D Lynn BNL LBNL Mechanical Meeting Sep 2012 1 US Stave Fabrication Sequence Differs mostly from UK sequence in that we premachine foam and make foampipe assembly Do we need identical standardized assembly of stave core in production ID: 278977

core stave assembly foam stave core foam assembly facing sequence ships chart lbnl bnl cores production glues bnlbnl expect day facings split

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "US Stave Core Production" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

US Stave Core Production

D. Lynn (BNL), LBNL Mechanical Meeting, Sep 2012

1Slide2

US Stave Fabrication Sequence

Differs mostly from UK sequence in that we pre-machine foam and make foam-pipe assembly

Do we need identical standardized assembly of stave core in production?

UK Foam Split

US Foam Split

2Slide3

LBNL fabricates facings (either standard or co-cured). Ships to BNL

BNL glues CF tubes, foam-pipe assembly, honeycomb to first facing, and end closeouts . Ships to Yale

Yale grinds honeycomb. Ships to BNL

BNL glues last facing Characterization (or QA) at BNL

Assembly Sequence and Institutions for US Stave Cores Built Up to Now

Expect facings will continue to be fabricated at LBNL

All of the other steps could in principle be done at any of these institutions

E.g. at present we do grinding at Yale as they have access to own grinder, but at BNL our central machine shops can do it (for prototyping, they are way too expensive!)

Is it possible to skip grinding in future? (or perhaps use corrugated core??)

3Slide4

Old Gantt Chart (2009) for Stave Core Assembly—I have not updated it

4Slide5

Old Gantt Chart (2009) for Stave Core Assembly—I have not updated it

Chart implied ~ 3 weeks assembly and QA (not including facing fabrication).

Expect to maintain a throughput of 1/day (although maybe could do 2/day without much additional effort?).

Seems likely need at most two main centers of production (US and UK).

Where in US to make stave cores will require a comprehensive look at where hybrids, modules, stave cores, and final module mounting and stave testing will be done to maximize utilization of resources within US community – also will depend upon funding.