PROGRESS REPORT OF NATIONAL RURBAN MISSION UNDER HANDLOOM AND TEXTILE PROGRESS REPORT OF NATIONAL RURBAN MISSION UNDER HANDLOOM AND TEXTILE

PROGRESS REPORT OF NATIONAL RURBAN MISSION UNDER HANDLOOM AND TEXTILE - PowerPoint Presentation

delcy
delcy . @delcy
Follow
27 views
Uploaded On 2024-02-02

PROGRESS REPORT OF NATIONAL RURBAN MISSION UNDER HANDLOOM AND TEXTILE - PPT Presentation

DIPHU CLUSTER SL NO NAME OF SCHEME ESTIMATED AMOUNT     in lakhs FUND RECEIVE  in lakhs FUND RELEASE in WORK PROGRESS          in  GEOTAGGING 1 CONSTRUCTION OF CFC BUILDING AT LONGNIT VDC OFFICE COMPLEX SINGHASON MAC ID: 1043946

mac construction nomati building construction mac building nomati support weavers dengaon level beam cfc office lakhs fund center marketing

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "PROGRESS REPORT OF NATIONAL RURBAN MISSI..." is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

1. PROGRESS REPORT OF NATIONAL RURBAN MISSION UNDER HANDLOOM AND TEXTILE DIPHU CLUSTER SL. NO.NAME OF SCHEMEESTIMATED AMOUNT    (in lakhs)FUND RECEIVE  (in lakhs)FUND RELEASE (in %)WORK PROGRESS          (in %) GEOTAGGING1.CONSTRUCTION OF CFC BUILDING AT LONGNIT VDC OFFICE COMPLEX, SINGHASON MAC.36.5018.0022.3350 % (POST PALTE BEAM LEVEL)DONE.2.CONSTRUCTION OF WEAVERS SUPPORT BUILDING AT VDC OFFICE COMPLEX, LONGNIT, SINGHASON MAC.26.0013.0031.3550 % (POST PALTE BEAM LEVEL)DONE.3.CONSTRUCTION OF MARKETING CENTER AT MANJA, DHANSIRI MAC.13.006.7528.3040 % (LINTEL BEAM LEVEL)DONE.4Nos. of beneficiaries to be benefited 100 Nos.

2. 1. CONSTRUCTION OF CFC BUILDING AT LONGNIT VDC OFFICE COMPLEX, SINGHASON MAC.       

3. 2. CONSTRUCTION OF WEAVERS SUPPORT BUILDING AT VDC OFFICE COMPLEX, LONGNIT, SINGHASON MAC.

4. 3. CONSTRUCTION OF MARKETING CENTER AT MANJA, DHANSIRI MAC.

5. PHULONI CLUSTERSL. NO.NAME OF SCHEMEESTIMATED AMOUNT    (in lakhs)FUND RECEIVED  (in lakhs)FUND RELEASED       (in %)WORK PROGRESS GEOTAGGING1.CONSTRUCTION OF CFC BUILDING AT DENGAON, NOMATI MAC.36.5018.0019.2040% (LINTEL BEAM LEVEL)DONE.2.CONSTRUCTION OF WEAVERS SUPPORT BUILDING AT DENGAON, NOMATI MAC.26.0013.0019.2515 % (TIE-BEAM LEVEL)DONE.3.CONSTRUCTION OF MARKETING CENTER AT DENGAON LAMPS CENTRE, NOMATI MAC.13.006.7519.2525 % (WINDOW SIL LEVEL)DONE.4.CONSTRUCTION OF WEAVERS SUPPORT BUILDING AT TEKE RONGPI GAON, MAHAMAYA MAC.26.0013.0038.50100 % (COMPLETED)DONE.5Nos. of beneficiaries to be benefited 150 Nos.

6. 1. CONSTRUCTION OF CFC BUILDING AT DENGAON, NOMATI MAC.

7. 2. CONSTRUCTION OF WEAVERS SUPPORT BUILDING AT DENGAON, NOMATI MAC.

8. 3. CONSTRUCTION OF MARKETING CENTER AT DENGAON LAMPS CENTRE, NOMATI MAC.

9. 4. CONSTRUCTION OF WEAVERS SUPPORT BUILDING AT TEKE RONGPI GAON, MAHAMAYA MAC.