/
TECHNIQUES SANJAY KHARE 	Sr. TECHNIQUES SANJAY KHARE 	Sr.

TECHNIQUES SANJAY KHARE Sr. - PowerPoint Presentation

chipaudi
chipaudi . @chipaudi
Follow
342 views
Uploaded On 2020-06-19

TECHNIQUES SANJAY KHARE Sr. - PPT Presentation

Prof Works IRICEN Pune Budget Overrun 1400 Schedule overrun 350 SOH may be failure in term of Project management but successful as a human creation Symbol of Australia Over Budget by 1900 ID: 782030

activity project schedule start project activity start schedule activities finish work scheduling time cont

Share:

Link:

Embed:

Download Presentation from below link

Download The PPT/PDF document "TECHNIQUES SANJAY KHARE Sr." is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

TECHNIQUES

SANJAY KHARE

Sr.

Prof.

(Works)

IRICEN, Pune

Slide2

Budget Overrun- 1400%, Schedule overrun- 350%

SOH may be failure in term of Project management,

but successful as a human creation.

Symbol of Australia

Slide3

Over Budget by 1900%.

Project was deliberately underestimated

SUEZ CANAL constructed in 1880

NOT for PROFIT MEGA PROJECT”

Slide4

Some Indian Project

Delay

(in Months)

Coast of

Delay

( Cr./

yr

)Production Loss(in Cr.)

Bokaro Steel Plant 72

51.72

3018.75

Gujrat Refinery1227.99438Idukki Hydel Project4811.95

Delays in Project and their effects

Slide5

What is a project?

A unique undertaking composed of interrelated activities

which has a

precise goal

,

well defined beginning and end

, often involving staff from

cross-functional groups, that operates under specific constraints of resources, schedules, and requirements

Slide6

Organization of resources into activities

Implementation of the activities in a logical sequence

WHAT ARE RESOURCES ?

Materials

Equipment

Technology

People

Time

Money

What is a project?

Slide7

Project and Program

A project is a one-time effort that produces a specific result, for example, a building .

This is in contrast to a

program

, which is

an ongoing process, such as

a quality control program, or

an activity to manage a series of multiple projects together.

Slide8

LIFE CYCLE OF A PROJECT

Seven Phases

Concept and Feasibility Studies

Preliminary Engineering and Design

Detailed Engineering and Design

Procurement

Construction

Start-up and Implementation

Operation or Utilization

Slide9

VARIOUS STAGES OF PROJECT

THINKINGPLANNING & SCHEDULING

DATA COLLECTION

STATUS UPDATE through NETWORK & EARLY WARNING

EXECUTION

TESTING

MAINTENANCE

Slide10

Identification of work

Chargeable to

Revenue

(Demand No. 4/7/11/

9

)

Chargeable to

Capital

(Demand No.-16)

Life Cycle of Railway Project (Govt. Funding)

Field survey & conceptual drawings

conceptual drawings and Justification

RECT/PECT

Proposal for sanction

Abstract Estimate

Approval

Sanction

IRPSM

Slide11

Chargeable to

Revenue

Chargeable to

Capital

Preparation of Estimate and Sanction

Detail Estimate

FLS

Contract

Planning for execution

Departmental

Store procurement

TENDERs

Contract Management & Execution

Commissioning

Life Cycle of Railway Project (Govt. Funding)

Slide12

Lifecycle of Railway Infra

Projects

(through

E

xternal Funding)

Feasibility

Study & DPR

Preparation

Project

Contracting

Asset operation

& maintenance

Project

Construction

Project

Financing

Railway

Infrastructure

Project Lifecycle

Project Identification

As-is assessment of railway connectivity

Traffic movement through competitive mode such as road

Structuring &

Procurement

Feasibility Study & DPR Preparation

Current and Future Traffic Assessment

Economic Analysis

Detailed

Project Assessment

Technical Assessment

Financial Assessment

Contracting

Contract Packaging

Defining obligations of contracting parties

Payment mechanisms

Financing

Debt Financing from Multilaterals, Financial Institutions and Banks

Equity Financing from stakeholders

Execution

Project Management

Project Governance

Contract Management

O&M

Asset optimization

Financial Management

Compliance reporting

Project

I

dentification

Structuring & Procurement

Structuring

- Risk Assessment, Financial Risk analysis, Risk allocation and sharing

Procurement

Procurement Strategy, Procurement delivery

Slide13

INTEREST GROUPS

Owner

(Employer) wants to achieve best value for their investment

Contractors

desire to bid low enough to win but high enough to realize profit on investment

Workers

hope to achieve better living standards and working conditions

 

Slide14

What is a project manager?

The role responsible for leading and coordinating the project effort from inception to its successful completion; the person

responsible for making things happen

Slide15

What is project management?

A set of skills and methods of planning, organizing, and managing a project from inception to its successful completion

Completion of Project on time within Budget without comprising Quality

Slide16

WHY PROJECT MANAGEMENT

To define the project and agree with the customer

To handle projects effectively in an organization.

