All Experimenters’ Meeting All Experimenters’ Meeting

All Experimenters’ Meeting - PowerPoint Presentation

karlyn-bohler
karlyn-bohler . @karlyn-bohler
Follow
409 views
Uploaded On 2016-04-10

All Experimenters’ Meeting - PPT Presentation

November 03 2014 Photo by Greg Vogel Accelerator Operation Summary Calendar Week 44 NuMI Weekly Integrated Intensity 5 60 E18 protons Beam Hours To NuMI ID: 278146

work hours october power hours work power october intensity test wilson 2014 west beam hall november center week saturday

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "All Experimenters’ Meeting" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

All Experimenters’ Meeting

November 03, 2014

Photo by Greg VogelSlide2
Slide3

Accelerator Operation Summary

Calendar Week # 44NuMI Weekly Integrated Intensity

5

.60

E18

protons Beam Hours To NuMI 147.2 hours

From :

October

27,

2014 (0000 hours)

To:

Nov

ember 03,

2014 (0000 hours)Slide4

Accelerator Operation Summary

Calendar Week # 44NuMI Weekly Integrated Intensity

7.95 E18

protons

Beam Hours To NuMI 145.4 hours BNB Weekly Integrated Intensity 5.76 E18 protons

Beam Hours To BNB

155.3 hours NMuon Weekly Integrated Intensity 3.49 E16 protonsBeam Hours To NMuon 130.6 hoursMTest Weekly Integrated Intensity 5.71 E14 protonsBeam Hours To MTest 105.8 hours

From :

October

27,

2014 (0000 hours)

To:

Nov

ember 03,

2014 (0000 hours)Slide5
Slide6
Slide7
Slide8
Slide9

AccessThursday – 8/21/14Beam off at 0600Keys available at 0700Install Refurbished Booster RF Cavity

Keys back at 1500Other jobs that fit during cavity changeBeam by beginning of evening shiftSlide10

Fall Shutdown Intensity Reduction PlanBegins Saturday, August 30

th @ 0800Main Injector will run $23 events instead of $2A events to NuMI (~80 KW reduction)Linac and Booster will meet program needsBNB should be unaffectedSeaQuest will go down from 4 turns to 3 turns.Beam off Friday, September 5th @ 0800Slide11

2014 ShutdownSix full weeks into the shutdownLinac and Booster Operational

Main Injector/Recycler startup todaySlide12

2014 ShutdownNuMI WorkBeryllium vacuum window leak

Replace windowHorn Stripline maintenanceWork complete by Monday, October 27th Switchyard WorkF1-F3 Vacuum recoveryOnce 46B work is doneImpact MI for ~3 hoursFeeder 43 maintenanceScheduled for Saturday, October 25

th

G1 Stub Magnet Installation

Magnet installed Leak check and final workFeeder 46B workPrevents daytime operation of switchyardExpected to be complete by end of weekVarious Safety System TestsMeson Center WorkMC6D-3Slide13

Complex StatusNuMI

Started upPerformed ScansLow intensity run until this morningIncreased intensity until tomorrowSwitchyardSigned off - October 31

st

Beam to Switchyard Absorber

SeaQuest

Working on target issuesMeson TestSign off later this week (Wednesday Morning?)Meson CenterMagnet replacement beginningBNBSetting up for another testPossibly next weekSlide14

Wilson Hall OutagesLow ImpactTues

day, October 10thPower to Wilson Hall (Entire site except Main Injector, Muon Campus, and Village)From 0700-0730MSS off KRSS backfeedSlide15

Upcoming IssuesIn July 2015 we will need to power the entire site (except the village) off of Kautz

Road SubStation (KRSS) for a year while operatingA new Master SubStation (MSS) will be built beside the old oneWe have the capacity, but don’t know if we can run a Physics ProgramPossible noise on the lines

Expect some problems with the Proton Source

Planned on starting up from the shutdown with the site on KRSS to test

Gives us some time to address

problemsWe don’t know what impact it may have on the rest of the LabWill lights flicker?Will processes be sensitive to the Main Injector ramp?Slide16

When do we test?Met with FESS and AD Departments to discuss possible test dates and impacts to schedules

Met with Division/Section power representatives to confirm test dateLocked in a test starting date – Tuesday, November 4th

The duration of the test will depend on the results

If we can operate, stay on KRSS for some time to allow the Lab to cycle through its normal power usage. Look for an agreeable time to switch back.

If we cannot operate, switch back to using both substations after a few days, apply fixes, regroup, retest

Worked with FESS HV to put together a likely schedule for the rolling power outages across the lab while the power feeds are being configuredSlide17

Rolling Outage Times(Estimated)Slide18

Wilson Hall Power OutagesSaturday,

October 18th – Sunday, October 19thPower outage to Wilson Hall0700 – 1600 SundayWilson Hall closed except authorized personnelRemote Operations Center West (ROC West) availableSaturday

,

November 8

st

– Sunday, November 9thRescheduled from Nov. 1st & 2nd Power outage to Wilson Hall0700 – 1600 Sunday (Last one ~2130 Sunday)Wilson Hall closed except authorized personnelRemote Operations Center West (ROC West) unavailableNeed to perform work impacting transfer switch on Saturday or SundayFurther scheduling and more details required – based on work accomplished this weekFriday, November 28th – Saturday, November 29th Rescheduled from Oct. 20th & 21st

Power outage to Wilson Hall

0700 – 1600 SundayWilson Hall closed except authorized personnelRemote Operations Center West (ROC West) availableCOMPLETEDSlide19

Schedules and Links:Schedule

can be accessed from the Operations Home Page- Schedules -> Operations Schedule Direct link to schedule- http://www-ad.fnal.gov/ops/schedule.html