FIS and Generation Commissioning Challenges FIS and Generation Commissioning Challenges

FIS and Generation Commissioning Challenges - PowerPoint Presentation

luanne-stotts
luanne-stotts . @luanne-stotts
Follow
364 views
Uploaded On 2018-03-19

FIS and Generation Commissioning Challenges - PPT Presentation

Chad Thompson Manager Operations Support Reliability amp Operations Subcommittee Meeting ERCOT Public January 7 2016 Full Interconnection Study Identify where and how to connect a resource ID: 656750

issues stability commissioning fis stability issues fis commissioning interconnection requirement constraints ercot generator process gtcs address approved proposed discussion

Share:

Link:

Embed:

Download Presentation from below link

Download Presentation The PPT/PDF document "FIS and Generation Commissioning Challen..." is the property of its rightful owner. Permission is granted to download and print the materials on this web site for personal, non-commercial use only, and to display it on your personal computer provided you do not modify the materials and that you retain all copyright notices contained in the materials. By downloading content from our website, you accept the terms of this agreement.


Presentation Transcript

Slide1

FIS and Generation Commissioning Challenges

Chad Thompson

Manager, Operations Support Reliability & Operations Subcommittee MeetingERCOT PublicJanuary 7, 2016Slide2

Full Interconnection Study

Identify where and how to connect a resourceIdentify risks of interconnection

No TO/RE/QSE requirement to resolve issues identifiedThermal constraints: OKNon-Thermal (e.g. stability) constraints: not OKNo ERCOT requirement to reject if resolutions to issues are not proposed (incomplete)If FIS meets PG requirements, FIS completed, approved, filed, and construction/commissioning ensuesSlide3

Generator Commissioning

Commissioning Plans submitted to ERCOTERCOT coordinates commissioning process

No TO/RE/QSE requirement to notify ERCOT if stability issues are resolvedGeneric Transmission Constraints (GTCs) created to address stability issuesSlide4

Topic for Discussion

ERCOT is observing an increase in generators seeking interconnection that have “unmitigated” stability problems that were identified during the FIS process

Increase in the number of GTCsThese “local” GTCs impact specific generators; not a classical use of GTCsIf this trend continues, management of GTCs may become a situational awareness riskSlide5

Questions for Consideration

Why would/should an FIS be approved if a proposed facility introduces stability issues?Why would/should a generator want to connect with stability issues when it guarantees curtailment?

If an FIS identifies a stability problem, should there be provisions to mitigate, or at least address, the stability issues laid out in the FIS before the generator begins commissioning?What market rules changes are needed to address and strengthen the interconnection process?Slide6

First Steps

Open the discussion at ROSRequest that PLWG be assigned the task of taking this concept in detailReport back to ROS