To plan and assess resource needs for the project

To estimate project cost and make proposals

To plan & schedule activities in a project

To allocate the right resource at the right time

To assess risk and failure points and make backup plans

To lead a project team effectively and communicate well among team members.

Slide17

Project Management Plan

“Tells How work will be done”The key to a successful project is on the planning.All the detailed planning work for different aspects of the project is integrated into one single plan known as the

Project Management Plan

Slide18

Planning & Scheduling

Planning is an art and science of converting a set of objectives to realization

through a series of steps executed in an

organized and predicted way

so that there will be less requirement of changes in the plan later on.

The old saying

“Plan the work, Work the plan”

Slide19

Fundamentals

Scheduling

Philosophy

Scheduling Terms and

Definitions

Types

of

Schedules

Relationships

Resources

Slide20

Scheduling Philosophy

Why do you

schedule?

What do you

schedule?

When do you

schedule?

Slide21

Scheduling Philosophy (cont’d)

Why do you schedule?

Provides a tool for breaking work into manageable chunks

Provides a tool for measuring progress

Monitor and measure progress against goals

Provides a commitment about when things will be done

Encourage everyone on the project to see their efforts as part of a whole

Satisfy customer or contractual requirements

A schedule is a formalized method of managing time and resources

Slide22

What do you schedule?

Milestones

Activities required by contract or customer

Activities

critical

to the performance of the project

Changes to the original plan

A simple schedule that is used is far more valuable than the most detailed schedule created to satisfy a contractual requirement!

Scheduling Philosophy (cont’d)

Slide23

When do you schedule?

Prior to, or at the beginning of a project. This schedule is referred to as the

“baseline”

At periodic intervals during the project. This is commonly referred to

“updating”

If there are changes in the scope of the project

If the project is substantially behind or ahead of the baseline

Scheduling Philosophy (cont’d)

Slide24

Scheduling

Terms and Definitions

Common scheduling terms :

Project

Activity (Schedule or Task)

Duration

Relationship

Bar Chart (Gantt)

Lag

Critical Path

Milestone

Float

Work breakdown Structure (WBS)

Resource

Slide25

Project

A project is finite, it has a specific beginning and endpoints

A project contains resources, typically time, money and people

A project is measurable

Scheduling Terms and Definitions (cont’d)

Slide26

Activity (Schedule or Task)

The activity is the basic building block of a schedule

An activity defines a measurable quantity of work

Activity-on-node (AON)

Nodes represent activities, and arrows show precedence relationships

Activity-on-arrow (AOA)

Arrows represent activities and nodes are events for points in time

Scheduling Terms and Definitions (cont’d)

Slide27

Activity On Arrows

3

2

0

1

3

1

1

1

1

2

4

6

7

3

5

Lay foundation

Design house and obtain financing

Order and receive materials

Dummy

Finish work

Select carpet

Select paint

Build house

1

3

2

2

4

3

3

1

5

1

6

1

7

1

Start

Design house and obtain financing

Order and receive materials

Select paint

Select carpet

Lay foundations

Build house

Finish work

Activity On Nodes

Slide28

Duration

Measurable unit to perform an activity

Typically, durations are in work hours or work days

Relationship

The interdependency of one activity to another.

Predecessors and successors

Predecessor

is a task whose completion (wholly or partly) determines the start of the successor

Successor

is a task which is dependent on the completion (wholly or partly) of the predecessor.

Scheduling Terms and Definitions (cont’d)

Slide29

Bar Chart (Gantt)

Graphical representation of a group of activities making up a project, represented by bars along the horizontal time axis. Shows duration and planned sequence of activities

Lag

The time associated in the relationship between two activities.

For example, stripping forms can not be completed until 10 days after concrete is placed. In this case, there is a

10 day lag

between the activities

Scheduling Terms and Definitions (cont’d)

Slide30

Critical Path

The path or

paths

which are the series of activities

having zero float

and must be completed on their scheduled dates or the project is in jeopardy

Milestone

A point in time that signifies

either the beginning

or

the end of a series of related activities. A milestone has

zero duration

Scheduling Terms and Definitions (cont’d)

Slide31

Float

A measure of leeway in activity performance.

Typical float types are

“free float”

and

“total float”

Free float is the amount of time that an activity’s

start can be delayed without affecting

the early start of

successor

activities

Total float is the

amount of time in starting or finishing

an activity that

will not affect the completion

of the project

Scheduling Terms and Definitions (cont’d)

Slide32

Work Breakdown Structure (WBS)

Framework for organizing activities that make up a project

A method of breaking down a project into individual elements (components and tasks) in a hierarchical structure to be executed by the project team to create required deliverables

Process of subdividing project deliverables and project work into more manageable components.

It groups tasks facilitating resource allocation, assignment of responsibilities and measurement and control of the project.

Structure of WBS and level (/duration) of activities depends on the Reporting requirements for the project.

It is developed before identification of dependencies and estimation of activity durations.

It is a foundation of project planning.

