/
Operations Working Group Operations Working Group

Operations Working Group - PowerPoint Presentation

jezebelfox
jezebelfox . @jezebelfox
Follow
343 views
Uploaded On 2020-08-03

Operations Working Group - PPT Presentation

Chair Rickey Floyd ViceChair Shawn McCreary 03072019 NPRR 849 Clarification of the range of Voltage Set Points at a Generation Resources Point of Interconnection POI This Nodal Protocol Revision Request NPRR clarifies the range of voltages at the Point of Interconnection POI and c ID: 796553

ercot owg chair working owg ercot working chair voltage system ras nodal reactive capability limits voltages transmission action group

Share:

Link:

Embed:

Download Presentation from below link

Download The PPT/PDF document "Operations Working Group" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

Operations Working Group

Chair-

Rickey Floyd

Vice-Chair- Shawn McCreary

03/07/2019

Slide2

NPRR 849, Clarification of the range of Voltage Set Points at a Generation Resources' Point of Interconnection (POI)

This Nodal Protocol Revision Request (NPRR) clarifies the range of voltages at the Point of Interconnection (POI) and circumstances for which a Generation Resource’s reactive capability must be designed to meet and clarifies the ability of ERCOT and the TSP or its designated agent (e.g. Transmission Operator (TO)) to issue an instruction for any available reactive capability at voltages outside of the reactive capability requirements.

This item is still being discussed and will remain at OWG.

OWG is working on the objectives directed by ROS at their last meeting.

Slide3

NOGRR183, Remedial Action Scheme (RAS) Submittal and Review Requirements

This Nodal Operating Guide Revision Request (NOGRR) aligns the Nodal Operating Guides with North American Electric Reliability Corporation (NERC) Reliability Standard PRC-012-2 - Remedial Action Schemes.

Documentation describing the system performance resulting from the possible inadvertent operation of the RAS or failure to operate. RAS inadvertent operation or failure to operate must satisfy all of the following:

a. The ERCOT System shall remain stable;

b. Cascading shall not occur;

c. Applicable Transmission Facility Ratings shall not be exceeded;

d. ERCOT System voltages shall be within post-contingency voltage limits and post-contingency voltage deviation limits as established by ERCOT; and

e. Transient voltage responses shall be within acceptable limits as established by ERCOT.

OWG took no action and will discuss NOGRR183 in

March

(

03/21/19

).

Slide4

Outage Coordination Working Group

Minor edits

are being submitted to ROS for considerations to the Operations Working Group (OWG)

Scope

Annually develop

list

of High Impact Transmission Elements (“HITEs”) as discussed in ERCOT’s HITE methodology document. The OWG chair may

designate

a subgroup chair to facilitate this

activity.

It is recommended that OCWG be combined with OWG.