Download The PPT/PDF document "Schedule 25th April 2013" is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.
Slide1
Schedule
25th April 2013
Christian Irmler (HEPHY Vienna)
C. Irmler (HEPHY)
Belle II – New Collaborators Meeting
Slide2Belle II Schedule
https://belle2.cc.kek.jp/~
twiki/bin/view/Detector/BelleIISchedulePresented by Y. Ushiroda at B2GM March 2013VXD ready by 8/2015VXD Installation 01/2016Physics Run 10/2016
2
Christian Irmler (HEPHY Vienna)
25th April 2013
Slide3SVD construction schedule
http://www.hephy.at/project/belle/belle2svd/schedule/
3
Christian Irmler (HEPHY Vienna)
25th April 2013
MS Project 2010
Considers dependencies between tasks
Need information from collaborating institutes!
Latest version online (
including updates
by Toru)
Slide4Milestones 2013
March: delivery
of Origami & PAMay: mockup evaluation done
mechanical design of ladders and mount blocks finalizedJune:
FADC & FTB & DATCON connectivity testJuly: mechanical design finished
of cones, shell, end flanges and heavy metal shields finished
August:
all parts for ladder assembly must be ready
September:
ladder
assembly
starts
ladder
mount procedure designed
Oct. – Dec. :
preparation of DESY
beam
test
November: SVD readout electronics ready for beam test4Christian Irmler (HEPHY Vienna)25th April 2013
Slide5Milestones 2014+
January 2014: VXD beam test @ DESY
August 2014: all parts for ladder mount must be ready
ladder production should be almost completedSeptember 2014: start of SVD assemblyladder mount
installation of cooling pipes and servicescommissioningtesting, testing, testing, ….
5
Christian Irmler (HEPHY Vienna)
25th April 2013
Slide6Sept. 2014 – Aug. 2015
6
Christian Irmler (HEPHY Vienna)
25th April 2013
August 2015:
SVD should be ready!
Sept. 2014 – August 2015:
~1 year for assembly, commissioning, system tests, …
only little contingency included
August 2015:
VXD (PXD+SVD) delivery
Slide7Responsible persons
Mechanics, Cooling & Services
I. GfallEnd flanges, shielding, support shell S. Tanaka
Electronics M. Friedl
, C. Irmler
Ladder assembly C. Irmler, Y. OnukiL3 Melbourne, G. Taylor
L4 TIFR, R.
Kamesh
/G.
Mohanty
L5 Vienna, C. Irmler
L6 IPMU, Y. Onuki
Sensors
Barrel sensors, HPK
T.
Tsuboyama
Trapezoidal sensors, Micron
M.Valentan
/T.BergauerMockup KEK, DESYThermal mockup C.NiebuhrPrecise mechanical mockup S. Tanaka
SVD
assembly and installation
Procedure, table and tool design T.
Tsuboyama
, S. Tanaka
SVD assembly work KEK, Vienna, (Tata, Melbourne)
tba
7
Christian Irmler (HEPHY Vienna)
25th April 2013
Slide8Responsible persons continued
Beam / system tests coordinationPXD
C. MarinasSVD M. Friedl
DAQ T. HiguchiFTB, data link, copper, DatCon
Cracow, KEK, BejingFTB
W. Ostrowicz
data link K. Hara
copper
T. Higuchi
DatCon
M. Schnell
Software
A.
Bozek
DAQ, Slow control, Run / configuration database
Radiation, temperature, humidity monitoring
T. Tsuboyama
8
Christian Irmler (HEPHY Vienna)25th April 2013
Slide9Thank you
9
Christian Irmler (HEPHY Vienna)
25th April 2013
Slide10Others
Please check the scheduleIf something is missing?
If something is wrong?Any delays / changes?Please tell me
10Christian Irmler (HEPHY Vienna)
25th April 2013