource usage in each bar of the related activity

Critical activities to be drawn first (do not move them)

Aggregate the resources in each time periodSlide17

Resource Leveling (Smoothing)Heuristic Method ProcedureCalculate the total usage of resources = Σ unit period usageCalculate the average resource usage = Σ usage / utilization periodShift non-critical activities within their FF first, then their TF to decrease the peaks and raise the valleys

Revise the activities float

Aggregate the resources in each time periodSlide18

Resource Leveling (Example)ActivityActivity Duration (Weeks)

Predecessors

Resource

(units/week)

A

B

C

D

E

F

G

H

I

J

K

L

M

N

0

2

5

3

2

6

6

6

4

2

7

3

2

2

-

1

1

1

2

2

3

4

4

5, 6

6, 7

2, 8

2, 8, 9

10, 11, 12, 13

0

0

2

2

1

2

3

1

0

4

2

2

4

0Slide19

Resource Leveling (Example)Slide20

Resource Leveling (Example)ActivityESEF

FF

TF

A

B

C

D

E

F

G

H

I

J

K

L

M

N

0

0

0

0

2

2

5

3

3

8

11

9

9

18

0

2

5

3

4

8

11

9

7

10

18

12

11

20

0

0

0

0

4

0

0

0

2

8

0

6

7

0

0

3

0

6

12

3

0

6

9

8

0

6

7

0Slide21

Resource Leveling (Example)Slide22

Resource Leveling (Example)Slide23

Resource Leveling (Example)Slide24

Resource Leveling (Example)Slide25

Resource Leveling (Example)Slide26

Resource SchedulingConstrained resource scheduling (Unconstrained time)Resource SchedulingConstrained ResourcesUnconstrained project completion; project time may be delayedReduce the resource usage to be less than the resource availabilityThe objective is to meet the resources limitsSlide27

Resource SchedulingSlide28

Resource SchedulingIs there is a way to prioritize activities That compete for the limited resourcesso that the net project delay isminimized?Slide29

Resource SchedulingResource Scheduling Rules of ThumbMany rules have been experimented withLeast TF were found to be most effectiveLeast LS has the same effect as the least TF and doesn’t require network recalculationsIn case of a tie use least TFSlide30

Resource SchedulingProcedurePrepare a complete activity scheduleAggregate the daily resource demandIf demand greater than available then determine activities compete for resourcesPrioritize these activities based on their LSAllocate resources to some activities and delay the others

Put your solution in table formatSlide31

Resource Scheduling (Example)Activity

Duration (Weeks)

Predecessors

Resource (units/week)

R1≤8

R2≤1

A

B

C

D

E

F

G

H

I

J

K

6

4

2

8

4

10

16

8

6

6

10

-

-

-

A

D

B

B

F

E, H

C

G, J

3

6

4

0

4

0

4

2

4

5

2

0

1

0

1

1

1

0

0

1

1

0Slide32

Resource Scheduling (Example)Slide33

Resource Scheduling (Example)Slide34

Resource Scheduling (Example)Slide35

QuestionsContact:Dr. Ahmed Elyamany019-4100-824

a2hyamany@yahoo.com