Scheduling Terms and Definitions (cont’d)

Slide33

Resource

Anything needed to complete an activity: Labor, Materials, Equipment, Design, etc.

Scheduling Terms and Definitions (cont’d)

Slide34

Types of Schedules

Written Schedule

Bar or Gantt

Charts

CPM

Schedules (Critical Path

Method)

PERT

Time

Scale Arrow Diagram

Slide35

Bar

or Gantt Chart :

Graphical presentation of the schedule

Lists

activities and

durations

May show

logic

Used for small

projectsThe bar chart was originally developed by Henry L. Gantt in 1917 and is alternatively called a Gantt chart

Types of

Schedules (Contd..)

Slide36

Program Evaluation & Review Technique (PERT):

Graphic view that allows for easy evaluation of the flow of a project

developed during 1958. The technique was developed and used in conjunction with the planning and designing of the Polaris missile project.

Types of

Schedules (Contd..)

Critical Path Method (CPM):

which was developed by DuPont Company and applied first to the construction projects in the chemical industry

Slide37

Time Scale Arrow Diagram :

Is a combination of bar chart and normal network.

Activities are represented by horizontal lines on time scale.

Also shows interdependencies between activities.

It facilitates better assimilation of overall project- easy to mark progress, compare actual progress to schedule progress.

Useful for effective resource allocation technique- for leveling of resource utilisation shifting of certain activities.

Types of

Schedules (Contd..)

Slide38

Slide39

Relationships

Relationships are the interdependencies between one activity and another or group of activities

The four types of relationships are:

Finish-to-Start

Start-to-Start

Finish-to-Finish

Start-to-Finish

Slide40

Relationships (cont’d)

Finish-to-Start

The most common type of scheduling activity relationship. Simply stated, the start of the next activity is dependent upon the completion of the previous activity

For example, on a construction project you can’t pour the concrete until the reinforcing steel is in place

Start-to-Start

Start-to-Start relationship implies that an activity can start once another specified activity has started

For example, Concealed plumbing work and concealed wiring work can start together.

Slide41

Finish-to finish

Finish-to-Finish relationship implies that the completion of an activity is dependent upon the completion of another activity. This relation ship is

commonly used with start-to-start relationships.

For example,

Color

wash and electrical switch fixing need to be completed together.

Relationships (cont’d)

Slide42

Task Dependency

Description

Relationship Diagram

Finish to Start

The finish of the predecessor determines the start of the successor

Finish to Finish

The finish of the predecessor determines the finish of the successor

Start to Start

The Start of the predecessor determines the Start of the successor (e.g. Plastering)

Start to Finish

The Start of the predecessor determines the Finish of the successor

(e.g. Dewatering )

A

B

A

B

A

B

A

B

Relationships (cont’d)

Slide43

Resources

All projects consume resources!

Resources are not just people:

Resources can include money, material, equipment, and more.

How well these resources are allocated and monitored is a key measure of any project’s success or failure

Slide44

Steps in Creating a Project Schedule

Activity De

f

init

i

o

n

Activity

Sequ

e

ncing

Estimating Activity DurationSchedule DevelopmentSchedule Control

Slide45

Developing a Project Schedule

Activity Definition

An activity must have a

definable start and end

An activity is used to develop a plan for completing a project that sequences and schedules each activity

An activity is quantifiable and measurable

Activities shall relate to the WBS and allow for ease in quantifying and reporting

Slide46

Sample WBS for Construction Project

Slide47

Typical WBS

Slide48

Logic and relationships

Use conventional Finish-to-Start logic to develop relationships. This is the first pass at developing a schedule.

As you refine the schedule you will incorporate Start-to-Start and Finish-to-Finish relationships.

Calendars

Is the project going to be scheduled in hours or days?

Will there be work activities that are outside the normal work periods of the project?

Will the project include week-ends and holidays?

Developing a Project Schedule (Cont’d)

Slide49

Developing a Project Schedule (Cont’d)

Durations

Does the duration of each activity seem practical and achievable?

Nature of the task

critical

to the project or fill-in work?

Durations should be no less than 2-3 days nor longer than 15 days

Resources

What resources should be incorporated?

Tie resources to the level of the activities

A good place to begin assigning resources is from the budget or cost estimate

Slide50

Baselining the Plan

Original Plan =

Baseline

Baseline

vs. Current

Schedule

Changes

to

BaselinePerformance MeasurementEarned Value

Slide51

Updating / Progressing

Percent

Complete

Time

Budget

Physical

Remaining

Duration

Remaining

Work

Slide52

Outputs From Progressing

“Schedule updates”

“Corrective action”

“Lessons learned”

Slide53

Change Control Management

A famous General once said “

To win the war, you must know the enemy.

A famous Project Manager once said

“We have met the enemy and the enemy is change.”

Manage change, or it will manage you!!!

C

H

ANG

E

Slide54

Slide55

Project Managements…..

Project cost ManagementProject Quality Management Project human resource managementProject communication management

Project Risk Management

Project Change Management

Slide56

THANKS…..